ILLINOIS POLLUTION CONTROL BOARD
    July 21, 2008
    AMEREN ENERGY GENERATING
    COMPANY,
    Petitioner,
    v.
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent.
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    )
    PCB 08-61
    (Beneficial Use Determination – Coal
    Combustion Waste)
    ORDER OF THE BOARD (by G.T. Girard):
    On April 17, 2008, at the parties’ request, the Board extended until July 6, 2008, the time
    period for Ameren Energy Generating Company to appeal a February 29, 2008 determination of
    the Illinois Environmental Protection Agency (Agency).
    See
    415 ILCS 5/3.135, 40(a)(1) (2006);
    35 Ill. Adm. Code 105.206. The Agency’s determination concerns coal combustion by-product
    (CCB) produced from the combustion of coal used in generating electricity at Ameren’s
    Meredosia Power Station in Morgan County. The Agency granted a beneficial use
    determination, subject to conditions, for CCB to be used as structural fill in the construction of
    three roads at the facility. Because Ameren failed to timely file an appeal, the Board dismisses
    this case and closes the docket.
    IT IS SO ORDERED.
    I, John Therriault, Assistant Clerk of the Illinois Pollution Control Board, certify that the
    Board adopted the above order on July 21, 2008, by a vote of 4-0.
    ___________________________________
    John Therriault, Assistant Clerk
    Illinois Pollution Control Board