ILLINOIS POLLUTION CONTROL BOARD
    March 2, 1972
    NORTH SHORE SANITARY DISTRICT
    #PCB71—343
    v.
    ENVIRONMENTAL PROTECTION AGENCY
    MR. MURRAY H. CONZELMAN and MR. JOHN H. SLOAN appeared for the
    NORTH SHORE SANITARY DISTRICT
    MR. RICHARD COSBY
    and MR. THOMAS W. SCHUENEMAN
    appeared for the
    ENVIRONMENTAL PROTECTION AGENCY
    MR. RICHARD M. KATES appeared for the
    LEAGUE OF WOMEN
    VOTERS
    MR.
    THOMAS H. COMPERE and MR. BERLE
    L. SCHWARTZ appeared for
    the CITY OF HIGHLAND PARE
    OPINION OF THE BOARD (BY MR. KISSEL):
    On January 31, 1972, the Board entered its order in this case
    after consideration of all of the evidence and arguments by the pa:
    ties: The North Shore Sanitary District (“District”), the Agency nd
    the League of Women Voters (“League”)
    .
    Although the order must,
    of course, speak for itself, generally it granted the District a
    variance to permit the connection of 1,000 living units (4,000 Pop
    lation Equivalents) on certain conditions. On February 10, 1972, the
    District filed a “Petition for Reconsideration and Rehearing” with
    the Board in which it objected to the following paragraphs of the
    January 31, 1972 order, and here seeks to have those orders modifI ~d.
    2. “The District shall be permitted to add a total of 100)
    living units or 4000 P.R. to the sewers tributary to the
    Clavey and Waukegan plants.”
    14. “The District shall install disinfection facilities ~:
    the Water Street and Gillette Avenue Sewers. Within 45 days
    of the entry of the order, the District shall present a time-
    table for the installation of such facilities to the Agency an
    the Board. The Agency shall formulate a written response to t
    Board within 15 days of receipt of the District timetable. Tt
    Board shall then issue an implementation schedule.”
    Its objections to the quoted paragraphs were nuxnerous~
    3
    697

    1. The District would not realize sufficient revenues from
    the 1000 living units to finance the various interim
    improvements required by the Board in previous orders,
    including the January 31, 1972 order and particularly
    the requirement for interim chlorination at the Water
    Street and Gillette Avenue Bypasses;
    2. The issuance of only 1000 permits precludes developers,
    contractors and others engaged in the Lake County housing
    industry from proceeding with concrete commitments for
    construction in the upcoming years; and
    3. The chlorination facilities required by the Board would
    not insure the use of the beaches in 1972 and 1973.
    The League filed a brief with the Board suggesting that the Board
    grant the variance for 5000 units on condition that the District
    expedite the construction of the Waukegan retention basin, and com-
    plete it by June 1973. The League’sposition was that if the
    retention basin would be completed by that date, or soon thereafter,
    there would be no need to require the disinfection facilities
    at the Water Street andGillette Avenue overflows. The Agency
    recommended that the Board not grant the additional variance
    requested by the District.
    As a result of the District’s motion,
    a public hearing was held before the entire Board on February 22,
    1972 at the Board’s office in Chicago, Illinois. At that hearing,
    the City of Highland Park sought leave to intervene in this case;
    the City’s motion was objected to by each of the parties on the
    ground of lack of proper notice. Opposing counsel were given five
    days to respond to the City’s motion. The City remained, at the
    hearing and was afforded an opportunity to present its position
    for the record. After receipt
    of the arguments of opposing counsel,
    the Board agrees that the City of Highland Park
    should be added
    as a party to the case.
    The Board has considered motions made by other parties in other
    cases for reconsideration of the Board’s order against them. We have
    consistently taken the position that we will not reconsider our
    initial decision unless there is a significant change in the circum-
    stances, or there is new evidence available after the hearing which was
    not available at the time of the hearing. We think that both of those
    circumstances exist in this case.
    The
    order of January 31, 1972 was predicated on the Board’s con-
    clusion that granting of the variance under the conditions detailed
    in this order would actually improve the quality of the water of Lake
    Michigan, and that had the variance not have been granted, (and therefore
    the conditions are met)
    the
    Lake wouI~Thave continued to show signs
    of bacterial contamination near the beaches located within the District’s
    bounds. One of the
    most important conditions of the variance was,
    therefore, “paragraph 14” which required disinfecting of Water
    Street and GilletteAvenue bypasses by September of 1972. If met,
    this would have meant that for part of the 1972 and all of the 1973
    bathing season, the bacterial contamination from the overflows would
    have been substantially
    reduced and the beaches within the District
    most likely would have been useable during those periods.
    In its motion
    3
    698

    ;i r.o:o:
    ~.
    i1e~
    ~:::~rictcb;e:;’.ed
    to
    caragi
    oph t.4” on a number
    (LO.
    05. 7 OL j~15~
    ~dtLLVeS COOS
    (.tsrnd
    by rho
    Board before
    T:~cL .j~~nuaroI .;rcwr
    .
    arc: now favcyed by the District, was
    ~ooct. :~:~a
    chlorine
    r.Lor,
    ~.t rhf. Wabor Street and GIllette Avenue
    ~
    ~
    we..~ crib:
    I
    r~e
    i&;ent3cr~ 5asz~ at ~aukegan
    plant
    lb aro~ ~oi-aii~.
    no ~hct at. couid handle the overflows,
    and treat
    r.enocs I.
    t ‘sos ce~.met:
    bc do. Tut based upon the evidence in the
    •:n: ir~!-:rtI
    he.ar:LrLu,
    ahe lntLcr was not: a feasible alternative
    at that tine
    boc~~~cof abe tie t~rict’
    :5 si stcro of
    delay in completing not only
    ci sf sts oro-~arts
    ,
    but this r:o~uct
    Jo particular.’
    if the “reten—
    son ~
    :~ltcroatavc nod
    been
    the
    one selected by
    tao Board in its
    iu:iny 31
    order, disinfection of one cverfiows
    would not have been
    occvtded
    untis ar least September,
    1973
    and perhaps later, knowinci
    Lh.:: t:~s Cistrich
    had
    a nor
    coano for I~1ay in completing its projects.
    in thr’
    hearing on abe
    Motion for Reconsideration,
    the District’s
    en t:o ccu:piet on of
    the
    “rateotaon
    casIo” pro300t
    was strongly
    Tue District: has
    actually awarded the contracts for the retention
    and
    for th~:
    sttendant
    oumping facilities
    since the original
    bearing on the I.
    ~:
    rariance no sr tion.
    The contract provides for
    c::’mpiatlon date ~or cii scsi:
    faciiat~os of September 1, 1973, which
    the Dastrict testified
    at would reguire be met.
    Further, it may also
    be
    possible to advance that completion date by declaring the retention
    oasis
    pro~ecb. at:
    Waukecan
    an ‘emergency project’, as t has done in other
    other cases,
    Since the installation
    of the retention basin and the pump-
    ing faciliti.’
    basically determines whether or not Lake Michigan bathing
    can occur
    in
    197:3, we believe that cause exists for the use of the
    Distrtct’s
    ‘emergency” declaration
    power. One
    way
    of
    completing the
    project earlier would be for the District to employ overtime whenever
    that will speed up work.
    Another way of speeding up would be the
    leasing of
    the
    necessary pumps and using
    them
    before
    tire
    installation
    of the permanent pumps. We will require, therefore, that the District
    complete the retention
    basin no later than Sept. 1, 19732 and
    investigate
    all means available to speed up this project,
    including
    the availability
    of leased pumps, and toe use of overtime work, and
    report to the Board and the other parties the results of its investigation,
    the manner in which it intends to proceed, and the reasons therefor.
    Even given the availability
    of the retention basin and the atten-
    dant facilities
    by the end of the summer, 1973, the Board believes that
    disinfection
    of the Water Street and Gillette Avenue bypasses would
    have been the most appropriate measure to be taken.
    Unfortunately,
    the evidence presented at the recent hearing indicated that disinfection
    facilities
    could not be installed
    by September, 1972 as originally
    forecast.
    prospects are also dim for installation
    by summer, 1973, the
    next bathing season.
    In order to install the disinfection
    facilities
    at the Water Street bypass, the District would have to acquire rights
    from E.J.&F.. Railroad.
    Under the Eminent Domain Act, this could
    not be done without prior approval from the Illinois
    Commerce Commission:
    i-The original contemplated completion date was March, 1973, and
    the contemplated date now ~s September 1, 1973.
    2The League has asked us
    to
    recuirs: a completion date of June 1973.
    hut based
    upon the present record on do not know
    if this car, be done,
    we
    agree with the League that all sccns an the tiOtrict’s
    disposal should
    be used
    to speed
    up the Project and ~: after .tnvestiqation the June
    dote can be met, we will
    require it.
    3
    699

    cwo proceedings, one before the Commerce
    Commission and
    then a condemna-
    tion suit, would most likely have to
    occur
    ti-ien before the District could
    obtain the necessary right—of—way.
    A seven-’rnonth construction
    period
    would then be pyramided on top of those hearing processes..
    The water
    Street project therefore appears to be effectively
    stymied.
    If
    that is the case, then to chlorinate
    at Gillette
    Avenue will make
    little
    sense since with Water Street still untreated,
    a large amount
    of untreated sewage will still be cascading into Lake Michigan wheb
    overflow conditions occur.
    Therefore,
    Paragraph 14 of the Board
    order of January 31, 1972 will be rescinded;
    instead,
    the District
    will be ordered to take the steps outlined above to advance the avail-
    ability date for the Waukegan retention
    basin, the pumping station, and
    the interceptor
    and relief sewer.
    While Lake Michigan will suffer
    for a few more months under this new Order, the people of the county will
    not he required to waste their money on a useless,
    and maybe, never
    available project.
    At the recent hearing,
    the District also objected to the Board’s
    limitation
    of 1000 hookups (4000 P. E.) to the Clavey Road and Waukegan
    Sewage Treatment plants. In support
    of this contention, the District
    indicated that
    it would not receive sufficient revenues from the 1000
    permits granted to finance the
    improvements which the Board had ordered
    because
    the grant of only 1000 permits would preclude developers, con-
    tractors and others in the housing and building industry from proceeding
    with concrete conirnitmen~s for construction in 1973 and 1974. Though
    the District’s
    first argument has been somewhat obviated by the Board’s
    rescission of its order directing that disinfection take place at the
    bypasses (because the disinfection facilities involved a large part of
    the cost)
    ,
    the
    second contention still remains a
    matter for concern.
    At the recent hearing, the District introduced new evidence regarding
    the need for 5000 permits.
    Allan Pickus, a Waukegan architect and
    contractor, indicated that scheduling and financing of projects requires
    that preparations
    be made several years in advance. Thus, for the
    lifting of this sewer ban to have any beneficial
    economic effect,
    the
    District would require that a sufficiently
    large number of
    permits be
    granted so that construction
    can proceed at an appropriate
    pace.
    This is necessary because builders need
    to obtain financing for the
    total construction
    project,
    be it an apartment house, or private homes,
    so that the costs common to the entire project, i.
    e., roads, sewers,
    etc. can be done at once and amortized over the entire project. Without
    the firm commitment to connect the entire construction project, builders
    could not risk the funds for the common costs. Pickus’ testimony was
    corroborated by that of Thomas A. Rostron, President of the First Federal
    Savings and Loan Association of Waukegan, who stressed that developers
    must be assured that sewers will be available at the conclusion of a
    project before they can commit capital toa building program. He
    in-
    dicated that no lending institution would make a mortgage commitment
    unless there were written approval from the Board as to the availability
    of sewer hookups. Based on this new evidence, the District shall have
    the power to issue 5000 living unit (20,000 P.E.) permits for the
    Waukegan and Clavey Road plants. Just because the Board authorizes
    the issuance of 5000 permits does not mean that such connections will
    occur within the next year; as Pickus indicated, actual connections
    to the plants will most likely total
    between 700 and 1000 the first
    3—
    700

    year, with approximately 2000 occurring ih each subsequent year.
    Of
    prime consideration
    in limiting the original grant to 1000 units was
    the Board’s desire to maintain a continuing supervision over the Dis-
    trict’s
    expansion program.
    Placing the limitation
    at 1000 would force
    the District to return to the Board at the end of that first year in
    order to renew the variance; at such a time, the District
    would have
    to show substantial
    compliance with the deadlines under their construc-
    tion program.
    Raising the level to 5000 does not preclude the maintenance
    of such supervision, sinpe in order that advance
    planning can take place
    for construction year 1975,
    the District will most likely have to
    return to the Board in about a year for a renewal of its variance.
    If the District is not
    complying with our Order, or proves that it
    has
    not exercised all good faith in trying to comply, new variances should
    not be granted in the future beyond those granted today. In addition,
    through the District’s
    monthly progress reports,
    the Board and the
    Agency will continue to be apprised of the District’s
    activities.
    It is important to note that the granting of a variance for 5000
    living units is essentially
    the same grant as previously made by the
    Board on January 31. In the January 31 order, the Board
    granted a variance for 1000 units for the next year,
    recognizing that
    if
    the District met its schedule,
    it
    would receive per-
    mission to connect additional living units in the next year, probably
    2000 such units, and so on. With the present grant of 5000 units, the
    testimony is that not more than 1000 units will be connected in the
    first year anyway. What the Board is really doing is to give the
    builders the wherewithal
    to build the 1000 units this year.
    Under
    the January 31 order, the manner of apportioning the 1000 unit allotment
    was left to the discretion of the District.
    Since 5000 units will
    ultimately be connected to the District system under this variance,
    however, we must now take into account the relative capacities of the
    Clavey and Waukegan plants.
    Accordingly, the District shall apportion
    the loadings under this variance in the approximate one—third to Clavey,
    two-thirds to Waukegan ratio proposed by
    the District in its original
    variance request in this case.
    One other point must be mentioned
    ---
    the District’s
    financial
    problems. Testimony at the
    hearing established that the value of
    the
    appraised real estate in the District had increased by 150 million
    dollars
    since the voters in the District had passed the original 36 million dollar
    bond issue in 1968. This increase
    in assessed valuation makes 7.5
    million dollars available to the District for its programs.
    Such funds
    are available within the five percent bonding limitation imposed on the
    District under Sec. 285,. Ch. 42,
    Ill. Rev. Stat. (1971)
    .
    At present,
    the District is committed to a large—scale construction and expansion
    program. Those
    facilities are being constructed in order to abate pollu-
    tion. (See Opinion, PCB7O—7, 12, 13 and 14, March 31, 1971)
    .
    The
    facilities ordered in this variance case are also directed to abating
    pollution (See opinion PCB71—343, January 31, 1972).
    To comply with
    such an order, the District is authorized by Section 46 of the Environ-
    3
    701

    mental Protection Act to issue general obligation
    or revenue bonds, if
    necessary,
    without referendum.
    No specific order to issue bonds is
    necessary; we leave the question of how to raise money to the District.
    but the money must be raised.
    See Ruth v. Aurora Sanitary District,
    17 Ill.
    2d 11, 158 N.E. 2d 601 (1959).
    The parties
    entered :into a stipulation
    regarding certain matters
    and •the League has asked that the Board make the stipulation
    part
    of the Board’s order.
    The stipulation, inter alia, would provide
    for operation of interim
    chlorination facilities at the North
    Chicago plant during the 1972 swirnminq season, for ample notice in
    the District and to
    contractors regarding the district’s
    bidding
    processes,
    and
    for the adoption of a fine schedule by the
    District.
    Such steps, we believe will assure better operation
    and a higher quality effluent,
    as well as possibly advancing the
    completion date for the District’s
    expansion program.
    The stipulation
    shall
    be incorporated into the Board Order.
    -ORDER-
    Upon examination of the record, the Order of the Board of
    January 31, 1972 in the ‘above—entitled case, PCB 71—343, granting the
    North Shore Sanitary District a variance from Paragraph 7 of the
    Order of the Board in the case of the League of Women Voters, et al
    v. North Shore Sanitary District, PCB 70-7, 12, 13 and 14 is hereby
    modified as follows:
    1. Paragraph 2 of the Board Order of January 31, 1972 is
    hereby repealed in full and replaced as follows:
    2. The District shall be permitted to add a total of
    5000 living units or 20,000 P.E. to the sewers
    tributary to the Clavey and Waukegan plants.
    2. Paragraph 4 of the Board Order of January 31, 1972 is
    hereby repealed in full and replaced as follows:
    4. The District shall apportion the allotment under the
    variance between the subject plants in approximate
    ratio of one—third of the new connections to Clavey,
    the remainder to Waukegan. Such apportioni~ent shall
    also be subject to the conditions in Paragraph 5 below.
    3. Paragraph 14 of the Board Order of January 31, 1972 is
    hereby repealed in full.
    4. The following paragraphs are hereby added to the Board Order
    of January 31, 1972:
    21. The District shall have the retention basin at the
    Waukegan plant (P3B)
    ,
    the pumping station (P3F), and
    the interceptor and relief sewers (S6A) (hereinafter
    called “retention basin”) tributary
    to the basin in
    operation as soon as possible and no later than Septem-
    3
    702

    her 1, 1973.
    The District
    shalL employ all means avail-
    able to advance the date of operation of the retention
    basin.
    The District shall investigate
    all available
    means to advance the date of operation of the retention
    basin, including the use of its emergency powers, over-
    time
    and leased pumps. Within
    60
    days of the entry of
    this Order, the District shall begin reporting in its
    monthly progress reports to the Board,the Agency and
    the
    other parties in this case, the results of its
    investigations,
    the steps it has taken to
    advance
    the
    operation date, the manner in which it intends to
    proceed, and the reasons therefor.
    Such reporting
    shall be included within each monthly progress report
    until the date of completion of the retention basin
    report.
    22,
    The District
    shall abate its discharge of untreated or
    inadequately
    treated sewage and its violations
    of the
    Environmental Protection Act and of regulations
    thereunder,
    in accordance with this Order and the Board Orders of
    January 31,. 1972, June 23, 1971 and March 31, 1971.
    23.
    Within 90 days of the entry of this Order, the District
    shall submit to the Agency and the Board a plan assuring
    financing of the program herein and heretofore
    approved,
    together with a study by bond counsel discussing
    the various
    financing alternatives
    available.
    5. The following stipulation
    is hereby incorporated, into the Board
    Order of January 31, 1972:
    24.
    Within sixty (60) days from the date of this Stipulation,
    the North Shore Sanitary District will adopt a fine schedule
    to a certain Ordinance relating to sewers and sewer
    systems as amended.
    25.
    That the North Shore Sanitary District will take whatever
    legal steps
    are necessary in the matter of illegal
    connections to its systems and facilities.
    26.
    That the North Shore Sanitary District
    will study the
    toxicity
    of polymers it plans to use by making a study
    of the literature
    and report its findings to the Illinois
    Pollution Control Board.
    27. That in connection with the interim chlorination
    facilities
    at its North Chicago Plant, the North Shore Sanitary
    District will install and operate such facilities
    for
    the swimming season of 1972.
    28. That the North Shore Sanitary District states that it
    ;
    advertises for bids on construction contracts in the Waukegan
    Nev~’s-Sun and notifies the
    Dodge Reports. That in addition
    it furnishes notices to contractors.
    3
    ‘03

    29. That a pilot study of ozone may be done at a plant
    approved by the North Shore Sanitary District
    if
    done
    by the Illinois
    Institute
    for Environmental Quality or
    other governmental agency so long as such study does not
    interfere
    with construction.
    30.
    That the North Shore Sanitary District will file its
    impact study of a sludge disposal site in Newport Township,
    Lake County, Illinois
    with the Federal Environmental
    Protection
    Agency as soon as a permit is issued by the
    Illinois
    Environmental
    Protection Agency.
    6. All other conditions
    of the variance granted on January 31,
    1972 in this cause shall remain in full force and effect.
    I, Christan Moffett, Clerk of the Illinois Pollutoin Cont~1. Board,
    certify that the above Opinion & Order was adopted this day of March
    1972, by a vote of
    9-c
    ~‘t4;L&v~~,
    I
    3
    704

    ILLINOIS POLLUTION CONTROL BOARD
    March 2, 1972
    NORTH SHORE SANITARY DISTRICT
    v.
    )
    PCB 71—343
    ENVIRONMENTAL PROTECTION AGENCY
    Concurring Opinion by Jacob D. Dumelle
    While I concur in
    the
    Board’s decision to grant 5,000 connec-
    tions as it did this date I do not agree with all the language of
    the March 2, 1972 opinion.
    In my dissent filed February 17, 1972 to the original January
    31, 1972 Board order granting only 1,000 connections I fully explored
    my reasons. Those reasons still hold and I shall not repeat them
    here.
    I do not feel that the “new evidence” mentioned in the Bo~d
    opinion (p.4) was needed or necessary. I think that our exten~ive
    sewer ban hearings plus the instant case proceedings fully developed
    the material for the conclusions reached.
    The
    distribution of the connections between the Waukegan and
    Clavey plants in the 2:1 ratio is not one I would have made. The
    Clavey plant’s effluent has been of such good quality
    that I
    would
    have reversed the ratio or made an unlimited grant at Clavey subject
    to the effluent stanc ~rd for secondary plants not being exceeded.
    ~/
    r\~/
    If.,!
    /
    /
    \/~//~~
    th~-b2~_
    / ____________________________________________
    ./
    ,Jacob D. Dumelle
    /
    /Board Member
    I, Christan~~.Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify the above Concurring Opinion was filed on the
    .~2//~dayof March, 1972.
    Christan L. Moffe’~t~4Clerk
    Illinois Pollution control Board
    3
    705

    Back to top