ILLINOIS POLLUTION CONTROL BOARD
January 6, 1972
MOLEX, INC.
v.
)
#
71—200
ENVIRONMENTAL PROTECTION AGENCY
)
Opinion of the Board (by Mr. Currie):
Molex’s petition, filed in June 1971, asked a year’s
variance from the particulate air contaminant emission
regulations to permit operation during installation of
scrubbers to control organic emissions from its plastics
plant in Brookfield. We grant the request subject to several
conditions for reasons indicated below.
Molex received letter—of—intent forms from the old
Air Pollution Control Board in 1967, specifically nOtifying
the company of its obligation to submit process emission data
and to file a program for bringing its operations into com-
pliance. By its own admission the company did nothing about
it until 1970, when it began looking for a solution. The
present petition, filed four years after the letter of intent
was required, was the first attempt to establish a control
program.
The plan envisions installation of two scrubbers that
will allegedly reduce emissions by 95. The Agency has issued
permits for the equipment, finding it adequate to meet the
emission standards. Construction cannot begin until Cook
County also gives a permit, and the County had at the time
of the hearing refused to do so because it wanted assurance
that excessive odors would not continue after the scrubbers
were in operation.
The company at the hearing November 22 said that nine
months would be required to complete the installation. As
the Agency demonstrated through company witnesses, however,
this schedule is based upon installation of the scrubbers
one at a time. By putting both in at once Molex acknowledged
that it could cut eight weeks from the timetable, and we
think it should do so. The added costs are those of hiring
three men for several weekends of work, or in the alternative,
of employing an independent contractor to do the installing.
These costs are relatively small in comparison with the
serious nature of the pollution the company is asking permission
3 —341
to continue during the installation. The record is full of
citizen testimony detailing how unpleasant it is to live near
this factory, and we think Molex should pay the extra money
in order to terminate this untenable situation as quickly
as is practicable. We therefore shorten the company’s time
from its requested nine months to seven from the date of the
hearing, requiring the controls to be in operation by May
22, 1972.
The problem with the County must not be permitted
further to hold up correction of this acute particulate problem.
It is Molex’s obligation to control odors as well as particulates,
and it should commit itself to whatever additional controls
may be required to deal with the odor problem in order that
it may get on with its present program. We will not permit
the company’s odor problems to stand as an excuse for failure
to take prompt action to abate the particulate problem.
Molex must meet the particulate standards by May 22, 1972,
or face appropriate enforcement sanctions.
We have considered the possibility of denying the
variance altogether, since these emissions of coal—tar
derivatives impose asevere hardship on the neighbors and sixice
any hardship suffered by the company, even if it were required
to shut down until the controls are in, would be self-inflicted
due to the four—year delay in submitting and commenc~inga
control program. In light of the hardship that a shutdown
would impose upon innocent emeloyees, however, we do not
believe this step necessary at this time, since the company
is
now committed to a reasonably brief correction schedule.
On the other hand, we cannot give Molex a free pass for its
inexcusable and lengthy delay. Had the company done what it
was required to do, this pollution would have ceased two or
three years ago. Instead it has saved the interest on its
investment for the period of inaction, and it must not be
permitted to profit from its own wrong, unless we are to
encourage others similarly to ignore their obligations. Not
only was the failure to file the required intent letter and
compliance program a double violation of the old Air Pollution
Control Act, which the company argues we have no jurisdiction
to enforce. We disagree with that contention, but the company
has been emitting contaminants in excess of those permitted
by the regulations ever since the new statute came into effect
in July, 1970. This unexcused violation clearly is within
our authority to penalize.
We could achieve the appropriate goal of approving
the present program while imposing penalties for past violations
by denying the variance request and entertainimg a subsequent
complaint. In similar cases in the past, however, we have
3
—
342
reached the same result without the unnecessary time and cost
of a second hearing by granting a variance in the sense of
protection from future prosecution on the condition of payment
of a money penalty for past delays. See, e.g., Marquette
Cement Co.
V.
EPA, # 70-23 (Jan. 6, 1971); Agrico Chemicals
Co., # 71-211 (December 21, 1971). We think the same course
is appropriate here, ~ $10,000 penalty condition is therefore
imposed.
In addition, the statute requires us in cases of this
kind to impose the condition of a bond or other security in
an amount sufficient to deter any failure to adhere to the
program. The cost of the program is estimated at $45,000,
and we shall require security in that amount, in accord with the
guidelines set forth in earlier Board decisions.
This opinion constitutes the Board~s findings of fact
and conclusions of law,
ORDER
Molex, Inc. is hereby granted a variance to emit particulate
air contaminants in exesss of those permitted by the Rules and
Regulations Governing the Control of Air Pollution, until May
22,
1972, provided the following conditions are met:
1. Molex shall diligently pursue the program of scrubber
installation as described in the record; and
2. Molex shall file monthly progress reports with the
Agency, commencing on February 1, 1972; and
3. Molex shall not increase its discharge of contaminants
during the period of this variance; and
4. Within 35 days after receipt of this order, Molex shall
pay to the Agency the sum of $10,000 as a penalty for
past delays in controlling particulate emissions; and
5. Within 35 days after receipt of this order, Molex
shall post with the Agency a bond of other adequate
security in the amount of $45,000 to assure adherence
to the control program.
Breach of any of the conditions of this order shall be grounds for
revocation of this variance.
I, Christan Moffett,
Clerk of the Pollution Control Board,
certify that the above Opinion was adopted by ~he Board this
‘~
day of January, 1972, by a vote of
‘7
to 0
~43
.
.