ILLINOIS POLLUTION CONTROL BOARD
    February 22, 1972
    CHICAGO VITREOUS CORP.
    v.
    )
    1
    71—372
    ENVIRONMENTAL PROTECTION AGENCY
    Opinion of the Board (by Mr. Currie)
    On November 11, 1971, we granted a variance approving the
    air pollution control program of Chicago Vitreous Corp., which
    envisioned control of enamel smelters by December 15 of that
    year (171-241). On November 30, however, the company asked
    for an extension of three months until March 15, 1972 because of
    “an error in judgment on my part in forecasting the completion
    of the project, as well as a delay in the delivery and installation
    of the control system.” Completion of the project according to
    the revised schedule was expected February 7, with a grace period
    to account for any further small delay. Site preparations have
    been and are being done. A letter from the supplier states
    that delays resulted from “the complexity of the circuit con-~
    figuration and the revisions to the system” (letter of Nov.
    22, 1971, from Mr. DePew of Honeywell Inc. to Chicag~oVitreous
    attached to the petition for estension of the variance).
    The Agency recommends that the extension be granted on certain
    conditions. We agree. While we would not tolerate a series of
    small delays that resulted in a substantial lengthening of the pro-
    mised time for compliance, we understand that short delays
    may occur through no fault of the company and that no penalties
    should in such a case be imposed. The expected date for compliance
    has passed, but to avoid the possibility that further problems
    might necessitate still another extension we will extend the date
    as requested until March 15, which allows a small cushion. We
    do not expect to receive any further requests for extension.
    As for conditions, the Agency asks that we require compliance
    with the original order, which we shall do except for the altered
    dates. EPA asks also that we limit production to three smelters
    at any one time during the varinace, but because the Agency
    recommendation was made quite close to the expiration of the 90-day
    period in which we must decide the case, we have no time to ascertain
    the effect of such a provision on the company, and it would not
    be fair to impose it without opportunity to respond. Late Agency
    3
    619

    recommendations make it impossible for the Board to compile an
    adequate record. We agree with the Agency that improved
    monitoring must be instituted at once to prevent incidents such
    as the Agency says occurred on December 7, when neighbor-
    hood complaints resulted. As for the request that we require
    a bond, as in the original case we think the time of the variance
    too short to justify such a requirement; the program will be
    over before the bond could be filed.
    ORDER
    The variance granted to Chicago Vitreous Corp. November 11,
    1971 (#71-241) is hereby extended to March 15, 1972, on the
    following conditions:
    1. All conditions of the original order shall be complied
    with, except that the stack test results required by that
    order shall be submitted no later than April 1, 1972;
    and
    2. The company shall upon receipt of this order
    immediately improve its procedures for monitoring
    the effects of its emissions so as to prevent the
    occurrence of nuisance conditions as required by the
    original order.
    I, Christan Moffett, Clerk of the Pollution Control Board, certify
    that the Board adopted the above Opinion this 22 nd day of
    February, 1972 by a vote of 5-0.
    ~LJ~I ~
    3
    680

    Back to top