ILLINOIS POLLUTION CONTROL BOARD
    January 6, 1972
    MOLEX, INC.
    v.
    )
    #
    71—200
    ENVIRONMENTAL PROTECTION AGENCY
    )
    Opinion of the Board (by Mr. Currie):
    Molex’s petition, filed in June 1971, asked a year’s
    variance from the particulate air contaminant emission
    regulations to permit operation during installation of
    scrubbers to control organic emissions from its plastics
    plant in Brookfield. We grant the request subject to several
    conditions for reasons indicated below.
    Molex received letter—of—intent forms from the old
    Air Pollution Control Board in 1967, specifically nOtifying
    the company of its obligation to submit process emission data
    and to file a program for bringing its operations into com-
    pliance. By its own admission the company did nothing about
    it until 1970, when it began looking for a solution. The
    present petition, filed four years after the letter of intent
    was required, was the first attempt to establish a control
    program.
    The plan envisions installation of two scrubbers that
    will allegedly reduce emissions by 95. The Agency has issued
    permits for the equipment, finding it adequate to meet the
    emission standards. Construction cannot begin until Cook
    County also gives a permit, and the County had at the time
    of the hearing refused to do so because it wanted assurance
    that excessive odors would not continue after the scrubbers
    were in operation.
    The company at the hearing November 22 said that nine
    months would be required to complete the installation. As
    the Agency demonstrated through company witnesses, however,
    this schedule is based upon installation of the scrubbers
    one at a time. By putting both in at once Molex acknowledged
    that it could cut eight weeks from the timetable, and we
    think it should do so. The added costs are those of hiring
    three men for several weekends of work, or in the alternative,
    of employing an independent contractor to do the installing.
    These costs are relatively small in comparison with the
    serious nature of the pollution the company is asking permission
    3 —341

    to continue during the installation. The record is full of
    citizen testimony detailing how unpleasant it is to live near
    this factory, and we think Molex should pay the extra money
    in order to terminate this untenable situation as quickly
    as is practicable. We therefore shorten the company’s time
    from its requested nine months to seven from the date of the
    hearing, requiring the controls to be in operation by May
    22, 1972.
    The problem with the County must not be permitted
    further to hold up correction of this acute particulate problem.
    It is Molex’s obligation to control odors as well as particulates,
    and it should commit itself to whatever additional controls
    may be required to deal with the odor problem in order that
    it may get on with its present program. We will not permit
    the company’s odor problems to stand as an excuse for failure
    to take prompt action to abate the particulate problem.
    Molex must meet the particulate standards by May 22, 1972,
    or face appropriate enforcement sanctions.
    We have considered the possibility of denying the
    variance altogether, since these emissions of coal—tar
    derivatives impose asevere hardship on the neighbors and sixice
    any hardship suffered by the company, even if it were required
    to shut down until the controls are in, would be self-inflicted
    due to the four—year delay in submitting and commenc~inga
    control program. In light of the hardship that a shutdown
    would impose upon innocent emeloyees, however, we do not
    believe this step necessary at this time, since the company
    is
    now committed to a reasonably brief correction schedule.
    On the other hand, we cannot give Molex a free pass for its
    inexcusable and lengthy delay. Had the company done what it
    was required to do, this pollution would have ceased two or
    three years ago. Instead it has saved the interest on its
    investment for the period of inaction, and it must not be
    permitted to profit from its own wrong, unless we are to
    encourage others similarly to ignore their obligations. Not
    only was the failure to file the required intent letter and
    compliance program a double violation of the old Air Pollution
    Control Act, which the company argues we have no jurisdiction
    to enforce. We disagree with that contention, but the company
    has been emitting contaminants in excess of those permitted
    by the regulations ever since the new statute came into effect
    in July, 1970. This unexcused violation clearly is within
    our authority to penalize.
    We could achieve the appropriate goal of approving
    the present program while imposing penalties for past violations
    by denying the variance request and entertainimg a subsequent
    complaint. In similar cases in the past, however, we have
    3
    342

    reached the same result without the unnecessary time and cost
    of a second hearing by granting a variance in the sense of
    protection from future prosecution on the condition of payment
    of a money penalty for past delays. See, e.g., Marquette
    Cement Co.
    V.
    EPA, # 70-23 (Jan. 6, 1971); Agrico Chemicals
    Co., # 71-211 (December 21, 1971). We think the same course
    is appropriate here, ~ $10,000 penalty condition is therefore
    imposed.
    In addition, the statute requires us in cases of this
    kind to impose the condition of a bond or other security in
    an amount sufficient to deter any failure to adhere to the
    program. The cost of the program is estimated at $45,000,
    and we shall require security in that amount, in accord with the
    guidelines set forth in earlier Board decisions.
    This opinion constitutes the Board~s findings of fact
    and conclusions of law,
    ORDER
    Molex, Inc. is hereby granted a variance to emit particulate
    air contaminants in exesss of those permitted by the Rules and
    Regulations Governing the Control of Air Pollution, until May
    22,
    1972, provided the following conditions are met:
    1. Molex shall diligently pursue the program of scrubber
    installation as described in the record; and
    2. Molex shall file monthly progress reports with the
    Agency, commencing on February 1, 1972; and
    3. Molex shall not increase its discharge of contaminants
    during the period of this variance; and
    4. Within 35 days after receipt of this order, Molex shall
    pay to the Agency the sum of $10,000 as a penalty for
    past delays in controlling particulate emissions; and
    5. Within 35 days after receipt of this order, Molex
    shall post with the Agency a bond of other adequate
    security in the amount of $45,000 to assure adherence
    to the control program.
    Breach of any of the conditions of this order shall be grounds for
    revocation of this variance.
    I, Christan Moffett,
    Clerk of the Pollution Control Board,
    certify that the above Opinion was adopted by ~he Board this
    ‘~
    day of January, 1972, by a vote of
    ‘7
    to 0
    ~43

    .
    .

    Back to top