ILLINOIS POLLUTION CONTROL BOARD
    February 14, 1972
    In the Matter of the Application
    of COMMONWEALTH EDISON COMPANY
    for a Permit for Dresden Unit 3
    )
    PCB
    70—21
    at Dresden Nuclear Power Station
    Mr. William E. Eaken appeared for the Illinois Pollution Control
    Board
    Messrs. Arthur C. Gehr and John Rowe appeared for Commonwealth
    Edison Company
    Messrs. Lawrence D. Spears and Alan Sugarman appeared for the
    Environmental Law Society
    Opinion of the Board (by Mr. R.J. Kissel):
    On November 23, 1971, the Board revised the Permit previously
    granted to Edison to operate Dresden Unit 3. One of the provisions
    of the revised Permit required that Edison complete the installation
    of a catalytic recombiner and eight charcoal beds, as outlined in
    the record of the proceedings, by April 1, 1973. See Paragraph 4(a)
    of the revised Permit, dated November 23, 1971. On February 2, 1972
    Edison filed a motion to clarify the November 23 order by changing
    the date on which the catalytic recombiner and eight charcoal beds
    had to be completed to June 1, 1973. Edison points out that the
    basis of the Board’s order on November 23 was the Company’s advanced
    anticipated completion date, which was testified to in the record
    as being June 1, 1973. See the testimony of Mr. Roveke, page 186,
    transcript of October 19, 1971.
    While we would like Edison to expedite the completion of the
    control equipment, we must agree with them that the testimony in the
    record supports the position taken in their motion to clarify the
    Board1s order. The insertion of the April 1, 1973 date was merely
    a clerical error in drafting of the order, and therefore, we will
    modify the order by deleting the April 1 date in Paragraph 4(a) and
    inserting the June 1 date.
    I, Christan L. Moffett, Clerk of the Pollution Control Board,
    certify that the Board adopted t~’ie above Opinion this /j/ day of
    February, 1972, by a vote of 4-1.
    Mr. Dumelle dissents.
    &u_~
    ‘9~~i
    3
    ~29

    ILLINOIS POLLUTION CONTROL BOARD
    February 14, 1972
    In the Matter of the Application
    of COMMONWEALTH EDISON COMPANY
    )
    PCB 70-21
    for a Permit for Dresden Unit 3
    at Dresden Nuclear Power Station
    Dissenting Opinion of Mr. Dumelle
    My dissent on the modifica1E~ionof the permit is based on the
    ground that it is really both moot and premature.
    It is moot because the transmittal letter spoke of oral
    arguments before the Appellate Court on February 8 and that date
    was past when this was granted. It is premature because it
    logically follows after a determination by this Board on whether
    or not to hear from Dr. Edward Radford on the General Electric
    nuclear fuel reprocessing plant at Morris, Illinois. Dr. Radford
    has alleged people dosages of 680 mr per year now being inflicted
    upon those residents within one mile of the three Dresden reactors.
    If he is even partially correct in his radiation estimates then
    this Board should immediately order a speedup of the off-gas
    system construction not from the 27 months now lengthened to 30
    months) of the permit but to a much shorter period. And a power
    reduction, in my view, is also called for, if Dr. Radford is
    right, especially at the ancient Dresden I plant with its short
    stack and consequently more potent radiation effects.
    I would point out that my Board-approved amendment (December 9,
    1971) to the Quad-Cities permit changed the date for completion of
    the off—gas system there to conform to the 27—month period now
    scrapped for Dresden. See permit (p. 12, November 15, 1971 “Sep-
    tember 1, 1973” compared to opinion of same date, p. 2 “December
    1973” and minutes of motions made at November 15, 1971 Board meeting.)
    Will the Board now change the completion dates for the sister
    units at Quad-Cities to give them a 30 month period also? I hope
    not.
    These off—gas treatment systems were available and in use
    in Germany some five years before the Board’s December 1970 Dresden
    hearings. Had Edison been following the AEC stricture on radia-
    tion dosages of ‘as low as practicable” these treatment systems
    would have been designed, ordered constructed and on—line today.
    S
    3
    630

    The people around Dresden and around Quad—Cities (if it operates
    before off—gas treatment is on-line) are paying or may pay the
    price for Edison’s delay.
    The newspaper story today (February 24, 1972) telling of
    Governor Richard B. Ogilvie’s February 14 (the date of this
    action) request to the Illinois Commerce Commission to investi-
    gate the “incidents” at the Dresden reactors is recognition of
    the great dangers to the public which may result from improper
    design or operation of Dresden. The off-gas treatment system
    adds a measure of safety to these nuclear plants and ought to be
    built and installed just as fast as humanly possible.
    /
    /~
    Jacob D. Dumelle
    Board Member
    I, Christan L. Moffett, Clerk of the Illinois Pollution
    Control Board, hereby certify the above Dissenting Opinion was
    submitted on the 24th day of February, 1972.
    1.
    ~
    /
    1
    f
    / /
    /
    t—~~1/
    //
    ‘Christan L. Moffett,~CIer1~
    Illinois Pollution Control Board
    S
    3 — 631

    S
    S

    Back to top