1. ORDER
      2. 2. Incinerator shall properly maintain the operating
      3. 3. The period of this variance shall be eleven (11)
      4. 4. Incinerator shall post a bond guar&nteeing the

ILLINOIS POLLUTION CONTROL BOARD
Novembur 23, 1971
Environmental Protection Agency
)
)
)
V.
)
PCB
71—324
)
)
Incinerator, Inc.
)
Mr. James I. Rubin
and
Mr. Melvin A. Ret! f, Assistant Attorneys
General, on behalf of the
.
Environmental Protection Agency
Mr. Richard V. Noupt
and
Mr. Dennis 3. Eslick, on behalf of
Incinerator, Inc.
Opinion of the Board (by Mr. Rissel):
Originally, this action was brought by the Environmental Pro-
tection Agency (“Agency”) against Incinerator, Inc. asking for a
cease and desist order and penalties to be assessed against .uncinera—
tor for the operation of a refuse incinerator in Cicero, Illinois,
in violation of the Environmental Protection Act and
the Rules
and
Regulations promulgated thereunder. After hearings, this Board
entered an order
on September 30, 1971
which provided, in substance
that
.
Incinerator not operate its facility in Cicero until it had
installed an intetim control system to abate the nuisance which it.
had been causing in the neighborhood, until it repaired the thermo-
couple devices in the operation of the incinerator, and until it
had filed a petition for variance which would contain a fin program
for the installation of equipment to bring the facility into com-
pliance with existing Illinois standards. Incinerator appeared
before the Board on October 12 (pursuant to a motion filed on October 6)
and asked for a stay of the original order entered by the Board and
for a rehearing because of the hardship imposed by the order. After
consideration of the arguments, the Board entered an order on October 14,
1971, staying the original order in respect to the cease and desist
order, and the penalty to be paid. This order did, however, require
operation of the incinerator at a maximum capacity of 250 tons of
refuse per day at a certain moisture content, and
also required thc..t
a hearing be held on November 1, at which time Incinerator was to
prove that restricted operation of its facility abated, or “substan-
tially alleviated” the nuisance conditions found by the Board. Pur-
suant to that order the last hearing was held before George P; Sullivan,
Bearing Officer.
3— 167

As required by the last order entered by the Board, the first
issue which we must decide at this tine is whether Incinerator
is
still causing a nuisance even at
the
reduced operbtion of the plant
between October 12 and November 1. A review of the November 1
record indicates some dispute on the severity of
the
emissions from
the Incinerator facility. On the one hand, witnesses testified that
there was~“still soot in the~air” (4)
,
there was fly ash on the
ground (25—6), and that there was heavy smoke coming from the plant
on two days in Octoh~r (the 15th and the 18th). Other witnesses
sthted~that the fly~ash caused no particular problem. In fact,
Incinerator-cir~ul~ted~apetition which was to that effect and the
petition was signed by a number of people Above all the d~spute,
however, we can find agreement on one thing: Since the limitation
of operation, repair of the spray syst~mby Incinerator and repair
of the thermocouples (all of which was accomplished by Incinerator
in compliance with the last order of the Board), the facility has
caused less of a problem than it had before Octohe~ ±2 One wit-
ness said that the emissiOns “weren~tas heavy as normal”, but of
course admitted that they were “still there” (10). From the testi-
mon~t, including that di an expert who conducted a “windblown
particles” test around the plht~t, it is quite clear that the reduced
operation with the improved sprays and repaired thermocouples has
had a beneficial effect on the emissions from the plant and in the
opinion of the
Board no lor1uex xisLitu~cs a xiuiaanre ar Lha~des~
cribed in the original hea~ing and opinion of the Board,
Yes, the
neighbors are still affected by the emissions, hut the effect on
them is not so great as to require a compl~te shutdown of the
facility which was the Board~s original order. In effect, by the
operation as it is presently done, Incinerator has met the Board’s
original order for redi~cingthe nuisance. For it was the Board’s
original intent to keep the facility closed only until the nuisance
could be abated. It was not the intent of the Board to close the
facility until complete installation and operation of the ultimate
control equipment.
Having decided that Incinerator can operate its facility,
there will be a requirement that it be operated only within the
confines of the previous order of the Board. It is anparent that
the limitation
on the tonnage consumed by the incinerator each
day, the properly operating thermocouples and the new spray equip-
ment are the reasons that the present nuisance has been abated.
We will require that Incinerator operate its facility consuming
not more than 250 tons of refuse per day, that the sprays be kept
in operating order, that the refuse not contain more than a 20
moisture content, and that the thermocouples be kept operational.
3
168

In addition, we will impose the general conditions that the incin-
erator generally be kept in good operating condition, and that it
be well operated during the period of the variance.
If the sole question before the Board was whether to grant
a variance without limit on the conditions that have been previously
discussed, it would not be granted. One of the principle reasons
for granting the variance here is that Incinerator has agreed to
install control equipment within the next year which will bring
the entire facility into compliance with the law. Without that plan,
there would be no basis for granting the variance. Incinerator’s
new plan
--
namely, the installation of a high energy Venturi scrub-
ber on one of the incinerators
--
will, according to the undisputed
testimony, allow the incinerator to meet a standard of 0.1 grains
per standard cubic foot, dry. This standard is in fact less than
the Illinois standard which would require an emission of not more
than 02 grains per standard cubic foot. Between the time of the
first hearing and the last one, Incinerator has modified its program
for t~hebetter. Certainly the cost will be higher (the cost of the
present plan will be $1 million) for the planned emission control
equipment, but the time will be longer as well. The uncontradicted
testimony was that it will take nine months from the time of award-
ing contracts to install the facility. Before awarding of the con-
tracts, at least two months will be needed to prepare the bids,
get the permit and generally make ready for the construction. For
what is ~o be gained we do not think this is an unreasonable amount
oftime. We will therefore grant the variance for a period of
eleven months from this date upon the conditions recited above and
others imoosed in the order.
While the operation of the incinerator has lessened the particu-
late emission during the period beginning with October 12, the evidence
did show that the incinerator was operated at a tonnage input of less
than 250 tOns ~perday. ~ We do allow Incinerator by this order to
operate its facility atan input of up to 250 tons per day and we are
not convinced that operation of the facility at the 250 ton per day
level will not cause a nuisance to the neighbors. We feel, therefore,
that the Agency, after consultation with the neighbors, should be able
to open up these proceedings after six months of operation (May 23, l972~
if necessary, because of a possible nuisance condition created in the
neighborhood. If petitioned by the Agency~the Board will, if the Agency
petition is adequate to so demonstrate, hold a hearing on whether the
facility should be controlled or even shut down again. The importance
of a six-month period is that it will allo~ireview after a significant
period of operation and will allow us to look at the matter before the
lii An Agency investigator testified that the incinerator burned
between 77 and 226 tons per day during the month of October.
3
169

suimner
period
of 1972. In addition to the possible re-review of
the case, we also believe that Incinerator should look at the
feasibility of control equipment to catch some of the large particu-
late matter being
emitted from
the stack. Incinerator should con-
sider the installation of screening of some kind. The report will
be required in thirty days.
This
opinion constitutes the findings of fact and conclusions
of law of the Board.
ORDER
Upon
consideration of the evidence
and
the exhibits, the Board
hereby grants to Inciaerator, Inc. a variance from the existing laws
and regulations to operate an incinerator in Cicero, Illinois, under
the following conditions:
1.
Incinerator bhall dutifully
and
diligently operate
only one incinerator
unit
at its plant
and
that
unit
shall not be operated at a capacity in excess
of 250 tons of refuse
per
day at a moisture content
of not more than 20.
2.
Incinerator shall properly maintain the operating
incinerator, including the thermocouples and the
spray devices. Particularly, the mentione4 de-
vices
shall be operational whenever the incinera-
tor is in operation.
3.
The period of this variance shall be eleven (11)
months from the date herein.
However, if te
Agency shall so petition after May 23, 1972, the
Board shall hold a public hearinq on whether the
operation of the incinerator has caused a nuisance,
at various levels of tonnage input, to the neigh-
bors. The Agency shall, if
it petitions the Board,
set forth the alternatives to be consider~dby
the
Board
for abating the nuisance
“The
Board,
then, shall
make
such further’ order at that.
time
as the Board deems necessary under the circum-
stances.
4.
Incinerator shall post a bond guar&nteeing the
installation of the control devices ordered herein
and other conditions stated,herein in a form
approved by the Agency in the
amount
of $300,000.
3—170

5. By the end of the variance herein granted, Incin-
erator shall have installed and operating a high
energy Venturi scrubber of the type described in
the transcript of proceedings so as to limit the
emissions from the Incinerator facility to 0.1
grains per standard cubic foot, dry.
6. Incinerator, shall within thirty (30) days submit
a written report to the Board and the Agency on
the feasibility of installing interim devices,
i.e., mesh screening in the stacks, for capturing
the large particulate matter being emitted from
the stacks. The Agency shall file comments on
the report with the Board within ten (10) days
after Incinerator has filed its report. The Board,
after receiving both reports, shall make such
further orders as it shall deem necessary under
the circumstances.
I, Christan Moffett, Acting Clerk of the Illinois Pollution
Control Board, certify that the Board asooted the above Opinion
and Order on this
.~ .~
day of November, 1971
Christaii
,//7
Môfiett,
~
Acting Clerk
3
171

Back to top