1. PROCEDURAL HISTORY
    2. FACTUAL BACKGROUND
    3. STATUTORY AND REGULATORY PROVISIONS
    4. MOTION TO INCORPORATE DOCUMENTS
    5. Webb’s Motion
    6. Board Analysis
    7. WEBB’S PETITION FOR REVIEW
    8. BURDEN OF PROOF
    9. STANDARD OF REVIEW

 
ILLINOIS POLLUTION CONTROL BOARD
February 15, 2007
WEBB & SONS, INC.,
Petitioner,
v.
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent.
)
)
)
)
)
)
)
)
)
)
PCB 07-24
(UST Appeal)
INTERIM OPINION AND ORDER OF THE BOARD (by A.S. Moore):
Webb & Sons, Inc. (Webb) seeks the Board’s review of a determination by the Illinois
Environmental Protection Agency (Agency) that modified Webb’s proposed budget for the high
priority corrective action plan (CAP) for a leaking underground storage tank (UST) site at 1201
DeWitt Avenue, Mattoon, Coles County. Webb challenges the Agency’s determination to reject
all proposed personnel costs as unreasonable. For reasons described below, the Board affirms
the Agency’s rejection of Webb’s proposed budget for personnel for four specified job titles.
Also for reasons described below, the Board reverses the Agency’s rejection of Webb’s proposed
budget for the 16 remaining job titles in Webb’s proposed personnel budget. The Board also
grants Webb’s motion to incorporate specified documents by reference into the record of this
proceeding and reserves ruling on Webb’s request for the reimbursement of fees.
PROCEDURAL HISTORY
On October 13, 2006, the Board received from Webb a petition seeking the Board’s
review of a September 12, 2006 determination of the Agency. In an order dated November 2,
2006, the Board accepted Webb’s petition for hearing. The Agency filed the administrative
record (R.) on November 28, 2006.
The Board conducted a hearing (Tr.) on December 11, 2006. Mr. Kevin Saylor and Mr.
James Malcom testified for Webb. At hearing, Webb filed eight exhibits (Exh.), each of which
was admitted. Tr. at 63-67. Webb filed a post-hearing brief (Webb Br.) on December 29, 2006,
and the Agency filed a post-hearing brief (Agency Br.) on January 12, 2007.
On December 13, 2006, Webb filed a motion to incorporate documents by reference
(Mot.). Accompanying the motion were the documents that Webb seeks to incorporate into the
record of this proceeding.
FACTUAL BACKGROUND

2
Webb owns real property located at 1201 DeWitt Avenue, Mattoon, Coles County (Site).
R. at 1, 28. On May 3, 1993, Webb reported a release from USTs at the Site to the Illinois
Emergency Management Agency (IEMA). R. at 28. In a letter dated July 12, 2002, the State
Fire Marshal responded to Webb’s Reimbursement Eligibility and Deductible Application by
determining that Webb was eligible to seek payment of costs in excess of $15,000 with regard to
six specified USTs and in response to IEMA Incident Number 9301126. R. at 67. Webb
removed all tanks from the Site in October 2002. R. at 28. The resulting Incident Number
20021577 re-reports the Incident Number 931126.
Id
.
By a letter dated August 18, 2006, HDC Engineering (HDC) submitted a High Priority
Corrective Action Plan (CAP) and Budget to the Agency on behalf of Webb. R. at 25 (referring
to UST Incident No. 931126/021577);
see
R. at 47-66 (budget and billing form). On August 23,
2006, the Agency received the proposed plan and budget.
See
R. at 1. Webb’s proposed budget
divides personnel costs into the following four categories: High Priority Investigation and
Preliminary Costs, CAP Implementation (dig and haul), Additional Well Monitoring/Well
Replacement/TACO [Tiered Approach to Corrective Action Objectives] sample collection, and
CACR [Corrective Action Completion Report] Report/HAAs [Highway Authority
Agreements]/Reimbursement. R. at 54-56. Within those four categories, Webb lists job titles for
specified personnel, tasks to be performed by each title, the number of hours attributed to the
tasks performed by each title, the hourly rate paid to each title, and the total personnel costs
attributable to each title.
Id
. Under High Priority Investigation and Preliminary Costs, the
proposed budget attributes an unspecified number of hours to the Senior Project Manager,
Professional Engineer, and Engineer III for tasks performed with regard to two UST project
appeals. R. at 54.
In a letter dated September 12, 2006, and signed by Harry A. Chappel, P.E., the Agency
notified Webb that it had modified Webb’s proposed budget. R. at 2, citing 415 ILCS
5/57.7(b)(3), 57.7.(c) (2004); 35 Ill. Adm. Code 734.505(b), 734.510(b). Specifically, the
Agency approved total personnel costs of $0.00. R. at 5. In its September 12, 2006 letter, the
Agency stated that it modified Webb’s proposed budget in the amount of “$103,360.00 for
personnel costs deemed unreasonable. Such costs are ineligible for payment from the Fund
pursuant to 35 Ill. Adm. Code 732.606(hh). The Agency is requesting an hourly breakdown of
each task performed by each job title in order to make a more thorough review of the proposed
personnel costs.” R. at 5.
Two witnesses, Mr. Kevin Saylor and Mr. James Malcom, testified at hearing on behalf
of Webb. Mr. Saylor testified that he is a licensed professional engineer employed by HDC as
an environmental division manager. Tr. at 7. Mr. Saylor further testified that he prepared the
corrective action budget, including personnel costs, for the Site. Tr. at 10;
see
R. at 47-66.
Mr. Saylor testified that, in addition to this proceeding, there have been two previous
appeals involving remediation of the Site. Tr. at 19. Mr. Saylor further testified that the first of
those two appeals involved a request by Webb for reimbursement of the costs of tank removal
and soil excavation under Part 731 of the Board’s UST regulations.
Id
.;
see
35 Ill. Adm. Code
731.101
et seq
. Specifically, Webb appealed the Agency’s determination to deduct
approximately $70,000 from Webb’s reimbursement for those expenses. Tr. at 19;
see
Webb &

3
Sons, Inc. v. IEPA, PCB 04-105 (Mar. 26, 2004). Mr. Saylor testified that this first appeal
successfully recovered those costs (Tr. at 19), and the Board ultimately granted Webb’s
voluntary motion to dismiss its proceeding. Webb & Sons, Inc. v. IEPA, PCB 04-105 (Sept. 16,
2004). Mr. Saylor further testified that this 2004 appeal to the Board did not provide any way to
recover the cost of the time spent by HDC personnel performing work necessary to pursue the
appeal. Tr. at 20. Mr. Saylor further testified that this work was in addition to what it would
have performed if the Agency had approved its budget as submitted. Tr. at 22.
Mr. Saylor testified that the second appeal involved a request by Webb for the Agency’s
approval of a budget for Stage II site investigation activities. Tr. at 21;
see
Webb & Sons, Inc. v.
IEPA, PCB 05-183 (Apr. 6, 2005). Specifically, Webb appealed the Agency’s deduction of
$17,610 in personnel costs, the entire amount of personnel costs requested in that budget. Tr. at
21;
see
Webb & Sons, Inc. v. IEPA, PCB 05-183 (Apr. 6, 2005). Mr. Saylor further testified
that, in response to the Agency’s determination, HDC listed the hours of work performed on
each task by each title listed in the personnel budget. Tr. at 21. After the Agency approved
approximately half of the personnel budget requested by HDC, Mr. Saylor testified that Webb
filed the second appeal in order to restore the amounts deducted from its Stage II site
investigation budget. Tr. at 22;
see
Webb & Sons, Inc. v. IEPA, PCB 05-183 (Apr. 6, 2005).
Mr. Saylor testified that this appeal successfully recovered approximately 90% of those
requested costs (Tr. at 22), and the Board ultimately granted Webb’s voluntary motion to dismiss
its proceeding. Webb & Sons, Inc. v. IEPA, PCB 05-183 (Aug. 4, 2005).
Mr. Malcom testified that the Agency has employed him for eight years as a project
manager in the leaking UST section. Tr. at 39. Mr. Malcom further testified that he reviewed
the corrective action plan and budget for the Site and that he prepared the technical review notes
regarding Webb’s submission to the Agency. Tr. at 40;
see
R. at 8-9. Mr. Malcom further
testified that he believed that Webb’s budget proposed overall an excessive number of hours for
personnel and that he sought additional review by his unit manager, Harry Chappel. Tr. at 41.
Mr. Malcom further testified that Mr. Chappel and the Agency’s three other unit managers
reviewed Webb’s proposed budget and reached the final determination reflected in the Agency’s
September 12, 2006 letter to Doris Webb. Tr. at 43;
see
R. at 1-5. Mr. Malcom further testified
that the unit managers determined to seek a breakdown of personnel costs from Webb. Tr. at 52;
see
R. at 5.
Mr. Malcom testified that, under the category of high priority investigation and
preliminary costs, the 453 hours attributed to a senior project manger were excessive in
comparison with the 60 hours he considered to be the average for that title. Tr. at 43-45;
see
R.
at 54. Mr. Malcom further testified that the 84 hours attributed to a professional engineer in that
category were excessive based on his experience and in comparison with the 20 hours he
considered to be the average for that job title. Tr. at 45;
see
R. at 54. Mr. Malcom further
testified that the 68 hours attributed to an engineer III were excessive and that the tasks assigned
to that job title would probably require 35 hours. Tr. at 45;
see
R. at 54. Mr. Malcom further
testified that Webb sought reimbursement for UST appeals only for these three job titles. Tr. at
45-46. Mr. Malcom further testified that the Agency had not ever directly reimbursed costs
associated with previous UST appeals. R. at 60-61. In addition, Mr. Malcom testified that,
under the category of CACR Report/HAAs/Reimbursement, the 16 hours attributed to the

 
4
scientist III were excessive in comparison with the two hours he would have approved. Tr. at 47;
see
R. at 56.
STATUTORY AND REGULATORY PROVISIONS
Section 732.606(hh) of the Board’s petroleum UST regulations, addressing releases
reported between September 23, 1994 and June 23, 2002, provides in pertinent part that “[c]osts
ineligible for payment from the Fund include but are not limited to . . . [c]osts proposed as part of
a budget plan that are unreasonable.” 35 Ill Adm. Code 732.606(hh).
Section 734.660(dd) of the Board’s petroleum UST regulations, addressing releases
reported on or after June 24, 2002, provides in pertinent part that “[c]osts ineligible for payment
from the Fund include, but are not limited to . . . [c]osts proposed as part of a budget that are
unreasonable.” 35 Ill. Adm. Code 734.660(dd).
MOTION TO INCORPORATE DOCUMENTS
Webb’s Motion
On December 13, 2006, Webb filed a motion to incorporate documents by reference.
Webb states that the Board’s procedural rules provide that, “upon the written request of any
person, the Board . . . may incorporate documents from the record of another Board docket into
any proceeding. The person seeking incorporation must demonstrate to the Board . . . that the
material to be incorporated is authentic, credible, and relevant to the proceeding.” Mot. at 1,
citing 35 Ill. Adm. Code 101.306(a). Webb’s motion addresses five specific documents.
First, Webb seeks to incorporate its own petition for review from a separate UST appeal
regarding this Site. Mot. at 1. In that separate appeal, Webb requested the Board’s review of the
Agency’s determination to deny Webb’s site investigation budget. Mot. at 1;
see
Webb & Sons,
Inc. v. IEPA, PCB 05-183 (Apr. 6, 2005) (2005 Webb Appeal). Second, Webb seeks to
incorporate excerpts from the administrative record filed by the Agency in that separate appeal.
Mot. at 1;
see
Webb & Sons, Inc. v. IEPA, PCB 05-183 (May 27, 2005) (2005 Webb Record).
Webb states that it obtained this petition and these excerpts from its attorney’s files and that they
are “true and accurate copies” of the documents filed with the Board. Mot. at 2.
Third, Webb seeks to incorporate testimony offered by Douglas W. Clay, manager of the
UST section in the Agency’s Bureau of Land, in a recent UST rulemaking docket. Mot. at 2;
see
Proposed Amendments to Regulation of Petroleum Leaking Underground Storage Tanks (35 Ill.
Adm. Code 732, 734), R04-22(B), R04-23(B) (cons.) (Mar. 1, 2006) (2006 Clay Testimony).
Fourth, Webb seeks to incorporate excerpts of Clay’s testimony from a separate UST rulemaking
docket. Mot. at 2;
see
Proposed Amendments to Regulation of Petroleum Leaking Underground
Storage Tanks (35 Ill. Adm. Code 732), R04-22 (Mar. 8, 2004) (2004 Clay Testimony). Fifth,
Webb seeks to incorporate testimony offered by Harry A. Chappel, a unit manager in the UST
section in the Agency’s Bureau of Land, in that separate UST rulemaking docket. Mot. at 2;
see
Proposed Amendments to Regulation of Petroleum Leaking Underground Storage Tanks (35 Ill.

 
5
Adm. Code 732), R04-22 (Mar. 8, 2004) (2004 Chappel Testimony). Webb states that it
obtained these three documents from the Board’s on-line e-library. Mot. at 2.
Webb argues that “[a]ll of these materials are relevant to the Petition to review the
Agency’s denial of all personnel costs in Petitioner’s CAP budget.” Mot at 2. Specifically,
Webb argues that the materials show the vast experience the Agency has obtained from
reviewing over 12,800 budgets in 15 years.” Mot. at 2 (2004 figures). Webb further argues that
the testimony offered by Agency managers in the UST rulemaking dockets “show[s] the
Agency’s detailed analysis of personnel costs required for the creation and implementation of all
corrective action plans.” Mot. at 2. Concluding, Webb claims that these documents filed with
the Board “show that the Agency has such a vast knowledge of corrective action plan budgets
that it could have made a determination of the reasonableness of the Petitioner’s proposed
personnel costs without requesting additional break-downs of the hours to be expended by each
person identified as having a role in the preparation and implementation of the Petitioner’s
Corrective Action Plan.”
Id
.
Board Analysis
The Board notes that the Agency did not file a reply to Webb’s motion to incorporate
documents by reference. Under the Board’s procedural rules, “[i]f no response is filed, the party
will be deemed to have waived objection to the granting of the motion, but the waiver of
objection does not bind the Board or the hearing officer in its disposition of the motion.” 35 Ill.
Adm. Code 101.500(d).
In its motion, Webb first seeks to incorporate the 2005 Webb Appeal. Mot. at 1;
see
Webb & Sons, Inc. v. IEPA, PCB 05-183 (Apr. 6, 2005). Second, Webb’s motion seeks to
incorporate the 2005 Webb Record. Mot. at 1;
see
Webb & Sons, Inc. v. IEPA, PCB 05-183
(May 27, 2005). The Board notes that the hearing officer admitted these documents into the
record at hearing as Exhibits 2 and 5, respectively. R. at 64-65. The Agency had no objection to
their admission but objected to their relevance to this proceeding. R. at 64. Responding to that
objection, the hearing officer stated that, because they pertained to the same location within a
short period of time of this appeal, they were relevant as background information of which the
Agency should have been aware in making its determination. R. at 64-65.
Third, Webb seeks to incorporate the 2006 Clay Testimony. Mot. at 2;
see
Proposed
Amendments to Regulation of Petroleum Leaking Underground Storage Tanks (35 Ill. Adm.
Code 732, 734), R04-22(B), R04-23(B) (cons.) (Mar. 1, 2006). Fourth, Webb seeks to
incorporate of the 2004 Clay Testimony. Mot. at 2;
see
Proposed Amendments to Regulation of
Petroleum Leaking Underground Storage Tanks (35 Ill. Adm. Code 732), R04-22 (Mar. 8, 2004).
Fifth, Webb seeks to incorporate the 2004 Chappel Testimony. Mot. at 2;
see
Proposed
Amendments to Regulation of Petroleum Leaking Underground Storage Tanks (35 Ill. Adm.
Code 732), R04-22 (Mar. 8, 2004). The Board notes that the hearing officer admitted these
documents into the record at hearing as Exhibits 6, 7, and 8, respectively. R. at 65-67. The
Agency had no objection to their admission but objected to their relevance to this proceeding.
Id
. Responding to that objection, the hearing officer stated that the Board would be able to take

 
6
notice of public records such as the three documents that formed part of the record of one of the
Board’s own regulatory proceedings. R. at 65-66.
The Board notes that this appeal is to be decided on the basis of the record before the
Agency when it made its decision. Alton Packaging Corp. v. IEPA, PCB 84-145, slip op. at 3
(Apr. 24, 1986);
see
35 Ill. Adm. Code 105.412. The Board also notes that Webb seeks to
incorporate only public Board records related either to the Site or to the Board’s UST regulations
generally. Granting Webb’s motion would not incorporate new data into the Agency record but
would only incorporate documents of which the Board can take notice.
See
35 Ill. Adm. Code
101.630. Because the Agency has waived any objection to the granting of the motion to
incorporate documents by reference, and because the hearing officer has admitted as hearing
exhibits each of the five documents that Webb seeks to incorporate, the motion is granted, and
the five specified documents are incorporated into the record of this proceeding.
See
35 Ill.
Adm. Code 101.306.
WEBB’S PETITION FOR REVIEW
Webb states that it was the owner of USTs formerly located at the Site. Pet. at 1. Webb
further states that, on August 18, 2006, it submitted a CAP and budget for the Site to the Agency.
Pet., Exh. A (budget). Webb further states that the Agency on September 12, 2006 approved the
CAP with modification. Pet. at 1. Webb further states that “[n]o appeal is being taken as to the
approval of the CAP with modifications.”
Id
.
Webb states the Agency’s September 12, 2006 determination also modified the budget
proposed for the Site. Pet. at 2; Pet., Exh. B. Webb further states that it “accepts and does not
appeal the budget modifications made by the Agency for Investigation Costs, Field Purchases
and Other Costs, and Handling Charges.” Pet. at 2. Webb further states that it “does appeal the
Agency’s rejection of
all
personnel costs.”
Id
. (emphasis in original). Webb further states that
the Agency rejected the proposed personnel costs as “unreasonable” and ineligible for payment
from the Fund. Pet. at 3; Pet., Exh. B, citing 35 Ill. Adm. Code 732.606(hh). In its denial letter,
the Agency requested from Webb “an hourly breakdown of each task performed by each job title
in order to make a more thorough review of the proposed personnel costs.” Pet. at 3; Pet., Exh
B.
Webb claims that its proposed budget on pages G-1 and G-2 contains a detailed
breakdown for the personnel associated with its High Priority Investigation and Preliminary
Costs. Pet. at 3; Pet., Exh. A at G-1–G-2. Webb further claims that “[t]hat category is broken
down among eight different personnel, a description of the specific tasks to be performed by
each person, the number of hours attributable to each person the hourly rate of that person, and
total dollars allocated to each person.” Pet. at 3;
see
Pet., Exh. A at G-1-G-2. Webb further
claims that “[t]he hourly rate for each designated person is
less
than the hourly rate approved by
the Agency pursuant to the Agency’s Rate Sheet.” Pet. at 3 (emphasis in original); Pet., Exh. C
(Personnel Titles and Requirements).
Webb also claims that its proposed budget on page G-2 contains a detailed breakdown for
the personnel associated with its CAP Implementation costs. Pet. at 3; Pet., Exh. A at G-2.

7
Webb further claims that “[t]hat category is broken down among five different personnel, a
description of the specific task to be performed by each person, the number of hours attributable
to each person and the hourly rate and total dollars allocated to each person.” Pet. at 3-4;
see
Pet., Exh. A at G-2. Webb further claims that “[t]he hourly rate for each designated person is
less
than the hourly rate approved by the Agency pursuant to the Agency’s Rate Sheet.” Pet. at 4
(emphasis in original); Pet. at 3, Exh. C (Personnel Titles and Requirements).
Webb also claims that its proposed budget on pages G-2 and G-3 contains a detailed
breakdown for the personnel associated with its Additional Well Monitoring/Well
Replacement/TACO Sample Collection Costs. Pet. at 4; Pet., Exh. A at G-2–G-3. Webb further
claims that “[t]hat category is broken down into three different personnel categories with a
description of the services to be performed by each person, the number of hours allocated to each
person and the hourly rate and the total cost of services for each person.” Pet. at 4;
see
Pet., Exh.
A at G-2–G-3. Webb further claims that “[t]he hourly rate for each designated person is
less
than the hourly rate approved by the Agency pursuant to the Agency’s Rate Sheet.” Pet. at 3
(emphasis in original); Pet., Exh. C (Personnel Titles and Requirements).
Webb also claims that its proposed budget on page G-3 contains a detailed breakdown for
the personnel associated with its CACR Report/HAAs/Reimbursement costs. Pet. at 4; Pet., Exh.
A at G-3. Webb further claims that “[t]hat category is broken down into four different personnel
categories with a description of the services to be performed by each person, the number of hours
allocated to each person and the hourly rate and the total cost of services for each person.” Pet.
at 4;
see
Pet., Exh. A at G-3. Webb further claims that “[t]he hourly rate for each designated
person is
less
than the hourly rate approved by the Agency pursuant to the Agency’s Rate Sheet.”
Pet. at 4 (emphasis in original);
see
Exh. C (Personnel Titles and Requirements).
Webb claims that the Agency has approved “numerous projects” when HDC Engineering
LLC, Webb’s engineers on this project, used this method to provide a breakdown of the costs
and hours associated with various personnel. Pet. at 5. Webb argues that “[i]t was arbitrary and
capricious of the Agency to reject Petitioner’s Budget proposal based upon an alleged lack of a
detailed breakdown of all hours associated with each task, given the level of detail stated in the
proposed Budget.”
Id
. Webb further argues that “[i]t was arbitrary and capricious of the Agency
to reject Petitioner’s Budget proposal based upon the Agency’s objection to an alleged lack of
detail when the Agency has approved this same format as used in proposed budgets for other
project.”
Id
.
Webb requests that the Board find that the Agency’s September 12, 2006, rejection of all
of the personnel costs in the proposed budget for the Site “was arbitrary and capricious and
without statutory authority” and that the Board reverse the Agency’s decision to reject those
costs. Pet. at 5. Accordingly, Webb requests that the Board “[r]emand this matter to the Agency
with instructions to approve the Petitioner’s Budget proposal as submitted, except for the
modifications for Investigation Costs, Field Purchases and Other Costs, and Handling Charges.”
Pet. at 6. Webb also asks that the Board award Webb its engineer’s fees, attorney fees and
expenses incurred in bringing this action.
Id
.

 
8
BURDEN OF PROOF
The Board’s procedural rules provide that, in appeals of final Agency determinations,
“[t]he burden of proof shall be on the petitioner.” 35 Ill. Adm. Code 105.112(a). Specifically,
the burden is on Webb to demonstrate that the costs incurred are related to corrective action,
properly accounted for, and reasonable. Beverly Malkey, as Executor of the Estate of Roger
Malkey d/b/a Malkey’s Mufflers v. IEPA, PCB 02-104, slip op. at 9 (Apr. 17, 2003). When
requesting reimbursement from the fund, the owner or operator must provide a budget including
an accounting of all costs associated with the implementation and completion of the corrective
action plan.
Id
.; 415 ILCS 5/57.7(b)(3) (2004).
STANDARD OF REVIEW
The standard of review under section 40 of the Environmental Protection Act (Act) (415
ILCS 5/40 (2004)) is whether the application, as submitted to the Agency, would not violate the
Act and Board regulations. Ted Harrison Oil Co. v. IEPA, PCB 99-127, slip op. at 5 (July 24,
2003); citing Browning Ferris Industries of Illinois v. PCB, 534 N.E.2d 616 (2nd Dist. 1989).
The Board will not consider new information that was not before the Agency prior to its final
determination regarding the issues on appeal. Kathe’s Auto Service Center v. IEPA, PCB 95-43,
slip op. at 14 (May 18, 1995). The Agency’s denial letter frames the issues on appeal. Pulitzer
Community Newspapers, Inc. v. IEPA, PCB 90-142 (Dec. 20, 1990).
WEBB’S POST-HEARING BRIEF
Webb argues that the Agency has stated that it ‘could not make a determination as to
whether the personnel costs were reasonable with just the description of the tasks to be
performed by each person with the hourly rate and number of hours stated.” Webb Br. at 12.
Webb contends that the Agency now requires additional time and money to specify the hours
committed to each task listed for each of the twenty job titles listed in the proposed budget.
Id
.,
see
R. at 54-56.
Webb states that the Agency must determine that the costs proposed in a CAP budget are
reasonable before it can approve that budget. Webb Br. at 12, citing 415 ILCS 5.57.7(c)(4)(C)
(2004). After noting that neither the Act nor the Board’s regulations defines “reasonable” (
see
415 ILCS 5/57.2 (2004), 35 Ill. Adm. Code 732.103), Webb claims that the term may be defined
as “not excessive or extreme.” Webb Brief at 14 (providing no citation to definition). Webb
argues that, except for the three personnel involved in the two previous Webb appeals and the
scientist II filing the No Further Remediation (NFR) letter, “the Agency has sufficient
information within the Budget and the Plan to determine that all other personnel costs
were
reasonable
and should have been approved.” Webb Br. at 12 (emphasis in original).
Webb acknowledges that the Agency was warranted in seeking a breakdown of the tasks
to be performed by the senior project manager, the professional engineer, and the engineer III,
because the proposed reimbursement for those job titles included compensation for the two
previous appeals related to the Site. Webb Br. at 13. Webb states that “a breakdown of the
hours allocated to the appeals would be appropriate. Once the appeal hours are broken out, the

9
total hours allocated strictly to the CAP can be identified and approved by the Agency.”
Id
.
Webb claims that the Agency has admitted that the personnel costs for all of the other titles and
tasks are reasonable.
Id
.;
see
R. at 54-56.
Webb further argues that, in Mr. Malcom’s testimony at hearing, he stated that he would
approve 60-100 hours for the senior project manager, 20-40 hours for the professional engineer,
and up to 50 hours for the engineer III. Webb Br. at 13. Webb queries why, if Mr. Malcom can
determine a reasonable hourly breakdown for these titles, Mr. Chappel as his supervisor is not
able to do so.
Id
. Webb claims that Mr. Chappel has a “tremendous amount of experience in
reviewing and analyzing budgets to determine what is ‘reasonable’ and what is ‘excessive or
extreme.’” Webb Br. at 14, citing Proposed Amendments to Regulation of Petroleum Leaking
Underground Storage Tanks, R04-22, slip op. at 1 ((Mar. 8, 2004). Based on this experience,
Webb argues that “it was arbitrary, capricious and unconscionable” for Mr. Chappel to have
failed to determine that Webb’s personnel costs were reasonable as submitted, with the
exceptions of the senior project manager, professional engineer, and engineer III under High
Priority Investigation and the scientist III under the CACR category. Webb Br. at 16-17. “It was
reasonable for Mr. Chappel to have requested an hourly breakdown only of the appeal work
performed by the Senior Project Manager, the Professional Engineer, and the Engineer II in order
to make a more thorough review of the proposed personnel costs as to those individuals.” Webb
Br. at 17.
AGENCY’S POST-HEARING BRIEF
The Agency notes that Agency Project Manager James Malcom testified at hearing
regarding his review on Webb’s proposed CAP and budget. Agency Br. at 3. The Agency
argues that Malcom’s training and experience led him to conclude with regard to the budget that
“the overall hours were excessively high, specifically for the job titles of Senior Project
Manager, Professional Engineer, and Engineer III for High Priority Investigation and
Preliminary Costs, and Scientist III for CACR Report/HAAs/Reimbursements.”
Id
., citing Tr. at
44-45, 47, 49. The Agency further argues that the tasks listed for the first three of those four job
titles include previous leaking UST appeals for the Site. Agency Br. at 3. The Agency further
argues that Malcom had never before approved reimbursement for expenses of that nature and
had never seen a request for their reimbursement.
Id
., citing Tr. at 45, 61. The Agency claims
that, because the overall hours in Webb’s proposed budget were excessive, it was not unusual to
request a breakdown of the hours requested for each job title. Agency Br. at 3, citing Tr. at 48,
52.
The Agency claims that there are “several flaws” in Webb’ position in this appeal.
Agency Br. at 3. First, the Agency notes that Webb’s petition for review asked the Board to
instruct the Agency to approve the proposed budget as submitted.
Id
.;
see
Pet. at 6. The Agency
further notes that Webb is “now conceding that the Illinois EPA needed additional information to
review the hours of the Senior Project Manager, Professional Engineer, and Engineer III for High
Priority Investigation and Preliminary Costs.” Agency Br. at 3;
see
Pet. Br. at 16-17.
Second, the Agency argues that Webb has referred to the job titles of Senior Project
Manager, Professional Engineer, and Engineer III as “limited” and has suggested that the hours

10
and costs associated with them are not significant. Agency Br. at 3-4;
see
Webb Br. at 12. The
Agency states that “[t]his is simply not the case. These three job titles account for almost 48% of
the total hours and 54% of the total personnel costs presented in the budget.” Agency Br. at 4.
The Agency argues that, even if Webb identifies the hours for those three job titles that are
attributable to the previous UST appeals for the Site, “the remaining hours will still have to be
scrutinized to determine if they satisfy the statutory and regulatory requirements for
reimbursement.”
Id
. The Agency notes that Malcom characterized the number of hours
requested for the Senior Project Manager as “really excessive.”
Id
., citing Tr. at 44-45.
Comparing its situation to facing “an unfinished jigsaw puzzle,” the Agency states that it could
not prudently have approved reimbursement for the other job titles in the budget as long as it
could not determine whether a majority of the personnel costs submitted were eligible for
reimbursement. Agency Br. at 4.
Third, the Agency cautions that Webb’s emphasis on the Agency’s expertise and
experience in reviewing UST plans and budget is a “double-edged sword.” Agency Br. at 4.
The Agency suggests that it is inconsistent for Webb to chastise Harry Chapell for failing to
approve its personnel budget and not to submit the hourly breakdown sought by the Agency in its
September 12, 2006 decision letter.
See
Agency Br. at 4. The Agency further argues that
Webb’s emphasis on the Agency’s expertise “is further weakened by Webb’s concession that
additional information was appropriate for three job titles.” Agency Br. at 4.
The Agency argues that the Board confronted a reduction of requested personnel hours in
the case of Todd’s Service Station v. IEPA, PCB 03-2 (Jan. 22, 2004). The Agency claims that,
although Todd’s had the opportunity to submit additional information about the reasonableness
of its proposed costs, the Board ultimately upheld the Agency. Agency Br. at 5, citing Todd’s
Service Station v. IEPA, PCB 03-2, slip op. at 7 (Jan. 22, 2004). The Agency argues that,
although Webb also had the opportunity to submit additional information, “Webb instead elected
to pursue this appeal.” Agency Br. at 5. The Agency argues that this appeal is similar to Todd’s
Service Station in that “there was little, if any, testimony explaining how the Illinois EPA’s
Administrative Record demonstrated that the costs of the Senior Project Manager, Professional
Engineer, and Engineer III for High Priority Investigation and Preliminary Costs were
reasonable.” Agency Br. at 5. The Agency argues accordingly that “Webb has failed to meet its
burden of proof in this matter” and “respectfully requests that the Board affirm its September 12,
2006 decision.” Agency Br. at 6.
BOARD DISCUSSION
After careful review of the record in this proceeding, the Board is persuaded that the
Agency correctly rejected specific amounts of personnel time for certain job titles in Webb’s
proposed budget, as described in detail below. Specifically, the Agency correctly rejected
personnel time under the category of High Priority Investigation and Preliminary Costs for the
positions of senior project manager, professional engineer and engineer III and under CACR
Report/HAAs/Reimbursements for the position of Scientist II. However, the Board reverses the
Agency’s rejection of all personnel time for all of the other job titles in Webb’s proposed budget,
also as described in detail below.

11
The Board has stated that “the purposes of the UST Fund are narrow.” Todd’s Service
Station v. IEPA, PCB 03-2, slip op. at 6 (Jan. 22, 2004) (citation omitted). The Act restricts a
corrective action plan to the mitigation of any threat to human health, human safety, or the
environment resulting from a UST release. 415 ILCS 5/57.7(c)(1)(A) (2004). In an earlier UST
appeal, the Board stated that “[t]he definition of corrective action does not encompass the
recovery of moneys from the Fund. . . . We find nothing in the definition of corrective action
that links those actions with actions taken to seek access to the Fund..” Chuck and Dan’s Auto
Service v. IEPA, PCB 92-203, slip op. at 14 (Aug. 26, 1993), citing State Bank of Whittington v.
IEPA, PCB 92-152, slip op. at 20 (June 3, 1993). In reviewing a corrective action plan budget,
the Agency must consider whether the costs are reasonable and are not incurred for corrective
action in excess of that which is necessary to meet the minimum requirements of the Act and
Board regulations. 415 ILCS 5/57.7(c)(4)(C) (2004). Applying this standard, the Board
determines whether Webb’s proposed budget, as submitted to the Agency with regard to specific
positions, would not violate the Act and Board regulations.
See
415 ILCS 5/40 (2004).
Senior Project Manager, Professional Engineer and Engineer III
In its proposed budget for High Priority Investigation and Preliminary Costs, Webb
sought the Agency’s approval for 453 hours at $98.00 per hour, or $44,394.00 for five tasks
attributed to a senior project manager. These five tasks include those related to “two LUST
project appeals.” R. at 54. Webb also sought approval for 84 hours at $87.00 per hour, or
$7,308.00 for seven tasks attributed to a professional engineer. These seven tasks include those
related to “two LUST project appeals.”
Id
. Webb also sought approval for 68 hours at $77.00
per hour, or $5,236.00 for five tasks attributed to an engineer III. These five tasks include those
related to “two LUST project appeals.”
Id
. The proposed budget did not allocate a specific
number of hours to any of the tasks attributed to any of those job titles. Citing 35 Ill. Adm. Code
732.606(hh), the Agency rejected these costs in their entirety as unreasonable. The Agency then
requested that Webb itemize the hours associated with each task performed by each job title.
Webb’s witness, Mr. Malcom, testified with regard to recovering costs associated with
prior UST appeals at the same site. In eight years as an Agency project manager reviewing
technical plans and budgets, Mr. Malcom had not seen an owner/operator attempt to recover
those appeal costs as an itemized task in a personnel budget. Tr. at 45. In addition, he had never
approved direct reimbursement of that cost. Tr. at 61.
Mr. Malcom further testified that the total number of hours requested for the job titles of
senior project manager, professional engineer, and engineer II were “excessive.” Tr. at 44-45.
Under High Priority Investigation and Preliminary Costs, Webb sought approval of 453 hours for
the senior project manager, while Mr. Malcom considered 60 hours as the average time required
for the tasks listed in the proposed budget for senior project manager, 20 hours as the average for
the professional engineer, and 35 hours as the average for the engineer III. Mr. Malcom
acknowledged that, for the senior scientist job title also listed under High Priority Investigation
and Preliminary Costs, Webb’s proposed personnel budget did not seek approval of hours for
previous UST appeals. For that job title, Webb sought approval of 150 hours, which Malcom
characterized as “a little excessive, but not unusual.” Tr. at 46.

12
In its post-hearing brief, Webb acknowledges that the Agency was warranted in seeking
an hourly breakdown of each task listed under High Priority Investigation and Preliminary Costs
for the job titles of senior project manager, professional engineer, and engineer III. Pet. Brief at
13. Webb suggests that this breakdown is appropriate because the specific number of hours
attributable to previous UST appeals and ineligible for reimbursement can be identified.
Id
.
With regard to these three job titles, the Board finds no persuasive explanation either in
the proposed budget itself or in the testimony at hearing that the total number of hours proposed
is reasonable. Without a more specific breakdown of the number of hours allocated to each of
the tasks to be performed by these three job titles, particularly the two earlier UST appeals
relating to this site, the Agency lacks sufficient information to determine whether the proposed
personnel costs are reasonable and properly accounted for as corrective action.
See
415 ILCS
5/57.2 (2004). Accordingly, Webb has failed to meet its burden of proving that its application,
as submitted to the Agency, would not violate the Act and Board regulations. The Board
therefore affirms the Agency’s September 13, 2006 determination to reject the proposed
personnel budget under High Priority Investigation and Preliminary Costs for the senior project
manager, professional engineer, and engineer III.
Scientist III
In its proposed budget for CACR Report/HAAs/Reimbursements, Webb sought the
Agency’s approval of 16 hours at $71.00 per hour, or $1,136.00 for filing an NFR letter and
decommissioning groundwater monitoring wells by a scientist III. The proposed budget did not
allocate the requested 16 hours between those two tasks. Citing 35 Ill. Adm. Code 732.606(hh),
the Agency rejected these costs in their entirety as unreasonable. The Agency also requested that
Webb itemize the hours associated with this job title.
Webb’s own witness, Mr. Malcom, testified that “16 hours would seem excessive for
filing of the NFR and closing up seven wells.” Tr. at 47. Mr. Malcom elaborated that the work
relating to wells would be reimbursed on a per-foot basis and not on the basis of personnel.
Id.
For filing an NFR, Mr. Malcom stated that the task “surely” wouldn’t require 16 hours.
Id
. He
further stated that budget proposals generally attribute one or two hours to that task and that he
would have approved two hours for its completion.
Id
.
With regard to this job title, the Board finds no persuasive explanation either in the
proposed budget itself or in the testimony at hearing that the 16 proposed hours requested under
CACR Report/HAAs/Reimbursements for the scientist III are reasonable. Without a more
specific breakdown of the number of hours allocated to the two tasks to be performed by the
scientist III, the Agency lacks sufficient information to determine whether the proposed
personnel costs are reasonable. Accordingly, Webb has failed to meet its burden of proving that
its application, as submitted to the Agency, would not violate the Act and Board regulations.
The Board therefore affirms the Agency’s September 13, 2006 determination to reject the
proposed personnel budget under CACR Report/HAAs/Reimbursements for the scientist III.
All Remaining Job Titles

13
In addition to the four job titles addressed above, Webb’s proposed budget includes hours
for five other job titles under the category of High Priority Investigation and Preliminary Costs:
150 hours at $83.00 per hour, or $12,450.00 for a senior scientist; 102 hours at $67.00 per hour,
or $6,834.00 for a scientist III; 21 hours at $55.00 per hour, or $1,155.00 for a scientist I; six
hours at $50.00 per hour, or $300.00 for a draftsperson, and 9.5 hours at $40.00 per hour, or
$380.00 for a technician I.
Webb’s proposed budget also includes hours for five job titles under the category of CAP
Implementation (dig and haul): eight hours at $100.00 per hour, or $800.00 for a senior project
manager; four hours at $100.00 per hour, or $400.00 for a professional engineer; 16 hours at
$87.00 per hour, or $1,392.00 for a senior scientist; 30 hours at $71.00 per hour, or $2,130.00 for
a scientist III; and 70 hours at $45.00 per hour, or $3,150.00 for a technician I.
Webb’s proposed budget also includes hours for three job titles under the category of
Additional Well Monitoring/Well Replacement/TACO sample collection: 8 hours at $87.00 per
hour, or $696.00 for a senior scientist; 42 hours at $71.00 per hour, or $2,982.00 for a scientsist
III; and 42 hours at $45.00 per hour, or $1,890.00 for an environmental technician I.
Webb’s proposed budget also includes hours for three other job titles under the category
of CACR Report/HAAs/Reimbursements: 8 hours at $100.00 per hour, or $800 for a senior
project manager; 32 hours at $100.00 per hour, or $3,200.00 for a professional engineer; and 92
hours at $87.00 per hour, or $8,004.00 for a senior scientist. R. at 54-56. The proposed budget
did not allocate a specific number of hours to any of the tasks attributed to any of those sixteen
job titles.
See id
. Significantly, none of these 16 positions listed prior UST project appeals
among the tasks to be performed in the requested personnel hours. Citing 35 Ill. Adm. Code
732.606(hh), the Agency also rejected these costs in their entirety as unreasonable. The Agency
then requested that Webb itemize the hours associated with each task performed by each job title.
At hearing, Mr. James Malcom testified on behalf of Webb. Mr. Malcom has eight years
of experience as a project manager in the Agency’s UST section and states that he has reviewed
“hundreds” of submitted budgets. Tr. at 39, 49. In his testimony, Mr. Malcom stated that he was
uncertain about the number of hours attributable to three job titles for previous UST appeals for
the site but found the hours proposed for 16 other job titles “acceptable.” Tr. at 53. Although
Mr. Malcom acknowledged that his work is subject to review by supervisors, he stated he would
have approved the hours submitted for those 16 personnel and rejected the hours proposed for
the other 4 job titles. Tr. at 54.
With regard to these 16 personnel, the Board finds that Webb has provided persuasive
evidence that the hours proposed for them are reasonable. Not one of these job titles lists work
associated with the previous UST appeals regarding this site among the tasks to be performed.
An Agency employee has characterized the hours proposed for these 16 job titles as “acceptable”
and not inconsistent with other budgets he has reviewed and approved. Tr. at 47. Accordingly,
Webb has met its burden of proving that its application, as submitted to the Agency with regard
to these 16 job titles, would not violate the Act and Board regulations. The Board therefore
reverses the Agency’s September 13, 2006 determination to reject the proposed personnel budget
for these 16 job titles.

14
FEES
In its petition for review, Webb requested that the Board award it “engineer’s fees,
attorney’s fees, and expenses incurred in bringing this action.” Pet. at 6. Section 732.606(g) of
the Board’s UST regulations provides that “[c]osts ineligible for payment from the Fund include
but are not limited to . . . [l]egal fees or costs, including but not limited to legal fees or costs for
seeking payment under this Part unless the owner or operator prevails before the Board and the
Board authorizes payment of such costs.” 35 Ill. Adm. Code 732.606(g).
The record does not now include the amount of any legal fees or costs incurred by Webb
in this proceeding in which it has partially prevailed before the Board, and the Board today
reserves ruling on the issue of fees.
Webb is directed to file on or before March 8, 2007, 21 days from the date of this order, a
statement of its legal fees and costs that may be eligible for reimbursement and its argument why
the Board could exercise its discretion to direct the Agency to reimburse from the UST Fund
those costs relating to this docket, Webb & Sons, Inc. v. IEPA, PCB 07-24.
See
35 Ill. Adm.
Code 732.606(g). The Agency may respond to this filing by filing its response with the Board
on or before March 29, 2007.
CONCLUSION
On the bases described above, the Board affirms the Agency’s rejection of Webb’s
proposed budget for personnel for the job titles of senior project manager, professional engineer,
and engineer III under the category of High Priority Investigation and Preliminary Costs and the
job title of scientist III under the category of CACR Report/HAAs/Reimbursements. The Board
also affirms the Agency’s modifications to Webb’s budget for Investigation Costs, Field
Purchases and Other Costs, and Handling Charges, which Webb has not appealed. Also on the
bases described above, the Board reverses the Agency’s rejection of Webb’s proposed budget for
the 16 remaining job titles in Webb’s personnel budget.
This opinion constitutes the Board’s interim findings of fact and conclusions of law in
this matter.
ORDER
1.
The Board affirms the Agency’s rejection of Webb’s proposed budget for personnel
for the job titles of senior project manager (453 hours), professional engineer (84
hours), and engineer III (68 hours) under the category of High Priority Investigation
and Preliminary Costs and the job title of scientist III (16 hours) under the category of
CACR Report/HAAs/Reimbursements.
2.
The Board reverses the Agency’s rejection of Webb’s proposed budget for the 16
remaining job titles in Webb’s personnel budget. Specifically, under the category of
High Priority Investigation and Preliminary Costs, the Board reverses the Agency’s

15
rejection of Webb’s proposed personnel budget for the job titles of senior scientist
(150 hours), scientist III (102 hours), scientist I (21 hours), draftsperson (6 hours),
and technician I (9.5 hours). Under the category of CAP Implementation (dig and
haul), the Board reverses the Agency’s rejection of Webb’s proposed personnel
budget for the job titles of senior project manager (8 hours), professional engineer (4
hours), senior scientist (16 hours), scientist III (30 hours), and technician I (70 hours).
Under the category of Additional Well Monitoring/Well Replacement/TACO sample
collection, the Board reverses the Agency’s rejection of Webb’s proposed personnel
budget for the job titles of senior scientist (8 hours), scientist III (42 hours), and
environmental technician I (42 hours). Under the category of CACR
Report/HAAs/Reimbursements, the Board reverses the Agency’s rejection of Webb’s
proposed personnel budget for the job titles of senior project manager (8 hours),
professional engineer (32 hours), and senior scientist (92 hours).
3.
Webb is directed to file on or before March 8, 2007, 21 days from the date of this
order, a statement of its legal fees and costs that may be eligible for reimbursement
and its argument why the Board could exercise its discretion to direct the Agency to
reimburse those costs. The Agency may respond to this filing by filing its response
on or before March 29, 2007.
IT IS SO ORDERED.
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, certify that the Board
adopted the above interim opinion and order on February 15, 2007, by a vote of 4-0.
Dorothy M. Gunn, Clerk
Illinois Pollution Control Board

Back to top