ILLINOIS POLLUTION CONTROL BOARD
February 3, 1972
LAKE
COUNTY DEPARTMENT OF
)
PUBLIC WORKS
v.
)
PCB 71—337
ENVIRONMENTAL PROTECTION AGENCY
Mr. Lawrence S. Bloom, appeared for the Petitioner;
Mr. Lee A. Camtbell, Assistant Attorney General, appeared for the
Respondent
OPINION OF THE BOARD (by. Mr. Dumelle)
On October 28, 1971 the Lake County Department of Public Works
(hereafter Department) filed a petition for variance seek4ng a waiver
of one of the special conditions established in a permit3-~ issued by
the Environmental Protection Agency (EPA) to the Department for the
Department’s Vernon Hills Sewage Treatment Plant (Vernon Hills
STP). The Department sought to be relieved from complying with the
permit requirement for clarification and chemical treatment following
tertiary lagoons.
We grant a variance for one year, until January 23, 1973 subject
to several conditions.
A new sewage treatment plant is to be in operation for the area
now served by the Vernon Hills STP by August of 1973 (R. 29). The
present plant will then be abandoned. After August of 1973 the
Vernon Hills STP will be serving as a lift station to transport wastes
to the New Century Town Sewage Treatment Plant. The permit applied
for in this case was to enlarge the existing plant to accommodate
the additional population load up untill the time that the new plant
1 Permit Number l971-~B—4O3
“Special Condition. This permit is issued subject to the condition
that the owner/operator shall submit plans and specifications within
four weeks of the date of this permit to provide for final clari-
fication with chemical coagulation following the two cell lagoon,
in accordance with the latest policies and technical requirements
of this agency.”
3
—
601
is in operation. The Department, on ~1ay 11, 1971 submitted plans
for the use of a temporary portable plant until the new plant is on
line. The expansion was to be accomplished with the use of four
modular units handling 50,000 gallons each (R. 53). A permit was
granted bn July 13, 1971 which approved the submitted plans and
added the special condition for clarification by chemical trtatment
which is the subject of this variance request.
The equipment called for by the special condition was necessitated
by a new technical policy statement issued by the EPA in July of
1971. The added requirement came into existence some two or three
months after the Department had applied for a permit to operate the
temporary facilities. The special condition requirement related to
removal of algae. The algae growth represents a problem for about
three months of the year at the end of the summer season (R. 45).
For the remaining months there would be no need for the chemical
clarifier
(R. 45-46). There was testimony that had the Department
known of the new requirement before they start~ed on their expansion
plans by excavating the lagoons they would have likely opted to
install mixed media filters instead of the lagoon system. The
special condition was a requirement for the Department to change
courses in midstream.
Compliance with the special condition
will add a substantial
expense to the temporary plant.. In making
our decision the fact
that the facilities required to meet the special condition of the
permit were of a temporary nature weighed heavily.
In little more
than one year the need for the additionally required treatment will
surcease. Meanwhile an increment of one—third of the cost of the
temporary
plant will have been added to the estimated cost of the
temporary facilities.
Mr. Robert J. Degan, Directof of Public Works
for the Department testified that the cost of engineering and con-
struction of the temporary plant, exclusive of the special condition
requirements, was $206,064 (R. 26). The cost of the chemical clarifier
required by the special condition would be approximately $65,000.
On the record facts we find that the special condition require-
ments impose an unreasonable hardship on the petitioner. Further
since the algae growth will potentially be a problem for cnly about
three months of the.year we find that there will not be such a
significant detriment to the environment to not allow the operation
of the temporary plant without the special condition requirements.
The evidence showed that the effluent from the temporary plant as
regards BOD and suspended solids will very likely be of such a quality
as to exceed the quality of the receiving stream. The plant effluent
was characterized as meeting the applicable standards of 4 mg/i BOD
and S mg/l suspended solids (R. 5). The receiving stream~ Seavey
Ditch, was sampled and showed concentrations of 22 and 19 mg/i ROD
and 5 and 12 mg/l suspended solids (R. 14). ‘The 22 mg/i BOD and
5 mg/l suspended solids were samples taken upstream from the present
plant and would not be a reflection of the character of the present
plant effluent. With the use of the temporary plant ~which is expected
to be operational in February 1972 (R. 46) the quality of the
eceiving ditch should improve.
3
—
602
We have a precedent for granting a variance in a case such as
this where it is requested that a governmental body operate a
sewage treatment facility at variance with the regulatory require-
ments on a temporary basis while permanent improvements are being
made. In The Metropolitan Sanitary District of Greater Chicago v.
EPA, PCB 71-166, (September 16, 1971) we allowed the operation of
?he
District’s Orland Park plant until permanent adequate facilities,
a new interceptor sewer, could be constructed which would lead to
the abandonment of the plant for which a variance was asked. There,
as here, it was demonstrated that no permanent ecological harm would
occur in the receiving stream.
We therefore grant the variance subject to the conditions that
the Department complete construction of its tertiary lagoons by
February 1972; that the Department abandon the Vernon Hills
STP as a treatment facility after the ~ Century Town plant is
in operation and; that the Department submit quarterly reports to
the Board and the EPA on the~rogressto date.
One final note, there was some considerable record discussion as
to the commencement of the ninety day period by which this Board must
make a decision on the instant variance request. Our rule states
that “A variance proceeding shall be commenced by filing a petition
for variance with the Ag~ncyand by filing ten copies of the petition
with the Clerk of the Board.” (Pollution Control Board Regulations
40. (a), emphasis added). The instant request was filed with the
Board on Oôtober 28, 1971. The clock started running on that date.
This opinion constitutes the Board’s findings of fact and,:con-
clusions of law.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the Board adopted the above Opinion on the~~
day of February, 1972 by a vote of ~
Christan L. Moffett; erk
tllinois Pollution Control Board
3— 603
S
S