ILLINOIS POLLUTION CONTROL BOARD
October
31, 1972
MATTISON MACHINE WORKS,
Petitioner,
vs.
)
PCB 72—338
ENVIRONI~1ENTALPROTECTION AGENCY,
Respondent.
Mark
E. MacDonald
for Petitioner
Melvyn A.
Rieff, Assistant Attorney General for the EPA
OPINION AND ORDER OF THE BOARD
(by Mr. Henss)
Petitioner Mattison Machine Works requests extension of
a
variance
with
respect to applicable emission standards for the
operation of its cupola.
We
granted the variance on February
3,
1972 and at the same time ordered Mattison to pay a penalty of
$3500 and post a performance bond in the amount of $160,000 to
guarantee installation and performance of a cupola emission
control
system.
The variance was to expire August 31, 1972 or
sixty days
after final delivery of all equipment necessary for
installation of the emission control system, whichever first
occurred.
Installation of the system has not progressed as rapidly as
anticipated.
The delay was caused by late delivery of equipment
to Mattison by the supplier.
The Environmental Protection Agency
inspected the site on August 24, 1972 and found that all major
pieces of equipment which had been delivered were assembled.
It
was said that all items were operable except for the primary
blower which was expected to be completed within
a few days.
Baghouse bags had not yet been received although the delivery
had been promised for May
1,
1972.
Delivery of the bags was
expected by September
15,
1972.
On the date of inspection the
only work remaining to be done was installation of bags,
installation
of shaker motors and connection of the cyclone collection exhaust to
the
baghouse.
In an attempt
to comply with the August
31,
1972 deadline it was
Petitioner~sintention to temporarily operate the emission control
system without the baghouse.
The supplier had represented to
Mattison that the
system,
even without the baghouse, would result
in
80 percent collection of cupola emissions.
Petitioner therefore
calculated that its emissions would comply with regulations
as of
6—111
—2—
startup.
The Agency had no way of verifying the accuracy of
the claim that
80 percent efficiency would be achieved on startup--
but using figures from a 1971 stack test did agree that if an
80
percent collection were achieved the emissions would be less than
the allowable 23.75 pounds per hour.
Whatever the exact percentage
of efficiency may he,
it seems clear that operation of the system
prior to installation of the complete baghouse will mean
a sub-
stantial reduction of emissions.
Petitioner has made good progress and is not at fault in the
delayed completion of the baghouse.
It seems reasonable
to us
that Mattison should not bear the risk of
a possible violation
pending completion of the baghouse and the necessary testing to
determine compliance.
Therefore, we grant the extension of
variance subject to appropriate conditions.
ORDER
It
is ordered that:
1.
The variance granted Petitioner on February
3,
1972
is extended through December 15, 1972 or sixty days
after final delivery to Mattison of all equipment
necessary for installation of the cupola emission
control system, whichever first occurs.
2.
Continued operation of Petitioner’s facility during
the period of the variance shall he controlled with
all available control equipment.
3.
Petitioner
shall review the information in its
installation permit application,
and,
if
nucessary,
apply for a revised permit.
4.
Petitioner shall inform the Environmental Protection
Agency in writing when bags are received for its
baghouse and when installation of
the baghouse is
complete.
5.
Petitioner shall comply with all requirements of
Rule 103 of Chapter
2, Part
1 of
the
Pollution
Control Board Regulations.
All applicable conditions
of
the Board’s Order
in PCB 71-277 shall be continued
in effect.
6.
The
Bond
filed
with
the
Environmental
Protection
Agency under Condition
3 of the Board’s Order in
PCB 71-277 shall be continued in effect and amended
to insure compliance with the Order of the Board
entered
in
this
case.
6—112
—3—
I, Christan L.
Moffett, Clerk of the Illinois Pollution
Control Board, hereby certify the above Opinion and Order was
adopt~edthis
.-~J/~’
day of October, 1972 by a vote of
_________
to
~
~\
/
/
CI~ristanL. Moffet~~erk
Illinois Pollution Control Board
6—
113