ILLINOIS POLLUTION CONTROL BOARD
    April 14, 1971
    MISSOURI PORTLAND CEMENT CO.
    V.
    )
    #71—5
    ENVIRONMENTAL PROTECTION AGENCY
    Opinion and Order of the Board (By Mr. Currie)
    Missouri Portland is a substantial interstate operation with
    sales
    of thirty million dollars a year (R. 57—59), which operates,
    amona other ventures, a cement production plant in Joppa, Illinois
    (R. 38)
    .
    The kiln at this plant is equipped with a precipitator
    of 95 efficiency CR. 39), and recent work done by the company
    is estimated by its engineer to have increased collection efficiency
    to 97 CR. 50-51). This falls considerably short of what is
    required by the regulations: Rule 3-3.222 of the Rules and
    Regulations Governing the Control of Air Pollution, made applicable
    to existing plants by Rule 2-2.21, requires cement plants to be
    equinped with devices of not less than 99.7 efficiency and to
    emit particulates not in excess of 0.1 grain per standard cubic
    foot of flue gas. Thus even with the improved efficiency claimed
    the efficiency of the present control equipment is ten times less
    than the law requires.
    The comPany filed an air contaminant emission reduction program
    (ACERP) in which it agreed to upgrade its precipitator to meet
    the standard (P. 76—77), and to do so by April 15, 1971 CR. 56).
    The equipment has been ourchased and is on the premises (R. 55)
    Installation work, which is expected to take 42 days CR. 83),
    was
    tc have begun March
    1, 1971, during the annual maintenance
    shutdown (R. 43). In January, however, the company experienced
    mechanical and power failures that necessitated a premature plant
    shutdown (P. 43). Efforts to have the precipitator installed
    during this period were unsuccessful because of an
    alleged shortage
    of skilled labor CR. 44, 107). The breakdowns in no way interfered
    with the comoanv~s ability to install the precipitator on schedule
    (R~ 61-62, 66-67). Yet the company seeks a variance to allow it
    to wait until January, 1972 to begin installing its control equipment
    (R. 103,109), on the ground that a second shutdown to install it now
    would cause a loss of profits (P. 52).
    1
    439

    The variance is denied. Whether or not in this case the
    alkalinity of the recovered cement particles (R. 135—36) creates
    an exception to the general rule that emission control in the
    cement industry is a profitable method of product recovery (P.
    124—25), the cost of pollution control is one that must be borne
    by the polluter and not by his innocent neighbors. The record
    includes serious objections from citizens to the grant of this
    variance (H. 119). It is clear that the emission of some 780
    pounds per hour of cement dust (H, 73)——even if reduced somewhat
    by recent actions——although posing so far~as the record shows no
    health danger (R. 53—54), is a rather considerable nuisance. There
    is no sufficient showing of hardship to justify the continuation of
    this nuisance. The equipment to stop it has already been ordered
    and delivered. It is ready to be installed, and there is no ex-
    cuse for delay. As the Agency says in its recommendation, the
    unfortun~~tepremature shutdown “is no more related to compliance with
    Rule 3—3.222 than is the fact that Eve ate the apple.” One cannot
    avoid paying the rent on the ground that he has had a bad day on
    the stock market.
    Under the statute (section 36(b)) a variance may be extended
    (and an ACERP is
    ~.
    variance, see EPA v. Commonwealth Edison Co.,
    # 70—4 (Feb. 17, 1971)) only upon a showing that staisfactory progress
    ha~ been made. This provision makes clear the statutory policy that
    variances are for those who are working as fast as they can to
    control emissions, not for those who simply prefer to postpone
    compliance for their own convenience so they can make an extra
    buck. To allow continued pollution while abatement work goes
    on is one thing; to stop working on abatement so that one may
    go on polluting is quite another.
    Missouri Portland has missed its deadline without excuse.
    It stands in violation of the Environmental Protection Act and
    of the regulations. It shall cease and desist from such violations
    at once and proceed to install the required control equipment
    forthwith. Any further violations shall be subject
    tO
    severe
    money penalties.
    The variance is denied,
    This opinion constitutes the Board’s findings of fact,
    conclusions of law, and order,
    I, Regina E. Ryan, certify that the Board has approved the
    above Opinion and Order of the Board this
    ~
    ~
    of April
    ,
    1971
    ~
    I
    —~
    440

    Back to top