1. (R. 220).
      2. Board,Thomas
      3. Golz,concerningfrom USEPA,
      4. 13. James Ambroso, Land & Lakes Company, testifying on
      5. 14. Larry Eastep, P.E., from the Illinois Environmental
      6. 15. Sally S. Whalen, Illinois Manufacturers Association,
      7. concerning on-site exemptions and legislative intent
      8. (ft. 988),
      9. 16. John L. Kirby, Executive Director, Illinois Solid Waste
      10. Association (ISWA), concerning interim rules CR. 1001).
      11. Following the first notice and hearings the Board received
      12. the following written public comment:
      13. 1. Illinois Department of Insurance, August 15, 1984.
      14. 2, Cecos International, September 7, 1984.
      15. 4. CRCDA, International Association of Waste Management
      16. Professionals, September 17, 1984.
      17. 5. Surety Association of Illinois, October 18, 1984.
      18. 6. Chicago Association of Commerce & Industry, October 19
      19. 8. Granite City Steel Division of National Steel
      20. 9, Illinois Power Company, October 26, 1984.
      21. 10. Agency, October 26, 1984.
      22. 66-465
      23. 4. The Agency is authorized to enter into such contracts
      24. e. The Agency shall have the authority to approve or
      25. the State for any other penalty or relief provided bythis Act or any other law.
      26. OVERVIEW
      27. 1184—17
      28. Section 807.504 Amendment of Closure Plan
      29. 1. Modification in the operating plans or site design
      30. affecting closure.
      31. 2. Temporary suspension of wine acceptance, or reduction
      32. or increase in volume.
      33. 3. Change in the expected year of closure, or the year in
      34. which the cost of premature closure will be the
      35. greatest.
      36. Se:tjon 807.506 Initiation of Closure
      37. ‘°ure plan within 30 days after receipt ~? the fLna~ volume of
      38. 66-482
      39. Section 807.602 Time for Submission of Financial Assurance
      40. Section 807.603 Upgrading Financial Assurance
      41. 06485
      42. Section 807,604 Release of Financial Institution
      43. Section
      44. 807.604 Release of financial institution following a
      45. substitution of financial assurance or release ofthe operator.
      46. 807 .606 Release of the operator upon completion of closure
      47. and post-closure care.
      48. Section 807.605 Application of Proceeds and Appeal
      49. 66-486
      50. -33-.
      51. The post-closure cost estimate is:
      52. PCCE 3CCCPA)(P)CA) + C600)CM))
      53. The complete cost estimate is:
      54. The number of wells CM) cannot be less than three.
      55. Section 807.644 RCRA Financial Assurance
      56. Section 807.661 Trust Fund
      57. The Board will specify the form of trust agreements inAppendix A CR. 123, 390).
      58. 1. Time for submission by new facilities has been moved to
      59. Section 807.602.
      60. 2. Requirement to update the trust agreement with a change
      61. in the cost estimate has been deleted.
      62. 3. Provisions on release have been moved to Sections
      63. 807.604 and 807.606.
      64. Section 807.662 Surety Bond Guaranteeing Payment
      65. The Board will specify the form of bonds in Appendix A CR.123, 461, 465).
      66. The following ~rov4 e r~~osaJhave boon moved toother Sections:
      67. assurance;
      68. 3. Release of open
      69. ta.t~ most be submitted;
      70. ‘.ose the amount of rinanrial.
      71. 4. Release of finan • insVtution.
      72. Section 807.663 Suret B
      73. The perforniarce bo
      74. The EcIS conclude
      75. Section 807.664
      76. (,.a anteeing Performance
      77. ounter difficulties In
      78. arformance of closure CR. 392).
      79. The Board viii speAppendix A.
      80. o etters of credit in
      81. 3 ard has provided that.
      82. t-r at least four years,r ns allowing the Agency to
      83. crator fails to provide
      84. ~ e otice of cancellation.
      85. Section 807.665 C1ob se lioutaire
      86. c lied or.y for failure to pay-he operator builds equity in
      87. To meet the financial test, an operator must have a tangiblenet worth which is:
      88. 1. At least six times the current cost estimate; and
      89. 2. At least $10,000,000.
      90. Following the merit hearings it appeared that the

ILLINOIS POLLUTION
CONTROL
BOARD
November 21, 1985
N
THE
MATTER OF:
)
)
FINANCIAL ASSURANCE FOR
CLOSURE
)
R84~22C
~D POST-CLOSURE CARE OF
WASTE )
OISPOSAL SITES (ECONOMIC
IMPACT )
OF TEMPORARY REGULATIONS AND
)
AIX)PTION OF FINAL REGULATIONS) )
Final Order, Adopted Rule
(R84-22C),
OPINION OF THE BOARD (by J.
Anderson)
This Opinion
supports the Order of this same day adopting
permanent regulations to
replace temporary regulations adopted
prior to the filing/of an
economic impact study~
Public Act 83-775 became
effective on September
24, 1983.
Provisions of this
law, which are fully set out below,
prohibited
certain non—hazardous waste
disposal operations after March 1,
985 without a performance bond
or other security for the
purpose
oF insuring closure of the site
and post~c1osurecare in
accordance with the Environmental
Protection Act’
and Board
rules, Section 21.1(b) of the Act
required the Board to adopt by
January
1, 1985 rules which
specified the type and
amount
of
the
bonds or
other securities,
Gn June S., 1.984 the
Board opened this Docket for the purpose
of
promulgating regulations
implementing P,A~ 83-775,
On ~uly
1.9,
1954
the
Board proposed such as amendments to Part 807 The
proposal appeared at 8
Ill. Reg. 14145, August 10, 198/4,
On August 2, 1984 the
Board authorized the hearing oFficer
to seek outside expertise
to assist in developing the
record.
Another Board Assistant, who
had not been directly involved ~in
development of the
proposal and testimony, acted as hearing
officer at the formal
hearings.3
1”Act”: Ill. Rev. Stat.
1983, ch, 111
1/2,
pars. 10011 et seq.
2Unless otherwise indicated,
references to “Sections” or “Parts”
ar:? to Illinois Administrative
Code, Title 35,
3The Board appreciates the
assistance
of Morton F, Dorothy in
‘irafting these
regulations and this accompanying Opinion, and
of
Kathleen Crowley in
her responsibilities ss Hearing Officer,
66~463

-2-
The Board held five hearings
as folitows:
1. September 7, 1984,
Chicago
2. September 17, 1984,
Springfield
3. September 24, 1984,
Chicago
4. September 28, 1984, Carbondale
5,
October
9, 1984,
Springfield
The following witnesses testified,
with the primary area of
estimony indicated:
1.
Morton Dorothy,
Pollution Con~:ro1L Board, concerning the
overall outline of the
proposel (R. 12)
2. Douglas Andrews, P.E.,
testifying on behalf
of the
Illinois Chapter of
the Natbonel So~id Waste
Management
Association (NSWMA),
concerning the enuber and sizes of
sites (R. 171).
3, Gary Medler, counsel to the
Illinois Commissioner
o
Banks end Trusts,
concerning trust funds and letters of
credit (R. 206).
4. Kenneth Smith, Deputy
Director of the
Illinois
Department of Insurance,
concerning insurance
and bonds
(R. 220).
5. Carol Lee, from the United
States fnvironment~l
Proteccion Agency (USEPA),
testifying on
behalf of
NSWMA, concerning
self-insurance (FL
232)~
6. Paul Bailey, ICF, Inc., testif’Lrn~ ~Lhe
behest.
of the
7.
Board,Thomas
Golz,concerningfrom USEPA,
self-insurancetestifying(FL
at2hZ)the0 behest of the
Board, concerning
self—insurance (R~
531)~
8. James
W. Morgan, testifying at the behest of the Board,
concerning the Wisconsin
finenc:Ln1. essurance
program
(R.
568).
9. Charles Johnson, Technical
Director of the NSWMA,
concerning interim closure
plun rules (FL 633),
10. Joseph Benedict, John
Sexton Contractors,
Inc.,
concerning interim closure
p:Lan rules (R,~ 655).
11, Patrick Lynch, P.E,,
testifyin
at the behe~t
of the
Board, concerning closure
plans and cost estimates
(R. 681).
12, David C, Beck, P,E,, testifvrnn IsInif pE NSWMA,
concerning closure plans and
‘u~tIme :es
(R. 761.,
1032).
66-464

—3-
13. James Ambroso, Land & Lakes Company, testifying on
behalf
of
NSWMA
concerning self-insurance CR. 793).
14. Larry Eastep, P.E., from the Illinois Environmental
Protection Agency CIEPA or Agency), concerning closure
plans and cost estimates and implementation CR. 846).
15. Sally S. Whalen, Illinois Manufacturers Association,
concerning on-site exemptions and legislative intent
(ft. 988),
16. John L. Kirby, Executive Director, Illinois Solid Waste
Association (ISWA), concerning interim rules CR. 1001).
Following the first notice and hearings the Board received
the following written public comment:
1. Illinois Department of Insurance, August 15, 1984.
2, Cecos International, September 7, 1984.
3.
DuPage
County Forest Preserve District, September 19,
1984.
4. CRCDA, International Association of Waste Management
Professionals, September 17, 1984.
5. Surety Association of Illinois, October 18, 1984.
6. Chicago Association of Commerce & Industry, October 19
and
25, 1984.
7. Jan
Sexton
Coetrsetors, October 20, 1984.
8. Granite City Steel Division of National Steel
Corporation, Interlake Inc., Keystone Steel & Wire
Company,
LTV
Steel Company, Northwestern Steel & Wire
Company, and United States Steel Corporation, October
25, 1984.
9, Illinois Power Company, October 26, 1984.
10. Agency, October 26, 1984.
66-465

—4.-
11. NSWMA, October 26 and 30, l984..~
The Board was required to. adopt rules by January 1, 1985;
yet, it. had not received an economic impact study. ThereFore, on
December 27, 1984 the Board adopted emergency rules, and sent
t~rnporaryrules to second notice pursuant to Section 27(b) ani
27(c) oF the Act. The Board split the docket into Subdockets
R84-22A and R84-22B, with the former reserved for the emergency
rules and the latter for the temporary rules. The existing
record in R84-22 was incorporated into each Subdocket.
The emergency rules were accepted for fi.iing and became
effective on January 3, 1985. (9 111. Reg~741, January 13,
1985). in an Order dated January 10, 1985, the Board
corrected
~inerror in Section 807.624 (9 Iii. Reg~1:162, January 25, 1985).
The second notice in R84—22B was received by the Joint
Committee on Administrative Rules (JCAR) on January 24, 1985.
Although the second notice period ended on March 1l~1985, JCAR
did
not consider the proposal until March 19, 1985,
JCAR recommended that the Board seek clarifying legislation,
as to whether the amount of the bond is to be related to the
design and volume of the entire site, or just the disposal unit
as
one might conclude from the use of “facility” in the final
sentence of Section 21.1(b). The Board’s interpretation gives
greater weight to the requirement of Section 21.1(a) that the
bond be “for the purpose of insuring closure of the site.”
On April 18, 1985 the Board opened this docket, R84-22C for
the purpose of conducting economic impact hearings and revising
the temporary regulations as necessary in response to the
hearings. The Board also opened Docket~R84-22D’~F~i~ purpose
of addressing any remaining issues, including possible ambiguous
~ireasnoted by the JCAR staff,
4A public comment also was filed on April 1, 1985 by the Illinois
Chapter of National Solid Wastes Management Association
(NSWMA). This comment was untimely filed for Board
consideration, as it was received well after the end of the First
Notice period and commencement of the Second Notice period in
R84-22B. As noted in the Board’s April 4, 1984 Opinion in R84-
228, p. 3, note 4, and in the April 18, 1985 Order establishing
dockets R84-2.ZC and R84-22D, NSWMA’s concerns may be asserted in
docket R84-22D. See also the Order of October 10, 1,984 in R8L+—
22D, soliciting draft proposals addressing issues other
than
those raised by JCAR in R84-22B,
will appear below this matter
has been before
JCAR two times,
in R84-22B and in R84-22C. In this
0pinion.~
except where
otherwise i~dicateLj references to JCAR or
staff
actions or
comments reter to
K~4-LL~.
66~466

—5—
The temporary rules were adopted on April 4, 1985 in R84-
22B. They were filed with the Secretary of State on April 29,
L~85. They appeared at 9 Iii. Reg. 6722, May 10, 1985. The
~oard proposed to readopt the temporary
rules as permanent rules
in R84-22C at 9 Iii. Reg. 6598, May 10, 1985.
The Board received the final copy of the Economic Impact
Study from the Department of Energy and Natural Resources (DENR),
as approved by the Economic and Technical Advisory Committee, on
May 29, 1985. The Board conducted two economic impact hearing,s
as follows:
6. June 21, 1985, Springfield
7. July 2.~ 1985, Chicago
At the economic impact hearings the Board received testimony
from Dr. George Tolley, Mr. William Zeiler and Mr. Miguel Garcia
of RCF, Inc., the EcIS contractor, (R, 1049, 1063, 1129) The
Board also received testimony from Mr. Larry Eastep concerning
the extent of compliance with the emergency and temporary rules.
(R. 1100) The Board received no written public comment following
the economic impact hearings.
For the reasons discussed in detail hereafter, based on the
EcIS and the other evidence in the public hearing record, the
Board finds that these rules impose no adverse economic impact on
the people of the State.
On September 5, 1985 the Board adopted an Opinion and Order
sending the temporary rules adopted in R84-22B to second notice
as permanent rules without change. The second notice in R84-22C
was received by JCAR on September 13, 1985. The matter appeared
on JCAR’s agenda for its October 16 meeting, at which time ~JCAR
requested that the Board withhold filing the rules until after
JCAR’s November 14 meeting. The 45-day period for JCAR action
ended on October 28, 1985. However, the Board withheld filing of
the rules as requested by JCAR. A Board representative attended
the November 14 JCAR meeting. On November 18, 1985, the Board
received a letter of no objection from JCAR, In an Order adopted
this same day, the Board directed the Clerk to arrange for the
refiling without change of the temporary rules adopted in R84-22B
as permanent rules in this docket R84-22C.
In a related matter, on October 10, 1985, the Board proposed
for first notice, in R84-22D, to amend the temporary and
permanent rules in response to JCAR comments received in
connection with R84-228.
At. the outset, the Board notes that the scope of the pending
R84-17 proceedings, or any other proceedings concerning “Chapter
7 and 9,” is not intended
to be limited
by
any overlapping
issues
that may have been addressed in
this R84—~22 proceeding.
66-467

—6--
STATUTORY PROVISIONS
The non-hazardous waste permit requirement is contained in
Section 21(d) of the Act, which reads as follows:
No person shall:***
d.
Conduct any waste—storage, waste-treatment,
or waste—
disposal operations:
1. Without a permit granted by the Agency or in
violation of any conditions imposed by such permit,
including periodic reports and full access to
adequate records and the inspection of facilities,
as may be necessary to assure compliance with this
Act. and with regulations and standards adopted
thereunder; provided, however, that no permit shall.
be required for any person conducting a waste-
storage, waste-treatment, or waste-disposal
operation for wastes generated by such person’s own
activities which are stored, treated, or disposed
within the site where such wastes are generated;
or,
2. In violation of any regulations or standards
adopted by the Board under this Act.
The relevant portions of P.A. 83-775 are contained in
Section 21.1 of the Act, which reads as follows:
a. No person other than the State of Illinois, its agencies
and institutions, or a unit of local government shall
conduct any waste disposal operation on or after March
1, 1985, which requires a permit under subsection
(d) of
Section 21 of this Act, unless such person has
posted
witti the Agency a performance bond or other security f~or
the purpose of insuring closure of the site and post-
closure care in accordance with this Act and regulations
adopted thereunder.
h.
On or before January 1, 1985, the Board shall adopt
regulations to promote the purposes of this Section.
Without limiting the generality of this authority, such
regulations may, among other things, prescribe the type
and amount of the performance bonds or other securities
required under subsection (a) of this Section, and the
conditions under which the State is entitled to collect
monies from such performance bonds or other
securities. The bond amount shall be directly related
to the design and volume of the waste disposal facility.
c. There is hereby created within the State Treasury a
special fund to be known as the “Landfill Closure and
Post-Closure Fund~. Any monies forfeited to the State
66~488

-7—
of Illinois from any performance bond or other security
required under this Section shall be placed in the
“Landfill Closure and Post-Closure Fund” and shall, upon
approval by the Governor and the Director, be used by
and under the direction of the Agency for the.purposes
for which such performance bond or other security was
issued.
4. The Agency is authorized to enter into such contracts
and agreements as it may deem necessary to carry out the
purposes of this Section. Neither the State, nor the
Director, nor any State employee shall be liable for any
damages or injuries arising out of or resulting from any
action taken under this Section.
e. The Agency shall have the authority to approve or
disapprove any performance bond or other security posted
pursuant to subsection (a) of this Section.. Any person
whose performance bond or other security is’ disapproved
by the Agency may contest the disapproval as a permit
denial appeal pursuant to Section 40 of this Act.
f. The Agency
may
establish such procedures as it may .deem
necessary for the purpose of implementing and executing
its responsibilities under this Section.
g. Nothing in this Section shall
bar
a cause of action by
the State for any other penalty or relief provided by
this Act or any other law.
OVERVIEW
The following is a brief summary of the rules and major
issues. A detailed discussion appears below.
The rules implement the bond requirement of Section 21.1 of
the
Act
by requiring the preparation of closure and post-closure
care plans,
and
cost estimates based on these plans. The
operator is required to provide financial assurace in an amount
equal to the cost estimate. Financial assurance can be given by
several mechanisms, including a trust fund, surety bond,. letter
of credit, closure insurance, and, for non-commercial sites,
self-insurance.
1184—17
The rules rely on the existing closure and post-closure care
requirements for sanitary landfills in Part 807. These are
subject to revision in R84-l7. Operators will be required to
base cost estimates on the existing regulations pending
modification. Operators may be required to update plans in the
future to meet new regulations, and to provide additional
financial assurance.
86-469

—8—
SCOPE OF REGULATIONS
The rules primarily affect persons:
1) who conduct a “disposal” operation or an “indefinite
storage” operation; and
2)
who are required to have a permit (Section 21(d) of the
Act and Section 807.601); and
3) who receive waste for disposal or indefinite storage on
or after March 1, 1985; and
4) who
are
not a governmental unit.
Versons with permits who conduct other types of waste.
management operations, such as treatment and storage, will have
to comply with the general closure rules.
Those who have Section
21(d) permits will be required to file closure plans with their
next permit modification application (Section 807.205).
Persons who conduct waste management operations but are
exempt from the permit requirement must comply with the
general
closure rules, but need not prepare plans or provide financial
assurance (Section 807,501).
Sites which stopped accepting waste for disposal or
indefinite storage by March 1, 1985, will not be required to
provide financial absuratlee (Section 807,601),
The governmental units exemption applies only to persons
which “conduct” waste disposal operations.
Private contractors
who conduct operations on a site owned by local government must
provide financial assurance (Section 807.601).
PHASE-IN PROVISIONS
Under the rules operators had three choices on March 1,
1985, They could avoid the financial assurance requireiiient by
ceasing to accept waste and initiating closure pursuant to
existing permit conditions.
Alternatively,
they could provide
financial assurance either by preparing a closure and post-
closure care plan and cost estimate, or by submitting a cost
estimate based on the interim formula (Section 807.624).
Operators who utilized the interim formula will be required
to prepare closure and post-closure care plans and cost estimates
with the next application to modify the permit, or by March 1,
1988 at the latest,
SELF- INSURANCE
The Board has limited self—- insurance to those operators who
meet the USEPA financial test, and who derive less than half
66-470

—9--
their revenue from waste
disposal operations.
Self-insurance
will
be available to few sites, since on-site disposal generally
i~s not subject
to the permit or financial assurance
requirement. The Board has provided self-insurance as an option
For any on-site operators which might be subject to the permit
requirement, or for diversified firms which also conduct waste
.lisposal operations.
OTHER FINANCIAL MECHANISMS
Several alternative
financial
mechanisms were
suggested at
~he hearings. These included an escrow account, a savings
account, a cash deposit with the Agency and a risk pool (R. 194,
237, 240, 242, 248, 279, 288).
The escrow
account is similar to a trust,
and should be
available from~ basically
the same banks at a similar cost, t’~
savings account in the Agency’s name would not be secure in the
absence of a formal trust agreement
stating the trustee’s duties
and preventing the operator’s creditors from seizing
the account,
A cash deposit with the Agency might be a very desirable
mechanism.
It would save operators administrative
costs, and
give the State greater security. However, the landfill closure
and
post-closure fund can receive only
money which
is
“forfeited,”
and cannot refund money following proper closure by
the operator. If the Board were to allow use of the fund as a
pooled trust fund, there would be a possibility that the money
would be treated as general revenue to the State, and be
unavailable for closure of any site in the absence of an
appropriation.
Another possibility is establishment
of a
risk pool to which
each operator contributes during the active life
of the site.
The Board lacks the authority to create a fund in the State
Treasury, and to
obligate the State to pay money out of such a
ft,vncL In addition, this would require continuing oversight of
rates and an administrative apparatus to collect premiums and
handle
claims, each of which would require express authority and
an appropriation.
NUMBER OF SITES AFFECTED
The EcIS identified 209 landfills, Of these, 14~ were
privately owned and operated. Another nine were municipally
owned and privately operated. The EcIS was based on these 152
sites thought to be subject to the financial assurance
requirement. (R. 1064, 1149; EcIs p. 54) The Agency believes
that around 168 sites are subject to
the
financial assurance
requirement. (R. 1104)
66-471

-10-
ECONOMIC IMPACT
The following is a summary of the economic impact of the
financial assurance regulations and requirement.
More detailed
discussions of various aspects of the economic impact is
included
with the detailed disucssion of the rules which follows, In
particular, the closure and post-closure care cost elements are
discussed with the Board’s interim formula, and the costs of the
instruments are discussed with each type of instrument.
The EcIS attempted to quantify the costs of the financial
assurance requirement of Section 21.1 of the Act rather than the
costs and benefits of the financial assurance rules.
The
costs
of the financial assurance requirement itself would have been
incurred regardless of the Board rules, and so properly should
have formed the baseline of the study. From a review of the
study and hearings the Board has not been able to identify any
costs or benefits associated with the way the Board implemented
the financial assurance requirement apart from the cost of the
financial assurance requirement itself. The Board therefore
determines that there is no adverse economic impact on the people
of the State.
The EcIS did estimate the costs and benefits of the
financial assurance requirement itself. These are summarized as
follows.
The contractor reviewed the 209 sites to determine their
daily volume of waste received, open acres and total site
acreage. (EcIS p. 54) The aggregate closure and post-closure
care cost to the 152 sites subject to financial assurance was
determined using the Board’s interim formula and using the
contractor’s own formula. The aggregate cost estimate under the
interim formula was nearly $18.6 million, and, under the
contractor’s formula, nearly $9.0 million, (EcIS p. 59, 64) This
would result in a financial assurance cost of around $450,000
during 1985, assuming the most likely mix of financial
instruments? (EelS p. 66) This would reduce to around $230,000
per year by 1988 when all sites should have cost estimates based
on plans, which the study determined would result in lower cost
estimates. (EelS 66).
The study concluded that the Agency would spend around
S15,000 to $61,000 per year administering the financial assurance
proram. (EcIS p.67) The study
did not attempt to quantify the
benefits of the financial assurance requirement. (EelS p.76; R.
1062, 1088)
SUBPART A:
GENERAL PROVISIONS
Section 807.104 “Abandonment”
“Abandonment” means the failure to initiate closure within
30 days after receipt of the “final volume of waste”,
Section
86-472

—11—
807.503 requires the operator to give notice to the Agency of
receipt of a final volume within 30 days; Section 807.506
-
requires the operator to initiate closure within the same time
period. Abandonment is a condition which triggers liability by
financial institutions (Sections 807.662 et seq.) (R. L6, 117,
141, 429, 496, 688, 965).
Section 807.104
“Compaction”
A definition of “treatment” appears below.
“Treatment”
includes “reduction in volume.” The Board
has referenced the
definition of “treatment” in the definition of “compaction”
(R. 16, 933).
Section 807.104
“Development”
“Facility” has been changed to “unit” to agree
with
terminology which is described below (R. 16).
Section 807.104 “Disposal”
Section 21(d) of the Act requires ‘—a permit for anyone who
conducts a “waste-storage, waste-treatment, or waste-disposal
operation.” with certain exemptions. Section 21.1(a) prohibits
the conduct of any waste disposal operation, for which a permit
j~required, without a performance bond or other security, The
definition of disposal is therefore essential tO the scope of the
permit requirement and to the decision as to which sites must
provide financial acsurance (R. 17).
The definition is taken from Section 3 of the Act, with the
Final sentence added: “As used in this
Part, ‘disposal’ includes
methods of
storage
or
treatment in
which there is no certain plan
to remove wastes or waste residues from the storage or treatment
unit to another unit for ultimate disposal.” “Indefinite storage”
has been defined below to cover situations
in which there is a
plan, but there may be technical or economic obstacles to
actually implementing the plan. Persons who store waste with no
plan for disposal, or with an unworkable plan, will have to
provide financial assurance as though they were operating
disposal sites (R. 428, 434, 439, 445, 447, 456, 462, 960).
Section 807.104 “Facility”
As used presently in Part 807 “facility” refers to a portion
of a “site” used for a regulated activity. This conflicts with
the usage in the RCRA program in which a “facility” is roughly
equivalent to the entire “site” (Section 720.110). The Board has
replaced “facility” with “unit” as the preferred term to be used
when
referring to a portion of a “site” (R. 17).
88-473

—12—
Section 807.104 “Final Volume of Waste”
A quantity of waste is assumed to be the “final volume” if
the operator receives no additional waste within 30 days
thereafter. The operator can overcome the presumption by
(lemonstrati-ng that he expects additional waste (R. 429).
Receipt
of the final volume starts the 30 day
period in which the
operator must notify the Agency and initiate closure (Sections
807,505 and 807.506). Failure to do so is “abandonment” which is
a condition triggering liability by a financial institution
(Sections 807.662 et seq.).
Abandonment of a general waste site is likely to consist of
cessation of activity because of financial difficulty,
or, in the
case of very small sites,
che
death or illness of a sole
proprietor. The site will be left unattended, with open dumping
of refuse without compaction or daily cover (R. 786, 966). Such
waste would
not be received “by the operator”, and would not
affect the question of whether an earlier volume was a “final
volume”.
Section 807.104 “Hazardous Waste”
This definition controls the exclusion of “hazardous waste”
from the
permit requirement
of
Section 21(d) of the Act. The
Board has incorporated the elaborate definition of Part 721.
This definition is
not identical to the definition in the Act.
The
Board was obliged to adopt the Part 721 definition pursuant
to Section 22.4(a) of the Act. It fixes the scope of the RCRA
permit requirement of Section 21(f) of the Act. Utilizing the
same definition of
hazardous waste •here assures that hazardous
waste which is exempt from the Section 21(d) permit is within the
Sect-ion 21(f) RCRA permit requi~rement--(R. 17).
Section 807,104 “Indefinite Storage”
“Indefinite storage” is a type of “treatment” or “storage”
in which the operator has a plan to remove wastes or residues
from the unit, but technical or economic considerations may make
it difficult to remove the wastes or residues prior ~to closure.
Wastes are presumed to be in indefinite storage if they remain in
a unit for more than one year. The operator is required to
prepare contingent closure and post-closure care plans and
provide financial assurance in an amount sufficient to close the
indefinite storage unit as a disposal unit.
This definition closes a loophole in the proposal which
would have allowed an operator to avoid the financial assurance
requirement by declaring disposal to be storage. Two examples
would include speculative recycling of a waste which may someday
become valuable, and operation of a percolation and infiltration
lagoon. In the first case, if the
waste becomes
valuable it will
be sold. However, to satisfy the intent of Section 21.1, the
operator must provide financial assurance to close the
86-474

-13-
accumulated waste as a landfill if the waste cannot be sold and
it is too expensive or difficult to remove it to a landfill. In
the second case, wastes are pumped to an unlined lagoon for
treatment or storage without periodic removal of wastes or
residues, some of which may migrate into underlying soils. It is
likely that such a lagoon will have to be closed as a landfill
because of the cost and technical difficulties of removal (R.
362, 428, 434, 439, 445, 447, 456, 462, 506, 687, 960).
Section 807.104 “Modification”
“Facility” has been changed to “unit” (R. 18).
Section 807.104 “Operator”
The “operator” is the person who conducts a waste treatment,
storage or disposal operation which requires a permit pursuant to
Section 21(d) of the Act. The “owner” is not necessarily the
operator (R. 18, 23).
Section 807,104
“Owner”
The “owner” owns the land on which someone conducts a waste
treatment, storage or disposal operation. If there is no other
person conducting operations, the “owner” is also the “operator”
and subject to
the
permit requirement of Section 21(d) of the Act
(R. 18, 23). This language was modified pursuant to JCAR staff
comments.
Section 807.104 “Refuse”
“Refuse~has been replaced with the preferred term “waste”,
which is used in Section 21(d).
Section 807,104
“Salvaging”
“Solid waste” has been replaced with the preferred term
“waste”,
Section 807.104 Scavenging”
“Facility” has been replaced with the preferred term “unit”.
Section 807.104 “Site”
The definition has been modified to make it clear that the
term “site” refers to the area around a regulated “unit” and that
~ “site” may include one
or more such “units”.
The definition of “site” is important in the on-site
exemption from the Section 21(d) permit requirement. No permit
is required for a “unit” which is on the same piece of real
estate as the operation which generated the “waste” and which is
under the control of the same entity which generated the waste
(R. 19, 22).
66-475

-14-
Section 807.104 “Solid Waste”
This is modified to reflect the preferred term “waste”.
Section 807.104 “Solid Waste Disposal”
This concept has been replaced by the definitions of
“disposal” and “waste”, the terms used in Section 21(d) of the
Act.
Section
807.104
“Solid Waste Management”
This has been replaced by the
preferred term “waste
management”.
Section 807.104 “Storage” and ~Treatment”
These definitions are taken from Section 3 of the Act. They
are used in Section 21(d) to fix the scope of the permit
requirement.
Section 807.104 “Unit”
This term replaces “facility”. The phrase “device,
mechanism, equipment or area” is taken from the old definition of
“facility”. The rest of the definition has been reworded to read
“used for storage, treatment or disposal of waste” to agree with
the terminology of Section 21(d) of the Act (R. 21, 24,
2.7).
Section 807.104 “Waste”
This definition fixes the scope of the permit requirement of
Section 21(d) of the Act insofar as subject matter is
concerned. The definition is taken from Section 3 of the Act.
At the request of the JCAR staff citations to statutes and
regulations have been added.
Section 807.104 “Waste Management”
This definition is taken from the old definition of “solid
waste management”. The terminology has been Changed’ to refer to
“storage, treatment or disposal of waste” to reflect the
terminology of Section 21(d) of the Act. This is a generic term
for any activity subject to the permit requirement.
SUBPART B: WASTE PERMITS
Section 807.205 Applications for Permit
At
the request of the JCAR staff, the term “facility” has
been removed from para. (a). Either “unit” or “site” would he
appropriate in this paragraph.
66-476

—15—
The Board originally proposed to delete para.
(j),
which
created
a third party appeal right which was ruled invalid, since
i~t was not specifically authorized by statute, in LandfiLl Inc.
v. Tilinois
Pollution Control Board, 74 111. 2d 541, 387 N.E. 2d
‘23r11g78). However, the Act has since been amended to add
certain third party appeal rights to Title X. The Board
therefore retained para.
(j)
in the second notice order, but
prefaced
it
with
the phrase “If specifically authorized by
statute.” Pursuant to JCAR staff comments, the Board has
stricken the phrase “adversely affected by the issuance of a
permit” from the old language. This appeared to place a
condition on statutory rights of appeal.
Paragraph (1) requires that applications contain a closure
plan and a post—closure care plan showing how the operator will
provide closure and post-closure care in accordance with all
applicable regulations,
which will be discussed below (R. 35,
953). Original cost estimates will also be required with the
application (R. 361). Actual financial assurance need not be
tendered until
just prior to receipt of waste (Section 807.602).
The Board has modified para. (1) pursuant to JCAR staff
comments. Whether an application must contain plans and cost
estimates depends on Subparts E and F. The operator needi~
to
show compliance with applicable “Board” regulations.
Section
807.206 Permit Conditions
Secticn 21(d)(1) contains
a specific authorization for
permit conditions involving reports, access to records and
inspections. This has been added to
the existing general
language of Section 807.206(a), which is derived from Section
39(a) of the Act (R.
37).
Section 807.206(c) contains a listing of permit conditions,
related to financial assurance, which must be
in
all permits.
T1ie conditions are as follows with the related Section indicated:
1,
A closure plan (Section 807.503);
2~
For disposal sites, a post-closure
care plan (Section
807,523);
3. A requirement that the operator notify the Agency within
30 days after receiving a final volume of waste (Section
807,505);
4. A requirement that the operator commence execution of
the closure plan within 30 days after the site receives
its final volume of waste (Section 807.506);
5. A requirement that the operator file any final
application to modify the closure plan at least 180 days
orior to receipt of the final volume of waste (Section
807.505);
66-477

—16—
6. A requirement to provide financial assurance in an
amount equal to the current cost estimate (Sections
807.601 and 807.603);
7. A requirement to update the current cost estimate every
other year (Section 807.623).
Section 807.209 Permit Revision
Section 807.209(b) provides that a permittee may request
modification at any
time by filing
an application reflecting the
modification. This appears to be the existing Agency
interpretation
CR. 42, 362, 941).
Section 807.214 Revised Cost Estimates
This Section relates to the biennial cost adjustment of
Section 807.623~ Cost adjustments which do not result from
modification of a closure or post-closure care plan are a special
type of permit application in which the operator needs to provide
only minimal information, This provision does not require the
Agency to take affirmative action, However, the Agency can deny
the application within 90 days if the cost estimate does not
relate to the plan or if the Agency does not agree with the costs
(R. 951).
SUBPART E: CLOSURE AND POST-CLOSURE CARE
Section 807,501 Purpose, Scope and Applicability
Subpart E establishes general rules on closure and post-
closure care which are supplemented by the sanitary landfill
closure and post-closure care rules of Subpart C. Subpart E
requires that operators of sites with permits prepare closure and
post-closure care plans which will become permit conditions. The
plans will form the basis of the cost estimate of Subpart F,
which fixes the amount of financial assurance which must be
provided.
Sites which are not required to have Section 21(d) permits
are not required to prepare plans, or to provide financial
assurance CR. 68, 85, 90). Existing sites which are required to
have a permit may elect to utilize the formula of Section 807.624
in lieu of preparing plans and a cost estimate to meet the March
1, 1985 date, Such sites will be required to provide closure
plans with the
next
modification application or
by March 1, 1988
(Sections 807.205 and 807.624).
Section 807.502 Closure Performance Standard
This Section contains the general standard for closure of a
waste management site, The operator must close the site in a
manner: which minimizes the need for further maintenance; and
86-478

—17—
which controls~ minimizes or eliminates, post-closure release of
waste, waste constituents, leachate, contaminated rainfall, or
waste decomposition products to the groundwater or surface waters
or to the atmosphere to the extent necessary to prevent threats
to human health or the environment (R. 69, 166).
This general standard is supplemented by the specific
closure requirements for sanitary landfills which are listed
below. All waste management sites must meet the general closure
standard, but only sanitary landfills need meet the following
specific rules (R, 69, 95, 154, 682, 953):
Section
807.305
A total of two feet of final cover within 60
days following the placement of refuse in a
final lift,
807.313
Prohibition
on discharge of contaminants
807.314(e)
Adequate measures to monitor and control
leachate
807.315
Prohibition on damage to waters of the State.
807.316
Closure plan required in application.
807.318
Monitoring of gas, water and settling for
three years after closure; maintenance
during
the three year period; filing of a piat.
The closure standard requires closure so as to prevent post--
closure release of “waste constituents” and “waste decomposition
products”. This is not to be construed as an absolute
prohibition on release of water or gas from the completed
landfill.
Control is required only “to the extent necessary to
prevent threats to human
health or the environment” CR. 166,
955),
The closure performance standard, which is a minimal
standard
to avoid gross pollution, applies to all sites, whether
required to have a permit or not
CR. 56, 111).
Section 807.503 Closure Plan
The closure and post-closure care plans will become
conditions of the site permits. Modification of the plans will
require permit modification. The Agency can deny a permit
because of deficiencies in the plans, or it can issue a permit
with modified plans.
A possible alternative is a rule which just requires
preparation
and maintenance of
a
plan
even by permit~:ed sites.
This is what is
required in the RCRA
interim status rules at 35
66-479

-18-
Ill. Adm. Code 725,212. This alternative has been rejected for
two reasons. First, in a scheme where permits are actually
required, it seems unwise to leave an element so essential
to
protection of the environment out of the permit. Second, because
the plan is essential to the cost estimate and amount of
financial assurance, prior Agency review is necessary to
accomplish the purposes of Section 21.1 of the Act (R. 71, 99,
848, 850). However, the Board has allowed cost estimates based
on a formula without plans during the initial transition period
(Section 807.624). During the next three years operators will he
required to formalize plans only with the first permit
modifications.
In addition to forming the basis for the cost estimate, the
plans form the basis for the determination as to whether a site
is a treatment or storage unit on the one hand, or a disposal
unit or indefinite storage
unit on the other. Under the
definitions in the
Act and Section 807.104, treatment and storage
involve temporary placement of waste, while disposal involves
permanent
placement, or loss of the
waste into the background.
Indefinite storage involves
storage
under circumstances in which
costs
or technical difficulties will force closure as a disposal
unit. Only
sites with disposal units and indefinite storage
units are required
to
provide financial assurance.
Existing Sections 807.316(a)(1O), (a)(14), (a)(15)(A) and
(a)(15)(K) require virtually the same material in sanitary
landfill applications as is required in
the proposed closure plan
rules. However, these are usually not brought together into a
single portion of a permit identified as a closure plan CR. 685,
697, 715, 725),
The operator must prepare a closure plan detailing steps
necessary for final closure at the end of the intended operating
life and a plan for premature final closure at the point in the
intended gperating life when the cost of closure will be the
greatest. Although these could coincide, some landfills would
be expected to reach the point of maximum cost exposure early in
their operating life CR. 119, 286, 363, 416, 430, 688, 719, 7.56,
763, 780, 848, 854), The plan for premature closure forms the
basis of the cost estimate.
The possibility of a default by a
landfill operated according to the rules and permit conditions up
to the end of its intended operating life is remote (R. 684, 725,
756). The primary risk intended to be addressed is that of
premature closure by a landfill which has not been properly
operated.
The premature closure plan should give a better
indication of the cost
involved in such closure.
point in the intended
operating life when the cost of
closure will be the greatest is referred to as the “point of
maximum exposure’ or the “point of maximum cost exposure” in this
Opinion.
66-480

—19—
The closure plan must specify both the year of intended
closure and the year in which the cost of closure is expected to
be greatest. These are important to determination of the pay-in
period if financial assurance is provided through a trust fund
CR. 364, 431, 683, 687).
The operator must include a temporary shutdown plan if the
operator wants a permit which would authorize temporary
suspension of waste acceptance prior to final closure CR. 51,
78). A seasonal operation or one which could be affected by
strikes should apply for a temporary shutdown plan. The language
was modified pursuant to JCAR staff comments to
use
“suspension
of waste acceptance” in the rules.
Temporary shutdown is to be distinguished from partial
shutdown which involves closure of a portion of a site while
operations are ongoing on another portion CR. 51, 78, 92, 142,
363, 430. 688). Partial shutdown
may
be addressed two ways.
First, the operator can ask that the permit be modified to
specify certain “areas” pursuant to Section 807.307. The
operator could then prepare separate plans and coat estimates for
each area, providing financial assurance when waste is first
disposed in each area, and obtaining release with respect to
closure costs when closure is completed. Alternatively, the
operator could allow for the opening and closing of units in a
single plan, identifying the situation in which the greatest cost
exposure would occur. The operator could then post a bond in the
amount required to close the site at the point of greatest cost
exposure.
The proposal required that, a copy of the closure plan be
kept at the site so that it would be available to the Agency
inspectors. This could impose a hardship in that many general
waste sites lack a permanent structure which would be a suitable
repository. The Board has modified the proposal to require the
plan to be maintained at a location, approved in the permit,
where it will be available during inspection of the site.
Section 807.504 Amendment of Closure Plan
This Section is similar to Section 724.212Cb) in the RCRA
rules. It specifies the situations in which the owner or
operator must revise the closure plan:
*
1. Modification in the operating plans or site design
affecting closure.
2. Temporary suspension of wine acceptance, or reduction
or increase in volume.
3.
Change in the expected year of closure, or the year in
which the cost of premature closure will be the
greatest.
66-481

-20-
Under Section 807.209 the operator ~‘ald be eH.~
I’
an application
to
modify at any .ime. Section 807.504 $
;it’nded
1i~rit
!i~
operator’s rig to am’
,
but
at I
c.. Latn
jqi’ua’in’ in
which he must amend.
F’i’ ;2cend
,•,
I third situations under
a”
the
must
be
amended are directed in
part
at sites which ~o into
t
temporary nr partial .qhutdown which is not provided I.r
ii’ flu’
closure plan. Violations of Section 807.504(b) or Cc)
eoizi
I
hr
ill aged if activity slowed or
ceased at the site without in
‘n’nded plan. Section 807.503 allows the operator to prov
i.!.’
iprary shutdown plan which will not trigger the need
t~
mien’
the ‘losure plan. Existing Section 807.3161a)C12) requir~’~‘s3
‘~.
tator
to
specify expected quantities of waste In the
‘:
Itcation. The proposal has been modified to speeificail
te that changes, reductions or increases which are au
n
by
the
permit do not trigger the requirement to amend CR.
93,
‘a,
374, 496, 688, 780, 786).
Section 807.505 Notice of Closure and Final
~mnndmenL
~n
I~
ir
Section 807.505(a) requires the operator to give
not te~to
the Agency within 30 days after
receipt of the final vol‘ime
‘t
4aste. Violation of this section could be alleged Ln a s-. uittoe~
in which an operator abandoned a site without notice.
Section 807.505(b) requires any final amendment to dia
•flosure plan to be filed at least 180 days befpre receipt o: the
final volume. The Agency would be allowed to act on the late
application, but violation could be alleged in an enforcement
ir
au. This requirement serves two purposes. First,
it
should
~.‘ns.sre that the Agency will
have adequate time to review these
t
•.
:ions. Second, it encourages operators to maintain a
rea~cte closure plan which is up—to-date with current
operati)ns so that it could actually be executed in the event of
unexpected cessation of operations CR.
74,
82, 938).
Whether an operator must send a notice of partial closure
Japends on whether the site has been divided into areas undet
3.3.tlton 807.507 CR. 430, 687). If there are such areas, the
operator must send notices as though they were separate
siteq.
Otherwise, notice need not be sent until final closure is
reached. However, such partial closure activities would have
to
procee~daccording to the permit.
Se:tjon 807.506 Initiation of Closure
This requires
that
the operator commence tteatment, removal
or disposal of all wastes from the site in accordance with the
‘°ure plan within 30 days after receipt ~? the fLna~ volume of
This
rule
cerves two purposes. First, it establishes a
-
“me tc”
.loea~eto be conside...! y the Agency in
~3ii~wJ
-
a
c.. asure ;an. Second, a violation could be alleged
~ tn oparato: ?bandor3d a site CR. 75, 367, 959).
66-482

-
2.1
The operator
of an indefinite storage unit must either
initiate removal of wastes and waste residues, or
must
initiate
cTosure in accordance with the contingent closure plan.
Section 807.507 Partial Closure
Paragraph (a) allows the
operator to file an applicat:ion
with the Agency dividing the site into areas,
Each area must
include at least one entire unit,
If the permit specifies such
areas, the Agency
is to treat them as separate sites for purposes
oF
financial
assurance. This means separate closure plans and
cost estimates. The operator could provide separate financial
assurance for each
area,
or could lump pursuant to Section
807.642 (R.
5i~78, 92, 142, 363, 430, 433, 688, 957),
The Board construes Section 2.1.1 as requiring financial
assurance for closure of any treatment or storage units
associated with a disposal unit which are located on
the
same
site, JCAR considered this, but made no objection. However, it
recommended that the Board seek legislative clarification,
Paragraph (b) prevents the use of the area mechanism to evade the
requirement of financial assurance for associated treatment and
storage units, Although they could be placed in separate areas,
Financial assurance would have to be provided.
An operator can group units which are already closed into
areas which are already in post-closure care. The Agency should
not require closure plans or
cost estimates for these areas.
However, paragraph
Cc)
provides that post-closure
care continues
until the entire site is closed. The operator cannot use this
mechanism to cut short the post-closure
care for the site
required by Subpart C.
The proposal contained a section specifying duties of the
operator during closure. This has been dropped
as
inconsistent
with Section 807.502 CR. 75, 367, 372).
Section 807.508 Certification of Closure
When closure is
completed the operator and his
engineer
provide an affidavit to the Agency. When the Agency determines
that the site has
been
closed in accordance with
the plan, it
notifies
the operator of the
date on which the post-closure care
period begins
CR. 76, 144, 155,
163, 165, 368, 421, 959),
The Board
has dropped
from the proposal a requirement that
the operator
specify the
locations of special waste in the as-
built plans CR, 163, 165, 368, 688).
Section 807.509
Use
of Waste
Following Closure
After closure
an operator may accept waste as authorized in
the closure plan.
Operators often utilize construction
debris
as
,part
of cover material
or for subsidence
and erosion control (R.
o83), The
Agency may control such usage
by permit condition.
66~483

-22-
Section 807.523 Post-closure Care Plan
N~o
general standard for post—closure care has been
proposed.
The operator will have to prepare a plan
shOW:Lflg
how
he
would
comply with the post-closure care provisions specified
in
the
rules specific to each type
of disposal facil:ity.
presently these
would only be
the rules applicable to
sanitary
L-indfills CR. 77, 369, 449, 458).
Operators
of indefinite storage units must provide ~
contingent post--closure care plan which will have to be executed
ii the operator fails to remove all wastes and
waste
residues on
closure CR. 36~). £448, 455),
Section 807 .52’~ Implementation and Completion of post-closure
Care Plan
The opera~:orof a disposal site must implement the post-
closure care
~
commencing with certification of closure
(R. 77, 371).
Tho
operator of an indefinite storage
unit must
implement the cor~:ingent post-closure care plan unless
the Agency
determines that ho removed all wastes and waste res idties
dur ing
the
closure period.
The Agency
~S
to certify that the post-closure care period
has ended when ir.. determines that the post-closure care plan has
been completed and
that the site will not cause future
violations. The length of the post-closure care period for
sanitary
landfills is determined from the existing Subpart C
rules (R. 371).
SUBPART F:
FINANCIAL ASSURANCRE
FOR CLOSURE
AND POST-CLOSURE CARE
3ection 807.600
Purpose, Scope and Applicability
HfinancialThis
Subpartassurance”providesto
satisfythe
methodthe
requirementby
which theof operatorSection
21.1gives
of the Act. The operator prepares closure and post-closure care
pians
pursuant to Subpart E. Operators of non-governmental
disposal sites prepare cost estimates based on these plans. They
i-iust provide financial assurance
in an amount equal to the cost
estimate. Several mechanisms are provided by which the financial
assurance can be given.
Section 807.601
Requirement
to Obtain Financial
Assurance
This Section paraphrases Section 21.1(a) oF the Act.
The
phrase “unless such person has posted with the Agency a
performance bond or other security for the purpose of insuring
closure of the site and post-closure care in accordance with the
Act and regulations adopted thereunder” has been replaced with
~‘unless such
pooson
has provided financial assurance in
accordance
with ch:Ls
Subpart”. The Subpart defines and
implements the ~irst-quoted language.
66-484

—23-
The Section also states the requirement to çbtain financial
assurance for an indefinite storage unit. This is defined,
in
Section 807.104. As is explained above, these units must be
required to provide financial assurance to satisfy the purposes
of Section 21.1 of the Act.
Paragraph (a) includes the local government exemption taken
from Section 21.1(a) of the Act. The Board construes this
exemption to apply only when the governmental unit is actually
conducting waste
disposal operations: that is, when the
governmental unit is the ‘operator” If the governmental unit is
the “owner” of the site, but another person “conducts” waste
disposal on the site, the other person must provide financial
assurance for closure. A proviso has been added to state this
expressly CR. 53, 64, 686, 782, 943). SCAR considered this
matter and did iot object to the Board’s interpretation of the
statute.
Paragraph Cb) interprets the requiçement to provide
financial assurance by March 1, 1985. Sites which accept waste
for disposal or indefinite storage after
that
date will be
required to provide financial assurance, including both existing
sites and future sites.
Section 807.602 Time for Submission of Financial Assurance
Sites existing on March 1, 1985 must provide’financial
assurance by that date. Future sites will be required to provide
rinancial assurance prior to waste receipt. Plans and dost
estimates must be provided with the permit application. The
Agency will issue the operating.’permit with requireánts to
provide financial assurance as conditions, including a
requirement to tender financial assurance prior to redeipt of
waste. There is nothing to keep the operator from tendering
the
financial assurance prior to permit issuance CR. 35, 262, 390,
460, 938).
Section 807.603 Upgrading Financial Assurance
The operator has 90 days to increase the amount of financial
assurance if the cost estimate goes up or if the value of a trust
fund goes down or if the operator is disqualified from self-
insurance. Otherwise, the operator must maintain the financial
assurance at least equal to the cost estimate at all times. For
example, the operator must anticipate the cancellatipn or
termination of financial instruments and substitute alternative
instruments in advance of cancellation or termination’. These
provisions were with Sections 807.661 et seq. in the proposal,
but have been grouped in the”emergency rules.
06485

-24-
Section 807,604 Release of Financial Institution
There are three types of releases which were provided with
~ach instrument in the proposal. These have been grouped into
separate sections for each type of release:
Section
807.604 Release of financial institution following a
substitution of financial assurance or release of
the operator.
807 .606 Release of the operator upon completion of closure
and post-closure care.
807 .661 Partial release of financial institution
et seq. following a reduction in cost estimate.
Partial release following completion of closure is to be
treated as a reduction in the cost estimate by reducing to zero
the closure cost element.
Section 807.605 Application of Proceeds and Appeal
There are basically two extreme enforcement situations which
could arise involving closure. In the simple situation the
operator is bankrupt or
has
simply abandoned the site and it will
clearly be up to the Agency to arrangs for closure. In the
complex situation, the operator is onthe site, but the Agency
alleges violation of the rules and believes that closure is
necessary to protect the environment. • In the complex situation
an enforcement action must be brought before the Board. If the
Agency proved a violation, the Board could order that a closure
plan be implemented, and that the proceeds of financial assurance
be available for execution of the plan. In the simpler case this
would be a needless formality CR. 116, 965).
The financial assurance instruments are governed by the
general Illinois law pertaining to trusts, bonds, etc. If the
conditions of the instrument obtain and ths Agency gives the
required notices, but the financial inititution refuses to pay,
the Agency should sue in Circuit Court, or whatever court may be
appropriate. The filing of an enforcement action is not
necessarily
$
condition precedent. However an enforcement action
may be necessary to establish that the condition of the financial
instrument has obtained.
Section 807.605Cc) lists seven Agency actions which are
deemed permit denials. These are tantamount to disapproval of a
bond and are appealable as provided in Sections 5Cd) and 21.1(e)
of the Act. The necessity for Circuit Court resolution of these
disputes is avoided by providing an appeal route CR. 118, 141).
66-486

-25-
Section 807.606 Release of the Operator
The Agency is required to release the operator from the
requirement to maintain financial assurance for closure within 60
days
after receipt of affidavits from the operator and
his
engineer that the site
has been closed
according to the plan.
Paragraph (b)
includes a similar provision for post-closure care
(R. 118, 161, 384). The Agency can withhold release if it has
reason to believe the closure has not been in accordance with
the
plan, or that continued post-closure care is required by the
rules,
Section 807.620 Current Cost Estimate
The proposal differs from the RCRA rules in that under the
hoard
rules cost estimates for closure and post-closure care are
contaLned
into a single cost estimate. The operator must
give
financial
assurance in this amount. This reduces the volume of
rules, but creates possible problems relating to release of
closure assurance (R. 118, 384, 967). The rules do not prevent
an
operator from providing separate financial assutance for
closure and post-closure care. The operator could obtain release
of the financial assurance for closure by modifying the cost
estimate on closure, reducing to zero the closure cost estimate.
Section 807.621 Cost Estimate for Closure
The operator is required to maintain a written estimate of
the cost or closing the site. The cost estimate will be a permit
condition, although revision of a cost estimate can be
accomplished under Section 807.214 without filing a complete
application (R. 119, 143, 385, 450).
The operator must estimate the “current cost”
ot~
closing the
site assuming the work were to be
done tomorrow. This is not to
be discounted for the time lag to expected closure, nor is there
to
be an allowance for potential earnings of sums set aside for
closure, or for inflation, These matters are addressed through
pcriodic revision of cost estimates and evaluations of trust
funds (R. 457). The term “current dollars” used in the proposal
has been removed at the request of the JCAR staff, because of
possible confusion on
this point.
The operator must revise the closure cost estimate whenever
a change in the closure plan
increases the cost of closure. The
operator must also update the cost estimate at least once every
two years (Section 807.623).
The cost estimate must be based on the steps necessary for
premature final closure of the site at the time in its intended
operating life when the cost of closure would be greatest, or at
the end of its intended operating life, whichever cost is
greatest.
As provided in Section 807.503, the operator must plan
for both of
these contingencies in the closure plan (R. 119,
385,
66-487

—26-
688, 719, 756). Once the
point of maximum cost exposure has
passed, the operator can revise the plan to reflect any decrease’!
maximum future exposure.
The cost estimate must be based on third party costs: the
operator must assume that the Agency will contract w!Lh an
unrelated party to implement the closure plan. This will
probably be the situation if the operator becomes bankrupt or
abandons the site, so that the third party cost assumption forms
a better estimate of the potential liability (R. 304, 309, 385,
396, 454, 522, 700, 785, 1139),
The cost e~tirnatemay not include an allowance for salvage
value for waste or equipment, or the resale value of the
completed landfill. These items are speculative, and the value
may depend on whether the site has been properly operated and
closed, Since
the proceeds would be applied in a situation in
which the operator had failed in one of these areas,
the
salvage
value should not
be included in the estimate (R.
304, 307, 385).
The rule details the elements which go into the cost
estimate (R. 690, 849). This rule does not require that sites
provide these items on closure. However, they must be included
in the estimate if required for closure of the site.
The most important cost elements
are the area to receive
final cover
and the cost of obtaining and placing
the cover. If
an operator has an identified source of adequate cover on the
site, his closure cost estimate will likely be much less than an
operator who will have to purchase and transport cover to the
s±t:~(R. 690, 700, 719, 762, 1056, 1059, 1165).
The closure plan and cost estimate should only address the
activities which are to be done at the point of premature or
final closure. Activities which are done in construction or
normal operation of the site in anticipation
of closure should be
addressed in the construction or operating permit. The operator
should not be
required to pay for a closure activity and still
maintain
financial assurance for that activity.
Section 807.622 Cost Estimate for Post-Closure Care
The cost estimate for post-closure care is based on the
annual cost of monitoring and maintenance times the number of
years of post-closure care required. For sanitary landfills this
is three years (R. 120, 150, 386).
The cost estimate is based on the expected costs of post-
closure care as disclosed in the post-closure care plan (R. 120,
138). There is no provision for contingency funding to pay for
unanticipated costs such as might result from a liner failure or
retrofitting of a leachate collection system. Nor is there any
provision for third party liability insurance. Section 21.1 of
the
Act
is limited to financial assurance for the expected (~OsLS
of closure and post--closure care.
66- 488

-27-
The major cost elements include cover stabilization and
groundwater monitoring. The operator should estimate the
percentage of the cover which will require remed~.alaction to
control erosion or subsidence each year. The number of
parameters and frequency of groundwater monitoring should be
specified by the Agency in the permit (R. 385, 690, 700, 719,
724, 849).
Section 807.623 Biennial Revision of Cost Estimate
The proposal required the operator to adjust the cost
estimate for inflation on an annual basis based on the CNP
deflator,
Several revisions to the inflation adjustment
provisions were suggested at the hearings. These included:
1.
Prospective inflation adjustment at
the Out8et, in which
the operator projects an inflation
rate at the outset
throughout the expected operating life (R. 120, 693,
968).
2. Annual prospective adjustments
based on last year’s
inflation rate (R. 386, 397, 422, 424, 453, 457).
The problem with long-term prospective inflation adjustment
is that the formulas are very involved and the result is no
better than the inflation forecast. The Agency would have to
review economic forecasts. There would also have to be a
;r~echanism for reviewing the projected closure cost against actual
inflation, and a requirement of modification if they got too far
out of line.
Short-term prospective adjustment requires the operator to
estimate the cost today, then determine the cost to close in one
year, assuming the inflation rate in the coming year will equal
the rate during the preceding year. The cost to close in one
year would then become today’s cost estimate. This approach
reflects reality rather well, in that the operator is more likely
to close a year later than on the date the estimate is prepared
and last year’s inflation is a good estimate of next year’s.
However, it is likely to introduce a lot of confusion to gain an
adjustment which may be less than the other uncertainties
involved,
The Board has determined to utilize a biennial review of the
cost estimates, with adjustments to reflect actual changes in
cost elements. This gets the Agency totally out of the business
of reviewing inflation figures, and into reviewing actual costs
with which it should have ongoing experience. It would be
helpful if the Agency compiled current unit cost figures from
permits for distribution
to the public.
The biennial update will not be nearly so burdensome as an
annual update (R. 693). Also, the Board has provided an
abbreviated application mechanism for the revised cost estimates
~bich do not result from
a change in the plans (Section 807.214).
66-489

-28--
The operator is required to update the cost estimate at
Least once every two years,. If the operator updates the cost
estimate in connection with a permit modification before revision
is
due, the two years starts over.
Section 807.624 Interim Formula for Cost Estimate
The permanent structure of the rules follows the site-
specific plan/cost estimate approach. This has many advantages,
including the ability to accommodate site-specific factors, the
specification of duties on closure, and financial incentives to
adopt
operating modes with less cost exposure (R. 188, 290,
639). However, there were not enough engineers in the State to
prepare the needed plans and cost estimates by March 1,
nor
enough employees at the Agency to review the submissions (R. 179,
694, 768, 774, 7799 850,
852.,
876, 902). The Board therefore
adopted a formula which, although
it gives only
a crude estimate
of potential costs, can be used as an interim measure
to fix the
amount
The
of
EelS
financial
includes
assurance
formulas
0
which appear to relate total site
area and maximum open area to daily volume, based on the results
of a mailed survey, a review of the permit files and a 1981
inventory of sites. The formulas are on p. 57 of the Eels. Note
that “log” is intended to mean “natural logarithm”. (R. 1086)
It would be possible to write a rule basing cost estimates
on daily volume using these formulas, instead of requiring plans
bind
cost estimates. There are fundamental problems with such an
approach, and there is doubt as to whether the formulas are
valid,
If the formulas were written into the rules, the program
would lose the benefits of the site-specific plans and cost
estimates discussed above, In particular, there would be an
incentive to design landfills so as to take advantage of the
formulas, with no assurance as to whether the design would
actually result in a lower closure and post-closure care èost.
Furthermore, the formulas were
used by the contractor only
for interpolation purposes, not as a substitute for available
data. (R. 1165, 1167) The formulas have not been tested well
enough to base the rules on them. The data on maximum open area
was drawn from a small number of sites, and represents the
operators’ subjective estimates without field verification. (R.
1170, 1176, 1179) The formula for total site area appears to
give results two or three times larger than expected. (R. 1163)
Each operator will be required to file a closure plan and
cost estimate whenever he files the next application to modify
the permit. Plans and estimates will be required for all sites
by March 1, 1988. Operators will be allowed the option of
providing a plan and cost estimate initially, which they should
do if the formula disadvantages them (R. 880).
66-490

—29-
The cost estimate based on the formula will serve as a cost
estimate under the rules, The requirements to close in
accordance with
the plans will be understood to mean in
accordance with the existing permit conditions and closure and
post-closure care regulations for financial assurance instruments
based
on the formula.
The formula cannot be used to calculate financial assurance
under the RCRA rules.
The most important element of the cost estimate is the area
which will need final
cover, There are several considerations
affecting the
projection of this area, The first is the area
which is presently in need of final cover. This necessitates a
brief discussion of types of cover. Existing Section 807.305
provides for three types of cover:
a) Daily Cover
-
a compacted layer of at least 6 inches of
suitable material shall be placed on all exposed refuse
at the end of each day of operation.
b) Intermediate Cover
-
at the end of each day of
operation, in all but the final lift of a sanitary
landfill, a compacted layer of at least 12 inches of
suitable material shall be placed on all surfaces of the
landfill where no additional refuse will be deposited
within 60 days.
c) Final Cover
-
a compacted layer of not less than two
feet of suitable material shall be placed over the
entire surface of each portion of the final Lift not
later than 60 days following the placement oC refuse in
the final lift, unless a different schedule has been
authorized in the operating permit.
The Board construes Section 807.305 to mean that a total of
.~
least two feet of cover must be over the waste when closure is
completed (In re
Ch, 7, R72-5, 8 PCB
695, July 31, 1973; IEPA v.
Giachini, PCB 77-143;
3~3
PCB 547, May 24, 1979).
Many landfills apply intermediate cover to completed areas,
leaving final cover to closure of the entire site. Others apply
Final cover as
soon as an area or trench is completed (R. 768,
789, 798, 853, 855, 857, 869, 878, 904, 908, 910). Intermediate
cover is subject to erosion
if
it is not seeded and maintained
(R. 858). It is difficult to judge the depth and sufficiency of
the intermediate cover (R. 870, 905, 910). Because of the need
to base the formula on simple facts not likely to be subject to
dispute, the Board allowed deduction from the presently affected
area only the area which had received full final cover.
Most sites plan to apply final cover to much of the site
before final acceptance of
waste, such that only a very small
area is expected
to
remain on closure (R.
787). As has been
66-491

-30-
discussed above, the financial assurance requirement needs to be
based on closure at the point in the expected operating life when
the cost of premature closure would be the greatest, which may
not
correspond with the expected final closure. However, it is
not possible to determine the point of maximum cost exposure
without review of a site—specific plan. The formula has to use a
method for computing the maximum exposure with reference to facts
which are not likely to be subject to dispute.
Mr. Lynch suggested a formula which predicts the amount of
exposed refuse generated after a certain number of years, (Y),
based on the average depth (AD) of the landfill and the annual
volume of waste (AWR) received (R. 691, 703, 717, 723). It
should
he possible to determine both of these from the site
permit (Section 807.316). It
the permit is not up-to-date, it
should be
possible to measure the actual depth, and determine the
a~tualreceipts in recent years. The formula is
;is
fTollow~, with
the area in acres:
A
=
(Y)(AWR)
(3200)
(AD~)
It is necessary
to specify a value for Y, the number of
years of waste accumulation, Y is a projection of the number of
years which would elapse between the cessation of normal cover
activities by the operator and the initiation of site closure by
an Agency contractor. The formula will give the area to be
covered assuming people continue to dump at the same rate after
the operator stops covering. During this period the operator’s
non-compliance would come to the Agency’s attention, inspections
would be conducted, letters sent, enforcement initiated, hearings
held, an order entered and appealed, and a contract let. Based
on past experience, this would likely take three years (R. 671,
718, 729, 785). The Board has therefore assigned a value of
three to Y in the formula.
The acreage requiring cover is computed by adding the
presently exposed area to the projected exposed area whic.h could
he created within three years.
However, this cannot exceed the
total permitted area which has not received final cover as of
January 1,
1985.
The next major element in the formula is the cost per acre
(CPA). Most of this is the cost per cubic yard for cover
material. Ideally this should include the cost to purchase the
cover, lift it, transport it, spread and grade it (R. 698, 762,
847),
The Board received
three estimates of this cost:
Cost per
Cubic yard
$1.00
R. 692, 698
1.30
R. 763, 768, 771, 783
2.30
R, 847, 891, 897
86-492

-31-
These costs all assume that
cover material is available
within a short distance of the site (R. 692, 771, 847, 861). If
the cover must
be
transported a great distance, the cost would be
tour to five times greater (R. 692), The Board is prepared to
assume for purposes of the interim rule that
a source of cover
material is readily available at each site.
The $2.30 figure is based ~n a contract recently let by the
Agency for the Broverman/Taylorville landfill which is being
closed with State funds (8 Iii. Reg. 23951, December 14, 1984).
In many respects this may be the best estimate of
what it might
cost the Agency to close a
site
in the future.
However, this
landfill was a hazardous waste site with a
large uncovered area
which was never operated in
accordance
with the regulations (IEPA
v. Harold Broverman and Theodora
Baker d/b/a Taylorville
Landffll, PC~~6-1I4, ~P~123~November 10, 1977; Fifth
Wistrict, penalty reduced (Rule 23 Order), May 25, 1979). For
purposes of the interim rule the Board will accept $1.30/cubic
/ard as the best estimate of the cost of cover.
It takes around 3200 cubic yards of material to cover an
acre to a depth of two feet (R. 763, 692). At $1.30 per cubic
yard, this results in S4,160 per acre. The cost of establishing
vegetation must be added to this, Although the rules do not
explicitly require the operator to establish vegetation, it is
necessary to stabilize the cover against erosion (R. 692, 763,
893). If vegetation were omitted from the closure cost,it would
be necessary to include a greater allowance for erosion in the
post-closure care cost.
The
Board has received three estimates of the cost of
establishing vegetative cover:
$500
R, 763
S832
R. 69~2
$1235
(Ex, 18)
The Board will accept the $832/acre figure as the best
estimate of the cost of establishing a
vegetative cover.
Together with the cost of cover material, the cost per acre to
cover is approximately $5000/acre, which the Board will utilize
as the value for CPA in the formula.
There are other elements which would go into a complete
closure plan and cost estimate (R, 892, 900). However, it does
not appear feasible or necessary to include them in the interim
formula.
The post-closure
care cost formula includes the annual cost
of subsidence and erosion repair, and the cost of groundwater
monitoring (R. 693, 764, 858). Subsidence
and
erosion depends on
the p?xcent~2e~f
the
total cover area which
requires repair each
year
u’i. ir~e
t~oara has received two
estimates:
66-493

-32-
2
R. 764
5
R, 693
The Board has accepted 5 as the percentage of the total
cover which will require repair during each year of the post--
closure care period.
The other element of
post—closure care cost is the cost of
sampling groundwater. The rule assumes that monitoring wells
will be constructed during the operating life of the site, so
that no allowance has been made for construction (R.
777).
The
sampling cost depends
on the number of wells, the frequency of
sampling and the number of parameters analyzed. All of
the
witnesses agreed on quarterly sampling (R. 692, 765, Ex.
18).
Two witnesses suggested formulas Involving
a cost per well,
while
the Agency suggested requiring four wells (R. 692, 765, Ex.
1~). Permits should specify cert;ain well locations (R. 777,
Section 807,3l6(a)(15)(A)). However
it is possible that some
sites
may not have wells specified~
A minimal program involves
one well upgradient to establish the background water quality,
and two wells downgradient
to
detect
leaks. The Board has
therefore specified three as
a minimal number of wells
to
be used
in the formula. Any greater number actually existing or
specified in the permit will be included in the formula.
A basic permit should require analysis for alkalinity,
boron, chloride, pH, residue on evaporation, specific conduc-
tance, sulfate and total organic carbon (R. 765, 894). The cost
of basic
sampling and analysis is about $150 per sampling
(R.
692, 724, 765, 777). The Agency reports a range of $133 to $696
per sampling with an average of $288 per sampling (Ex. 18). The
higher costs appear to result from analysis beyond the eight
basic parameters (R. 894).
The Board accepts $150 per sampling as a good estimate of
the basic sampling cost, With four samplings per year, this
works out to $600 per well per year.
To recapitulate, the interim formula for the cost estimate
is as follows.
The area requiring cover (A)
is the sum of the
existing exposed area plus the potential future exposed area
according to the following formula:
A A(Existing)
+
3 AWR
3200 AD
A cannot be greater than the total permitted area which has
not
received final cover.
The closure cost estimate is:
CCE = (CPA)(A) ($5000/acre)(A)
66-494

-33-.
The post-closure cost estimate is:
PCCE
3CCCPA)(P)CA)
+ C600)CM))
-
750k
+
180011
The complete cost estimate is:
CE
-
5750k
+
180011
The number of wells
CM) cannot be less than three.
The EcIs computed cost estimates by a comparable formula.
The study formula estimated the area
requiring cover based on a
survey instead of the daily volume interim formula used above.
Also, the study used the total site area to estimate the
maintenance
and
monitoring costs.
The EcIS estimated the area requiring cover primarily
through a survey mailed to each
site, including those not thought
to be subject to financial assurance CR. 1065, 1083, 1170, 1173,
1179). The contractor developed a formula relating daily volume
to
open
area for the sites which responded to the survey CR.
1086, EcIS p. 57). For most sites the study used the open area
computed from the daily volume according to the formula CR.
1176).
The EcIS estimated the closure cost at $5,971.20/acre.
This
is based on $2.60
per
cubic yard for cover material, plus
$808/acre for seeding and fertilizing CR. 1057, 1059; EcIS p.
49).
The EcIS based maintenance of the site on the total area of
the site.
CR. 1059, EcIS p. 49). The site area was drawn from
the contractor’s survey, Agency permit files and a 1981 inventory
of landfills CR. 1066). For some sites the total areas were
estimated from the daily volume according to a formula drawn from
the sites for which data was available CR. 1165).
The maintenance cost estimate assumed that 3.5 of the total
site area required
replacement of cover, and
5
of the total site
required seeding and fertilizing each year for three years CR.
1057, 1059, 1086, 1129, 1164, EcIS 50). The study also includes
$25/acre/year for mowing. This works out to $155.76/acre/year,
or $467 for maintenance for three years of the entire site area
CR. 1059, EcIS 52).
The EcIS based monitoring cost also on the total site
area. The study assumed a minimum of four wells for sites
smaller than 10 acres, plus one well for each additional twenty
acres up to
100
acres. Thereafter,
one additional well was
assumed for each 50 acres CR. 1057, 1059, 1080, 1082; EcIS p.
50).

The EcIS assumed a cost of $150 per sampling. Four
samplings per year over a three-year period results in an $1,800
monitoring cost per well (R. 1059, EcIS p.49).
The EcIS included only aggregate amounts without displaying
its cost estimates
for individual sites. At the hearing, the
contractor presented
average values for the data (R. 1077,
1153). A typical
site is as follows (Ex. C-2i:
Maximum open area
Daily waste received
Total site acreage
Monitoring Wells
2.9 acres
1592 cubic yards
64 acres
6
Applying the EcIS cost estimate formula, one gets:
Closure S~971,20 x 2,9 =
Maintenance 467.00 x 64
=
Monitoring i~800
x 6
=
Cost Estimate
$17,316.48
29,888.00
10,800.00
$58,004.48
This is approximately equal to the average cost estimate
derived by dividing the aggregate cost of $8,900,000 by 152
sites.
Section 807.640
Mechanisms for Financial Assurance
The operator may use any of the following mechanisms:
1. Trust fund
2, Forfeiture bond
3.
Performance bond
4. Letter of Credit
5. Closure insurance
6. Self-insurance
(for non-commercial sites only).
Section 807.641 Use of Multiple Financial Mechanisms
The operator may use a combination of trust funds,
Corfeiture bonds, letters of credit and closure insurance
to
give
Linancial assurance ‘for a site. Performance bonds and self-
insurance
cannot be used in combinations.
Section 807.642
Use of a Financial Mechanism for Multiple
Sites
The operator may use a single mechanism to provide financial
assurance for more than one site.
The amount
is the sum of
the
cost estimates
for the sites.
Section 807.643 Trust Fund for Unrelated Sites
The Board
has allowed a
multiple unrelated operatorts trust~
fund
in which several operators contribute to a single trust.
68-486

-35-
This should reduce each operator’s share of the admlntstrative
cost of maintaining the trust. CR. 1055)
The trust works just like Section 807.661, with a few
exceptions.
The trustee must maintain books which show each
site1s account. The evaluation is made on the date of creation
of! the trust, regardless of the dates each site joined. Payments
out of the trust for a specific site are only from the account
for each site.
Section 807.644
RCRA Financial Assurance
The operator is not required to give financial assurance
under Part 807 if he demonstrates that the RCRA closure and post-
closure plans will result in closure and post-closure care in
accordance with the requirements of Part 807, and that he has
provided
adequate RCRA financial assurance. If there are closure
activities required under Part 807 which are not required under
the RCRA rules, the operator can either include the Part 807
activities in the RCRA plan and increase the RCRA financial
assurance,
or provide a separate Part 807 plan and financial
assurance.
Section 807.661 Trust Fund
The operator may satisfy the financial assurance requirement
by establishing a trust fund for the benefit of the Agency. The
trustee receives annual payments during the operating life of the
site.
Upon closure the trustee pays out as directed by the
Agency. The trustee pays the operator if he closes the site, or,
alternatively, pays the Agency’s contractor.
The
trustee must be an entity with authority to act as a
trustee. Illinois firms must be regulated by the Illinois
Commissioner of Banks and Trusts. Out-of-state firms must comply
with the Foreign Corporations
as Fiduciaries Act CIlt. Rev. Stat.
1983, ch. 17, par. 2801 et seq.).
The Agency should reject
financial assurance in the form of a
trust unless the trustee
complies with these requirements. Limiting
trustees to those
supervised by the Commissioner of Banks and Trusts provides
assurance
that
the
trustee will carry out its duties in a manner
such that funds will be available for closure CR. 206, 215).
The Board will specify the form of trust agreements in
Appendix A CR. 123, 390).
The Operator must make a
payment
into the trust fund each
year during the ‘pay-in period,’ which is equal to the number of
years remaining until the site
reaches the point in its operating
life at which the cost of premature closure would be the greatest
CR. 688, 757). The Board
has also specified that the pay-in
period be not less than three nor more than ten years, so as to
avoid requiring immediate full funding for sites which may
already be at the point of maximum closure cost, and yet to
68-497

-36-
assure reasonably prompt funding for all sites CR. 388, 398, 782,
1092, 1132). It is necessary to specify limits since Illinois
pnmits are of indefinite duration CR. 688).
An operator who elects to utilize the trust fund mechanism
has an obligation to the State to fund the trust and to provide
closure and post-closure care in accordance with these rules.
Closure and post-closure care costs are a necessary expense
associated with landfill operations. This expense should be
recognized during the operating life of the site, rather than
being postponed to the time of actual closure CR. 244, 474).
The trustee must evaluate the trust annually. The trustee
will be obliged to invest the funds under the terms of the
agreement. CR. 1093, 1137) The annual
evaluation will reflect
the losses or gains. CR.
1138) The operator will have 90 days to
make up any shortfall resulting from evaluation CSect ion
807.603).
The
operator can also request
release of profits in
excess of the cost estimate CSection 807.661(e)). The evaluation
date can be moved up for the convenience of the operator or
trustee.
Under paragraph (g)C2) the Agency has 60 days to determine
whether expenditures are in accordance with the plan. If so, it
instructs trustee to reimburse the
person providing closure.
Pursuant to JCAR staff comments, the phrase ‘or are otherwise
justified’ has keen deleted. The related language in Section
807.665Cf) hasalso been dropped.
The proposal was drawn from 40 CFR 264.143Ca).
The other
changes from the proposal include the following:
1.
Time for submission by new facilities has been moved to
Section 807.602.
2.
Requirement to update the trust agreement with a change
in the cost
estimate has been deleted.
3. Provisions on
release have been moved to Sections
807.604 and 807.606.
The EcIS
concluded that the one-operator trust fund would be
the most expensive mechanism CR. 1055, 1061, EcIS p. 19, 41).
This is in part because the banks surveyed charge large fees and
pay
low interest on the trust corpus CR. 1093, 1137). Annual
fees average about 6.33 percent of the cost estimate CR. 1061).
Also, the study failed to pick up the changes in the pay-in
period in the December 27 Order (1095, 1132). Actually, of the
91 sites which
had
complied with the temporary rules by the time
of the economic impact hearings, 36 utilized trusts CR. 1101).
68-498

—37-
Section 807.662
Surety Bond Guaranteeing Payment
The operator may satisfy the financial assurance requirement
by tendering a surety bond guaranteeing that the
operator wilt
close the site in accordance with the plan or the surety will pay
the amount of the bond which is based on
the current cost
estimate.
This mechanism assumes that the operator will provide
closure, with the surety liable only on default.
The surety company must be licensed by the Illinois
Department of Insurance. The Agency should reject bonds in which
the surety is not so licensed.
This requirement will assure
oversight of the financial institution to insure that funds will
be available when needed. This requirement will not restrict the
number of surety companies available significantly since the
majority of sureties
acceptable in Circular 570 of the U. S.
Department of the Treasury are licensed in Illinois CR. 221,
227).
The Board will specify the form of bonds in Appendix A CR.
123, 461, 465).
The Board has eliminated the requirement of a standby trust
fund to receive payments made under the bond. Any such
payments
will
be placed in the landfill closure and post-closure fund
where they may be earmarked for application to the site
pursuant
to Section 22.1Cc) of the Act. Deletion of the standby trust
fund will save costs for the regulated community CR. 390, 461).
The bond must guarantee that the operator will provide
closure and post-closure care in accordance with the plans in the
permit. The surety becomes
liable when the operator: abandons
the site as defined in
Section 807.104; becomes bankrupt; fails
to initiate closure at the time the Board or a court orders
closure to begin; or,
initiates closure,
but
fails to complete
closure
and post-closure care in accordance with the plans.
Abandonment occurs when the operator fails to initiate
closure within 30
days after receiving a final volume of waste.
If no waste is received within a 30-day period,
the operator must
demonstrate that it expects additional waste (Section 807.104).
Bankruptcy renders
it highly unlikely that an operator will
be able
to perform closure and post-closure care. It has
therefore been listed as a condition triggering the surety’s
liability.
Abandonment and bankruptcy represent simple factual
situations which do not directly involve the question of whether
the operator is in compliance with environmental regulations. If
the
surety refuses to pay on notice, the Agency should
sue
in
Circuit Court, which would make the determination as to whether
the abandonment or bankruptcy
had
in fact taken place.
66-499

38-
The surety .lo ~ n
d ctly giarantee that the operator
will comply with Boci.J
re a
aoas and permit conditions in
operation of the sste~
-!
t
Agency believes a site is poorly
operated, it must file
-
.l¼rementaction to obtain a finding
of violation. If the
C
.ei tsr ts closure of the
site, the
surety becomes liable onl3 -f t e operator fails to close as
ordered.
The fourth condit oi ‘1 ef at todd occur when the
operator starts to closc
tn. ...te tat fails to complete the job
as specified in the c1o~ ‘s
a: o
‘losure care plans. This is
similar to a constructi~
tr
b ~d in which the surety
becomes liable if the c
~
ca
oiL to build a building
According to specificat
The amount of tie
m st be
a least equal to the cost
estimate. The Agency r
a
ove a reduction in
the
amount
whenever the cost esttma
S.c oses
However, the operator
must
first request the reduct
a 3
hc surety is not obliged to
agree to it. If the Ag
i. aaees with the reduction in the
cost estimate, it should
-
cost estimate pursuant to
Section 807.214. If it a
tp
s
reduced cost estimate, it must
approve a reduction in ti.. bond atount. This language has been
clarified pursuant to
JCfl
commerts. Similar changes have been
made in Section’s 807.b63 th” and 807.664(f)C2).
The proposal was dra
a
..icn
40 (SR 264.143(b) but differs in
one respect. That Section
cli.
s
i r cancellation of the bond by
the surety on a 120-day notice to the Agency and the operator,
but makes the failure to obtai,r other financial assurance in a
90-day period a conditi.or
lc.sd
o liability by the surety.
Surety companies object to tnt opat-ended liability CR. 796, R.
1097, EcIS, A-i, 14). Ir order to attempt to make bonds more
available to operators, s
a d as specified that bonds be for
at least four years, but ~
u~. eQ
the provisions making
cancellation a condition lea
p
o liability. The four years
would provide assurance f’r
t
reasonable period of time during
which the Agency coald
in a forcement action and obtain a
closure order if opers~iorb
* •
d bad. Four years seems to be
within the range of cons- ‘ic
r 1rojects. This
change does
leave the State in an expo ed position if
the operator does not
provide additional asaurarce
•rmination of a bond. According
to the second telephor°
s
z’e conducted for the EcIS, this
modification did not sataf
the suretys’ objections (EcIS A-30).
The Board has pri
ided
r
si
automatic twelve-month
extension of the surety s liatisli y if the operator fails to
provide substitute financial aautance. The Agency should file
an enforcement action ategi.
n
tailure to provide financial
assurance if it wishes to er ‘ire
mpletion of the proceedings
during the twelve-month pen o.
The following ~rov4
e
r~~osaJhave boon moved to
other Sections:
0

-39-
1.
When financial
~.
2. Requirement
t
:
assurance;
3. Release of open
ta.t~
most be submitted;
‘.ose the amount of rinanrial.
4.
Release of finan
insVtution.
Section 807.663
Suret B
The perforniarce bo
except that the surey
and post-closure care p1
performance bond is spec-
Act. However, the Stab.
supervising a surety in
The EcIS conclude
expensive mechanisms to
no acceptance fee ana ha.
cost estimate CR. i056,
were not restricted to re
the 91 sites which had p
of the EcIS hearings, on.
Ex. C-3).
Section 807.664
(,.a anteeing Performance
)
cal ~o the forfeiture bond
‘e p ion of implementing the closure
i
s cad of paying the penal sum. The
..afly mertioned in Section 22.1 of the
ounter difficulties In
arformance of closure CR. 392).
bor s could be one of the less
c al assurance since they involved
o arnual fcc of around 2.1
of the
1.31 EcIS p. 40). Also, bonds
r customers CR. 1140).
However, of
.4 financial assurance by the time
rae actually used bonds CR. 1101,
The operator may sati
he financial assurance requirnment
by obtaining
a letter of c
.t ro. a financial institution.
The letter of credit a..
Si
ia.. to a bond in that it assumes that
the operator will provide
-
xc
If he fails, the Agency
writes a draft against tic
a
t-... of credit and presents it for
payment through banking ‘t. .ca.
The
issuing institution pays
the draft, and then attetpts L,
collect from the operator the
amounts paid like a bar
.
The Agency snould
IC
er
tnancial assurance in the form or
letters of credit froi ins~
-
ion which do not meet one of
these criteria which crit.e so ate intended to provide assurance
that the financial insti utson will be managed in such a way that
funds will be available I ‘
-
osure. Although FDIC and FSLC do
not actually insure lett.e...
r. ...rsdit their oversight provides
some assurance of continu
-
f .he financial institution CR.
208, 213, 216).
The Board viii spe
Appendix A.
o etters of credit in
Letter
.
...
cit
The financial i sti
to issue letters of 4rea
be regulated by the Ills
it must be insured b)
FDTt.
a.
ust be an
entity with authority
Its letter-of-credit operations must
r iasioner of Banks and Trusts, or
FSLIC

-4
-I—
The Agency is a iowA
operator fails to £ zde
accordance with ~he pia
.~
conditions as for a
~
As it did
vi.
tic
letters of credit
u c
has deleted the p c.r,s~.dc.
on the letter of cx
i.
:1
additional financi
a
The EcIS conc d t~a -era of credit should be widely
used instrument bet
e
c a. o acceptance fee and an annual
premium of only at 1.b c o the cost estimate CR. 1054,
1061, 1097, 1136, Y
,
F 1’
9) The letter of credit was
actually used by 3’ of 1 sites itch had provided financial
assurance by the tiau. o te cc somic impact hearings CR. 1101).
The operator may saL.,f
the if narcial assurance requirament
by providing closure
iisuran. wi h the Agency as a
beneficiary. Closure insurance is similar to a trust fund in
that payment is not de eidei cn sr default of the operator:
the insurance compa:
~
£
‘te operator voluntarily
closes the
site and 1c tin. wrk.
The insurance
c
s y ru
be licensed to transa”t the
business of insura
‘.e
m.soss Department of Insurance.
The Agency should re cc a irancial. assurance any insurance
from a firm which ic n so I ensed. Oversight by the
Department of Ins’-r
-
i’ t.
essary to assure that the insurance
company is managea ii .
-
a ray that funds will be available for
closure CR. 221, 3)1
The closure a
*
3~
ic iust be approved by the
Department of Insurai
R. 23, 22! 228).
The insurar’cs
c
~
t.3
es liable to pay out on the
policy whenever:
t
c opc.rator aoandons the site; Lhe operator
becomes bankrupt;
ti
Board crders the site closed; the operator
notifies the Ager” t~a it -s initiating closure; or, the
operator initiate0 do xc.
lie
ir’urer must pay out funds at
the direction of
tn.
Agen:y to ciomeve: is providing closure or
post-closure care.
The Board ha ~ d
it
c
oposed requirement
of a
standby
trust fund. Any p mer s i
.
a letter of credit will go into
the iindfill closu
..
ard
ct.r
Los ire fund in the State Treasury
pursuant to Section 21 1
of
tic Act. This should reduce
compliance costs CR 39 461).
dra or the letter of credit if the
-
re and post-closure care in
tie 4,c cy may draw under the same
3 ard has provided that.
t-r at least four years,
r
ns allowing the Agency to
crator fails to provide
~ e otice of cancellation.
but
draw
Section 807.665 C1ob se
lioutaire
An insura.c
-
the premium.
.s
-‘
c lied or.y for failure to pay
-he operator builds equity in
‘a

~41~
the policy
which
he is entitled to on
closure. The insurer must
give the Agency 120 days~ notice before
cancellation for
non—
payment of the premium. The insurer cannot
cancel if the premium
due is paid
by the
operator or the
Agency.
The proposal
specified abandonment, bankruptcy, etc. as
conditions preventing cancellation, These
have been reworded
t
be consistent
with the rest of the proposal and have been stated
with the guarantee of the policy. If the insurer becomes liable
under paragraph (e) during the cancellation grace period, it
continues to be liable after the period has ended,
The proposal provided specifically that failure to pay the
premium
was a
violation of the regulations. This has been
dropped as unnecessary. If the failure to pay results in
inadequate financial assurance, the operator will be in violation
oF Section 21.1 of the Act and Section 807,601.
The EcIS concluded that closure insurance would not he
utilized because no companies would write the insurance, and that:
annual premiums would range from 7 percent to 15 percent of the
cost estimate (R. 1056, EcIS p. 41). None of the 91 sites which
had provided financial assurance by the time of the EcIS hearings
used closure insurance
(R.
1101).
Section 807.666
Self—insurance
for Non—commercial
Sites
The Board
has added a self—insurance provision to the
proposal. The rule is largely drawn from the federal RCRA
Financial test of 40 CFR 264,143(e),
Section Z2.l of the Act requires a “performance bond or
other security.” The RCRA financial test alone does not meet this
description. The Board has therefore required operators seeking
to use the financial test to provide a bond without surety. The
assets of the firm will be sufficient security if the operator
meets
the financial test and other requirements of the Section.
The bond without surety will place the State in a better position
as a creditor in the event of the operator’s bankruptcy. The
bond will provide a liquidated amount which the State can claim
against the operator~s assets, Furthermore, the language of the
bond places
the burden
of proof on the operator to prove that he
provided closure and post—closure care in accordance with the
bond conditions (R, 128, 281, 288, 316, 323, 332, 426).
The financial test is intended to identify firms with
financial problems sufficiently far in advance so that the firm
still has assets to provide alternate financial assurance
(R. 311).
The
test balances reliability against availability:
the test attempts to exclude all firms which will
become
bankrupt,
and to pass all firms which will not become bankrupt
(R. 318).

-42-
USEPA selected 15 financial ratios from a list of possible
ratios.
It arrived at the financial test after testing these 15
against samples of bankrupt and non-bankrupt firms. The USEPA
financial test
is expected to allow 96 of non-banktupt firms to
pass, but is expected to pass only 0.1 of firms which will later
enter bankruptcy CR. 345).
In choosing the financial test,
USEPA sought
to minimize the
sum of the public and private costs, reasoning that increased to
operators were passed on to the public. The balancing involved
public and private administrative costs as well as possible
public costs from unfunded closure CR. 320).
The RCRA financial test is capable of predicting impending
bankruptcy sufficiently far in advance that the firm should have
sufficient assets to provide alternate financial assurance
at
the
time it fails the test, even if its financial condition is
rapidly deteriorating CR. 311, 319, 353, 415, 517).
The financial test includes alternate provisions involving
bond ratings for firms with publicly-held debt and ratios which
can be used by firms without ratings. The bond rating test is
often used by public utilities, which have trouble meeting the
ratio tests, but which are financially sound CR. 270, 312, 315,
330).
To meet the financial test, an operator must have a tangible
net worth which is:
1. At least six times the current cost estimate; and
2. At least $10,000,000.
The $10,000,000 tangible net worth requirement is related to
the probability that a firm will become bankrupt: exclusion of
firms with a lesser tangible net worth reduces the frequency of
bankruptcy by fifty percent CR. 239, 247, 281, 312, 326, 331,
343, 355, 509). The requirement of a tangible net worth at least
six times the cost estimate is an indicator of whether a firm is
large enough to complete the closure and post-closure care to
which it has obligated itself CR. 239, 312, 326, 328, 330, 355,
509).
The operator is also required to provide an opinion from a
certified public accountant. An adverse opinion or disclaimer
will be cause for disallowance. Other qualifications
may
result
in disallowance of the test CR. 240, 268, 313, 518).
A more stringent financial test could be constructed.by
adding a requirement that the ratio of net fixed assets to total
assets be greater than 0.3. The Wisconsin financial test
incorporates this ratio CR. 346, 350, 352, 516, 525). The Board
sees no need to make the test more stringent.
88404

-43—
The RCRA test is based on studies of the bankruptcy rates
for firms other than commercial disposal
firms CR. 232, 347, 415,
503). The RCRA
financial assurance requirement applies to
hazardous waste treatment and storage facilities, as well as
disposal facilities, and applies on-site
as well as off-site.
0ff-site hazardous
waste disposal facilities are only a tiny
fraction of the RCRA universe, which consists mostly of
manufacturing concerns managing their own waste CR. 332, 417).
The Illinois financial assurance requirement under consideration
applies almost entirely to off-site disposal CSections 2lCd) and
21.1 of the Act).
Firms which meet the financial test tend to be Jorge
diversified companies. However, if the test were applied only to
firms in any specialized line of business, the State would be
subject to greater risk because the economy could turn against
that specialized line, resulting in a large number of unfunded
closures. The firms which could use the test under this proposal
would be almost entirely engaged in a single line of business:
commercial waste disposal. Furthermore, these firms are in a
highly regulated area with high exposure to rapidly changing
regulations. The firms are all exposed to major liability for
potential environmental damage they may be causing CR. 315, 367,
351, 356, 619).
The Board has restricted use of the financial test to firms
which are not engaged in commercial waste disposal. This is
defined in terms of whether the firm derives more than 50 of its
gross revenue from waste disposal activities. The definition
suggested at the hearing was more than 80 of gross revenue in
waste management activities CR. 352). The Board has lowered the
percentage to 30, but has used disposal as a criterion.
Therefore a firm also involved in commercial waste treatment may
be eligible for the financial test.
Participants suggested a test at the hearings and in the
public comments. The suggested test was that the tangible net
worth exceed the cost estimate CR. 796; NSWMA comment of October
26, 1984). Since the cost estimate is not treated as a liability
in computing tangible net worth, it is possible that a firm could
meet this test and immediately declare bankruptcy simply by
recognizing its obligation to provide closure and post-closure
care as a liability (Appendix A). This would be short of the
three years prediction needed to make certain that the operator
has sufficient assets to provide alternate financial assurance at
the time it first fails the test.
It may be possible to construct a financial test which
commercial disposal operations could meet. However, the
participants in this rulemaking came forward with no firm
evidence suggesting the ability of any test to predict the
failure of such firms sufficiently far in advance that alternate
financial assurance could be provided.
66-505

—44—
Participants have provided evidence that small landfills may
not be able to obtain financial assurance, and may hence have to
close CR. 174, 186). Participants have suggested a financial
test as a way of avoiding such closures, which would be a
hardship on the public in some areas of the State, as well as
operators. However, for the reasons noted above, operations with
a smaller tangible net worth and the ones most likely to become
bankrupt.
Part 104 and Title IX of the Act provide a variance
mechanism by which operators which experience arbitrary or
unreasonable hardship may temporarily avoid the bond requirement.
Following the merit hearings it appeared that the
$10,000,000 tangible net worth test and the gross revenue test
would allow few, if any, disposal sites to utilize self-
insurance. The EcIS reached the same conclusion CR. 1098, EcIS
p. 34). However, of the 91 sites which
had
provided financial
assurance by the time of the EcIS hearings, 16 utilized self-
insurance CR. 1101, Ex. C-3).
The Board has received no requests for variances since the
emergency rules were adopted. 91 out of an estimated 168 sites
had provided financial assurance by the time of the EcIS hearings
CR. 1101, 1104, Ex. C-3). The sites which
had
not complied are
smaller sites, including sites receiving only construction debris
CR. 1105).
The RCRA rules provide that a parent corporation can
guarantee the operator’s cost estimate if the parent meets the
financial test. The Board has specified a form on which the
parent’s guarantee must be made. This is similar to the
forfeiture bond form.
The RCRA rules
limit the corporate guarantee to parent
corporations which own more than 50 of the operator’s voting
stock C40
CFR
264.l4lCd)). The Board has dropped the 50
requirement,
but
continues to require some ownership interest in
the operator. Unrelated firms offering this type of guarantee
are in the business of writing surety bonds, and should be
licensed by the Department of Insurance CR. 221, 227, 245, 271,
The Board has continued to limit financial tests and
guarantees to corporations.. The financial tests are geared
toward corporate accounting practices, and no one has proposed a
test applicable to individuals. Furthermore, there is a chance
that an individual will die, leaving the State in a position in
which it would have to claim against the assets of an estate CR.
246, 272).
The Board made several changes to the self-insurance
provision pursuant to
SCAR
staff comments. The Board has added
definition of “generally accepted accounting practices.” This
66-506

incorporates ~
published
by the Financial
Accounting Standards
Board, High Ridge Park, Stanford, CT
06905. The Board has also modified the definition of “tangible
net worth” to read more like the other definitions.
The first ratio test in Section
807,666(e)(1)(A)(i)
was
wrong in the
second
notice rules. It
read
“3.0” instead of
“2.0”, which
was used
in Appendix
A, Illustration
I, Alternative
1, line 15, and in 40 CFR 264~l43(f)(i)(A), which was the source
of the financial test, The Board corrected this pursuant to JCAR
staff comment.
The
Board has also reworded the provisions
of Section
807.666(g)
concerning
qualified opinions. The Agency must
disallow the test if the operator~s accountant gives an adverse
opinion or a disclaimer of opinion. The
effect
of other
qualifications
depends
on whether
they relate to the numbers used
in the test, and
whether, in light of the qualifications, the
operator has demonstrated that it meets the test.
This Opinion supports the Board~s Final
Order, Adopted Rule
of this same day.
I, Dorothy M. Gunn,
Clerk
of the Illinois Pollution Control
Board, hereby certify
that the above
Opinion was adopted on
the
~
day of
1985
by a vote of
Illinois Pollution Control Board
66~507

Back to top