ILLINOIS POLLUTION CONTROL BOARD
    January 30, 1973
    CITY OF WASHINGTON
    ~72—266
    v.
    ENVIRONMENTAL PROTECTION AGENCY
    KENNETH W. BLACK AND BRUCE BLACK, ON
    BEHALF
    OF PETITIONER
    LARRY EATON, ASST. ATTORNEY GENERAL, ON BEHALF OF ENVIRONMENTAL
    PROTECTION AGENCY
    OPINION AND ORDER OF THE BOARD (BY SAMUEL T. LAWTON, JR.):
    Petition for variance was filed by the City of Washington
    seeking variance from Rule 405 of the Water Pollution Regulations
    which limits effluent discharges to 400 fecal coliform per 1,000
    mg/i of effluent. Petitioner’s present sewage treatment plant
    consists of a primary clarifier, trickling filter and final
    clarifier with effluent discharging into Farm Creek, a tributary
    of the Illinois River. The plant was designed to serve a population
    equivalent of 5,500. The present population is in excess of
    7,500. Since December 2, 1968, new sewer extensions have been
    banned or restricted because of the overloaded condition. Plans
    have been submitted to the Environmental Protection Agency for
    construction of a new
    .75
    MG/D activated sludge plant, a new
    interceptor system and for revisions and modifications of the
    existing plant. The new plant will be located 1.5 miles downstream
    from the existing facility and will include complete treatment for
    average dry weather flow, surge facilities, storm holding facilities
    and chlorination of all flow received.
    The new interceptor system includes a connectiriq interceptor which
    conveys all excess flow from the existing plant to the proposed
    facility. The existing plant will be modified by inclusions of
    aeration basins, tertiary filters and chlorination. Flow to the
    old plant, as modified, will be limited to a maximum of 0.6 MG/D
    Construction has begun and it is contemplated that the chlorina-
    tion facilities for the existing plant will be on line 6 to 8 months
    from the beginning of construction which would presume compliance
    by March 1, 1973 or April 1, 1973, assuming some initial delay in
    commencing construction.
    6
    647

    While the petition and response are somewhat ambigious as
    to precisely what is being sought by this variance,for the purnose
    of this proceeding we assume that the request relates only to the
    installation of chlorination facilities at the existing plant
    which
    will bring the operation into compliance with respect to fecal
    coliform limitations.
    According to the Agency recommendation, effluent from petitioner’s
    present facilities had a fecal coliform as high as 770,000 per 100
    mg/l. This high count is considered by the Agency a consequence
    of the characteristically low flow of Farm Creek. The Agency does
    not believe that the granting of the variance would impose a pollu-
    tional danger to the Illinois River during the period in which the
    variance is soughtfor the installation of chlorination facilities.
    The Agency recommends that the variance be allowed until such time
    as the chlorination facilities are operable and that a bond be posted
    equivalent to the cost of construction of the treatment facilities.
    Hearing was held on the petition. The evidence indicated that
    installation of interim facilities would result in a net cost of
    approximately $40,000 and that the cost of construction on the
    existing facilities was in the amount of $461,451, of which $115,760
    has been paid, leaving an amount owing of $345,691. A letter dated
    September 13 was s~ibmittedto the hearing officer in which a 400-day
    time schedule is proposed for the contract dealing with improvements
    on the existing plant. Hhile the extent of the total work to be done
    may go beyond the time needed to install the chlorination facilities,
    we will assume that petitioner’s initial representation of 8 months
    for such chlorination installation is still applicable and will
    structure our order accordingly. Reference to the record (Page 24)
    suggests the possibility that the 400 days relate to the duration
    of the entire improvement program covering both plants. But again,
    the indication is made on the record that the existing facility will
    be on line in six to eight months at this point with the initial
    time running from June 27, 1972. The record substantiates the con-
    tention that the time involved in constructing interim chlorination
    facilities would not be substantially less than the time needed
    to install permanent chlorination facilities on the existing plant,
    and while some costs could be minimized by the use of the equipment
    in the new facilities, we believe the interests of the community
    and the State are best served by allowing the variance as requested.
    This opinion constitutes the findings of fact and conclusions
    of law of the Board.
    IT IS THE ORDER of the Pollution Control Board:
    1. That the City of Washington be granted a variance from
    Rule 405 (Water Regulations) relative to the limitation
    on fecal coliform emissions in its effluent until April 1,
    1973, at which time the sewage treatment facilities of
    the City will be in compliance with this Regulation.
    —2—
    6
    648

    2. Bond in the amount of $345,690 shall be posted in
    form satisfactory to the Agency within 30 days from
    the date hereof, guaranteeing completion of the
    construction program, with respect to the existing
    plant by August 25, 1973, as stated in the record
    herein.
    Provisions
    shall be made for proportionate
    reduction of the
    bond commensurate with the amount
    paid to the contractor
    pursuant to the contract
    completi~schedulc. Provision shall also be made for
    the forfeiture of $10,000 to the State of Illinois in
    the event the City is not in compliance with Rule 405
    (Water Pollution)
    by April 1, 1973.
    Bond shall be
    filed
    with the Fiscal Services
    Division, Environmental
    Protection Agency, 2200 Churchill Drive, Springfield,
    illinois 62706w within thirty days from the date hereof.
    3. Any extension of this variance or modification of this
    order shall be pursuant to further order of the Board
    upon
    the filing of
    a new variance petition,
    filed a
    sufficient period of time prior
    to expiration of this
    variance to enable apnropriate action by the Board.
    I, Christan hffett, Clerk of the I~1inoisPollution Control Board,
    certify
    that the
    above Opinion and Order was entered on the ~
    day of January, 1973, by a vote of
    to
    ~
    —3—
    6
    649

    Back to top