ILLINOIS POLLUTION CONTROL BOARD
    December
    20, 1990
    ERWIN HEDIGER, HORACE FILE,
    )
    SUSIE ARMBRUSTER, ARLIN WOKER,
    )
    LAYTON PEDDICORD,
    ARLINE
    DAIL,
    )
    BURNELL NEUMANN, LAVERLE EARLE,
    LYNN SCHMOLLINGER, HOWARD PRINGLE,
    )
    REID BINGHAM, AGNES PRINGLE,
    )
    CRAIG WOKER, MRS.
    0.3.
    DAIL,
    )
    JEANETTE TIFT, GLEN MILES
    )
    BILL G000ALL, DONALD SPRADLING
    )
    HOLLIE WILLMANN, CHARLES H.
    FUNK,
    )
    CAROLYN SPRADLING, PAMELA FUNK,
    )
    LOLA BROWN,
    JAMES
    DARNELL
    LEROY WIESE, LAMOINE BROWN,
    MIKE EATON, JIM STOECKLIN,
    )
    BOB BOWEN,
    MARY
    BLOEMKER,
    )
    DON
    CORE, ELDON BLOEMKER,
    )
    FRANCIS RINDERER,
    DANNY KUHN,
    )
    MRS.
    RALPH BAUMANN, PAMELA
    )
    BRYANT, LEORA LEISHER,
    MR.
    RALPH
    BAUMANN, JIM ZEBB,
    )
    MYRNA BRUCE, RICHARD ARMBRUSTER,
    )
    JOHN LANGFORD, MRS.
    PEGGY
    )
    DARNELL and BOND COUNTY
    )
    CONCERNED CITIZENS,
    )
    Petitioners,
    V.
    )
    PCB 90—163
    )
    (Landfill Siting)
    D
    & L LANDFILL,
    INC., BOND
    COUNTY BOARD OF SUPERVISORS,
    COUNTY OF BOND,
    STATE OF ILLINOIS,
    Respondents.
    JAMES BUCHMILLER APPEARED ON BEHALD OF THE PETITIONERS.
    W.A. DILLOW,
    III APPEARED FOR THE RESPONDENT, D & L LANDFILL,
    INC.
    JOHN KNIGHT APPEARED FOR THE RESPONDENT, BOND COUNTY BOARD OF
    SUPERVISORS.
    OPINION AND ORDER OF THE BOARD
    (by B.
    Forcade):
    This matter comes before the Illinois Pollution Control
    Board
    (“Board”) on a third—party appeal filed August
    20,
    1990
    pursuant
    to Section 40.1(b)
    of the Environmental Protection Act
    117—117

    —2—
    (“Act”) Il1.Rev.Stat.
    Ch.
    lll~,
    par.
    1040.1
    (b).
    The above—named
    individuals and Bond County Concerned Citizens
    (Collectively
    referred to hereafter as “BCCC”) appeal the decision of the Bond
    County Board of Supervisors
    (“County Board” or
    “Bond County”)
    granting site location suitability approval
    to D
    & L Landfill,
    Inc.
    (“D
    & L”) for
    a vertical expansion of its existing landfill.
    Procedural History
    D
    &
    L filed
    its application for landfill siting approval
    with Bond County on February 8,
    1990.
    Public Hearings on D
    & L’s
    application for the proposed vertical expansion and closure/post-
    closure were conductedby the Bond County Board on May 24 and
    June
    14,
    1990.
    The Bond County Board issued the decision to
    approve the application on July
    19,
    1990.
    BCCC filed their petition with this Board on August
    20,
    1990.
    The matter was accepted for hearing on August 30,
    1990.
    On September
    10,
    1990,
    D
    & L filed
    its response to the
    petition.
    On September 17,
    1990 BCCC filed an amendment to the
    petition.
    On September 24, 1990 Bond County submitted
    a
    certification of record and the County Board
    record.
    On
    September 25,
    1990, BCCC filed an amendment
    to the petition.
    On October
    19,
    1990 the Board’s hearing was held in
    Greenville,
    Illinois.
    A waiver
    of
    the decision due date until
    December
    22, 1990 was filed on October
    22, 1990.
    On October
    23,
    1990, original photographs were filed with the Board in
    substitution for the previously filed photocopies.
    The
    photographs comprise applicant’s exhibits 12—18 and the County
    Board’s consultant’s exhibits 12—19.
    Pursuant to the Board’s order of October
    25,
    1990, on
    October
    29,
    1990, Bond County submitted a revised certification,
    index of exhibits, and labelled exhibits.
    No briefs were
    submitted
    in this matter.
    The record submitted by Bond County
    consists of the transcripts from the May 24 and June
    14, 1990
    public hearings; the application documents; applicant’s exhibits
    1—24;
    the certification of publication of notice;
    copies of
    letters and certified mail receipts for notice
    to the Illinois
    Environmental Protection Agency
    (“Agency”) and legislators, BCCC
    exhibits
    1,
    2,
    3, and 6; Patrick Engineering’s (consultant to the
    County Board) exhibits 1—24;
    and the written decision of the
    County Board.
    Background
    The proposed facility would be a vertical expansion of a
    landfill now located
    in Bond County,
    Illinois,
    at the
    southwestern edge of the City of Greenville,
    Illinois.
    Ed. Tr.*
    *The abbreviation,
    Bd. Tr., will be used to signify the
    transcript
    of the Board’s October
    19, 1990 hearing.
    117—118

    —3—
    at
    6.
    The expansion would enable D
    & L to continue operations at
    the same site where D
    & L has operated since 1974.
    This landfill
    “was operated under the Illinois Department of Public Health and
    Pet Milk and the City of Greenville” prior
    to D
    & L’s acquiring
    its permit on May 13,
    1974.
    Tr.
    **
    at p.
    13.
    The original
    permitted facility includes
    32 acres, of which 15 acres would be
    used for the vertical expansion.
    Tr. at pp.
    21,
    40 and Bond
    County Board Ex.
    2.
    The vertical expansion would involve a
    maximum height of 590 feet above main sea level,
    compared with
    present levels of 530
    540 feet at one end of the existing trash
    area.
    Tr. at p.
    26.
    The fill depth for the new area was stated
    as being
    20 to 40 feet on average above the existing site.
    Tr.
    at p.
    39;
    see also Tr.
    at
    pp.
    76-77.
    The proposed facility would operate daily, Monday through
    Saturday from 5:00 a.m.
    to 8:00 p.m. May 1st through August 31st
    and from 6:00 a.m.
    to 6:00 p.m. from September 1st through April
    30th.
    Tr. at
    p.
    37.
    The vertical expansion would allow
    approximately 308,000 cubic yards of additional waste
    to be
    delivered to the site.
    Tr. at p.
    25; see also Tr.
    at pp.
    123—
    124.
    Hazardous wastes would not be accepted at the facility.
    Based on D
    & L’s records indicating that 500 cubic yards per
    day are now delivered
    to
    the site,
    D
    & L’s engineer projects that
    within
    2 years
    the waste capacity gained from the vertical
    expansion would be fully used.
    Tr.
    at p.
    26.
    But see also Tr.
    at pp.
    73—74 indicating that waste volumes reported to the state
    were last stated at 63,087 cubic yards per year, which suggests a
    longer “life”
    for the 308,000 cubic
    feet of added capacity.
    Final closure would then take place.
    Closure/post—closure plans
    include a groundwater monitoring program and plans, construction
    of
    a berm around the entire perimeter of the site, and quarterly
    inspections.
    Tr.
    at pp.
    17—19,
    p.
    31, pp. 96—102,
    112—120,
    and
    D
    & L Ex.
    8.
    Six monitoring wells are to be installed,
    replacing
    two existing monitoring wells.
    Tr. at pp.
    32—33,
    p.
    117.
    D
    & L’s enigneer described the area surrounding the facility
    as including agricultural/farming uses to the north and west;
    a
    number of residences on the opposite side of the road and a
    nearby public housing project to the south; and the City of
    Greenville directly to the east.
    Tr. at pp.
    21, 67—68.
    Introduction
    Public Act 82—682, commonly known as SB—172,
    is codified in
    Sections 3.32, 39.2 and 40.1 of the Act.
    It vests authority in
    the county board
    or municipal government to approve or disapprove
    the request for each new regional pollution control facility.
    These decisions may be appealed to the Pollution Control Board,
    whose authority to review the landfill site location decisions of
    **The abbreviations, Tr. and
    2 Tr.,
    will be used to signjify
    the transcripts
    of
    the
    County
    Board hearings held on May
    24,
    1989
    and June
    14,
    1990,
    respectively.
    117—119

    —4—
    Greenville directly to the east.
    Tr. at pp.
    21,
    67—68.
    Introduction
    Public Act 82—682,
    commonly known as SB-172, is codified
    in
    Sections
    3.32,
    39.2 and 40.1 of the Act.
    It vests authority in
    the county board or municipal government to approve or disapprove
    the request for each new regional pollution control facility.
    These decisions may be appealed to the Pollution Control Board,
    whose authority to review the landfill site location decisions
    of
    local governments is found
    in Section 40.1 of the Act.
    The
    Board’s scope of review encompasses three principal areas:
    (1)
    jurisdiction,
    (2) fundamental fairness of the local government’s
    site approval procedures,
    and
    (3) the nine statutory criteria for
    site location suitability.
    Pursuant to Section 40.1(a)
    of the
    Act,
    the Board is to rely “exclusively on the record before the
    county board or the governing body of the municipality” in
    reviewing the decision below.
    However, with respect to the issue
    of fundamental fairness,
    the Illinois Supreme Court has affirmed
    that the Board may look beyond the record to avoid an unjust or
    absurd result.
    E&E Hauling,
    Inc.
    v.
    PCB, 116 Ill.App.3d
    587,
    594,
    451 N.E.2d 555
    (2d Dist.
    1983),
    aff’d in part 107 Ill.2d
    33,
    481 N.E.2d 664
    (1985).
    Jurisdiction
    Jurisdiction is not at issue
    in this case.
    Fundamental Fairness
    Section 40.1(a)
    of the Act requires that the county board or
    local governing body must employ procedures,
    in reaching its
    siting decision, which are “fundamentally fair.”
    Due process
    considerations are an important aspect of fundamental fairness.
    Administrative proceedings are governed by the
    fundamental principles and requirements of due
    process of law.
    Citation.)
    Due process
    is a
    flexible concept
    and
    requires
    such procedural
    protections
    as
    the
    particular
    situation de-
    mands.
    Citation.)
    In
    an
    administrative
    hearing,
    due process
    is
    satisfied
    by proce-
    dures that are suitable
    for the nature of the
    determination
    to
    be made and
    that conform to
    the
    fundamental
    principles
    of
    justice.
    Citation.
    Furthermore,
    not
    all
    accepted
    requirements of due process
    in the trial of
    a
    case are necessary at an administrative hear-
    ing.
    Citation.
    ~
    Due process require-
    ments
    are determined
    by balancing the weight
    of the individual’s interest against society’s
    interest
    in
    effective
    and
    efficient
    govern-
    mental operation.
    Waste Management
    of Illinois,
    Inc.
    v.
    PCB,
    175
    117— 120

    —5—
    Ill.App.3d
    1023,
    1036—37,
    530
    N.E.2d
    682
    (2d
    Dist.
    1988).
    Thus,
    the manner in which the hearing
    is conducted, the
    opportunity to be heard,
    the existence of ex parte contacts,
    prejudgment of adjudicative facts, and the introduction of
    evidence are important, but not rigid, elements in assessing
    fundamental fairness.
    The recognized remedy for a lack of fundamental fairness
    is
    for the Board to remand to the county board to allow them an
    opportunity to cure this procedural deficiency.
    City
    of Rockford
    v. Winnebago County Board, PCB 87-92,
    83 PCB 47
    (November
    19,
    1987).
    This takes the siting decision back to the local
    authorities,
    who pursuant to Section 39.2(a)
    have been given this
    decisionmaking authority.
    Although BCCC raised the issue of fundamental fairness in
    its Petition at
    p.
    3, the Board finds that the arguments raised
    by BCCC are not concerned with whether the County Board conducted
    the proceedings below
    in a fundamentally fair manner,
    but rather,
    BCCC argues that the County Board should not have drawn
    conclusions from the evidence which resulted in approval of the
    application.
    This raises the issue that the County Board’s
    decision was against the manifest weight of the evidence,
    not
    that the County Board’s procedures or conduct was fundamentally
    unfair
    in reaching a different outcome than that sought by
    BCCC.
    The Board,
    therefore,
    will proceed to address the
    statutory criteria for site suitability and whether the County
    Board’s decision on each criterion should be upheld by this
    Board.
    Statutory Criteria
    Section 39.2 of the Act presently outlines nine criteria for
    site suitability, each of which must be satisfied if site
    approval
    is to be granted.
    Waste Management of Illinois,
    Inc.
    v.
    PCB,
    160 Ill. App.
    3d.
    434,
    513 N.E.
    2d 592
    (1987).
    In
    establishing each of the criteria, the applicant’s burden of
    proof before the local authority is the preponderance of
    the
    evidence standard.
    Industrial Salvage
    v. County of Marion, PCB
    83—173,
    59 PCB 233,
    235,
    236
    (August
    2, 1984).
    Section 39.2(a)
    of the Act sets forth the nine criteria as follows:
    The
    county
    board
    of
    the
    county
    or
    the
    governing
    body
    of
    the
    municipality,
    as
    determined
    by paragraph
    (c)
    of
    Section
    39
    of
    this
    Act,
    shall
    approve
    or
    disapprove
    the
    request for local siting approval
    for each new
    regional
    pollution control
    facility
    which
    is
    subject
    to
    such
    review.
    An
    applicant
    for
    local
    siting approval
    shall submit
    sufficient
    details
    describing
    the
    proposed
    facility
    to
    demonstrate
    compliance,
    and
    local
    siting
    approval shall be granted only
    if the proposed
    117—121

    —6—
    facility meets the following criteria:
    1.
    the facility
    is necessary to accommodate
    the
    waste
    needs
    of
    the
    area
    it
    is
    intended to serve;
    2.
    the facility
    is so designed,
    located and
    proposed
    to
    be
    operated
    that
    the public
    health,
    safety
    and
    welfare
    will
    be
    protected;
    3.
    the facility
    is located so as to minimize
    incompatibility with the character of the
    surrounding
    area
    and
    to
    minimize
    the
    effect
    on
    the
    value
    of
    the
    surrounding
    property;
    4.
    the
    facility
    is
    located
    outside
    the
    boundary
    of
    the
    100 year
    flood plain
    or
    the
    site
    is
    flood—proofed;
    5.
    the plan
    of
    operations
    for
    the
    facility
    is designed to minimize the danger
    to the
    surrounding
    area
    from
    fire,
    spills,
    or
    other
    operational
    accidents;
    6.
    the
    traffic
    patterns
    to
    or
    from
    the
    facility
    are
    so
    designed
    as
    to minimize
    the impact on existing traffic flows;
    7.
    if
    the facility will be treating,
    storing
    or
    disposing
    of
    hazardous
    waste,
    an
    emergency
    response
    plan
    exists
    for
    the
    facility
    which
    includes
    notification,
    containment
    and evacuation procedures
    to
    be used in case of an accidental release;
    and
    8.
    the
    the
    facility
    is
    to
    be
    located
    in
    a
    county where the county board has adopted
    a
    solid
    waste
    management
    plan,
    the
    facility
    is
    consistent
    with
    that
    plan;
    and
    9.
    if
    the facility will
    be located within
    a
    regulated
    recharge
    area,
    any
    applicable
    requirements
    specified
    by
    the
    Board
    for
    such areas have been met.
    BCCC challenges the County Board’s decision with
    respect
    each of
    the above criteria, except number
    7,
    which only involves
    hazardous waste facilities.
    The Board is now charged with
    deciding whether the County Boardts conclusion with respect to
    each contested criteria was against the manifest weight of the
    117— 122

    —7—
    evidence.
    Standard
    of Review
    As stated above, on appeal,
    the PCB must review each of
    the
    phallenged criteria based upon the manifest weight
    of the
    evidence standard.
    This standard of review was recently restated
    in Fairview Area Citizens Taskforce v.
    IPCB,
    144 Ill. Dec.
    659,
    555 N.E.2d 1178 (3d Dist.
    1990) as follows:
    In Tate,
    the standard of
    review
    in a regional pollution
    control
    facility
    site—location
    suitability
    case
    was
    stated:
    Waste Management of
    Illinois,
    Inc.
    v. Pollution Control
    Board
    (1987),
    160 Ill.App.3d 434
    (112 I1l.Dec. 178,
    513
    N.E.2d
    592,
    decided that all of
    the statutory criteria
    must
    be
    satisfied
    in
    order
    for
    approval and
    that
    the
    proper
    standard
    of
    review
    for
    the
    County
    Board’s
    decision is whether the decision is against the manifest
    weight
    of
    the
    evidence,
    with
    the
    manifest
    weight
    standard being applied to each and every criterion.
    See
    also City of Rockford v.
    Pollution Control Board
    (1984),
    125 Ill..App.3d 384
    80
    Ill.Dec.
    6501,
    465 N.E.2d
    996.
    A
    decision
    is
    against
    the
    manifest
    weight
    of
    the
    evidence
    if
    the
    opposite
    result
    is
    clearly
    evident,
    plain,
    or
    indisputable
    from
    a
    review
    of
    the
    evidence
    (Harris
    v.
    Day
    1983,
    115
    Ill.App.3d
    762
    71
    Ill.Dec.
    547),
    451 N.E.2d 262).
    The province of the hearing body
    is
    to
    weigh
    the
    evidence,
    resolve
    conflicts
    in
    testimony,
    and
    assess
    the
    credibility
    of
    the
    witnesses.
    A
    reviewing
    court
    is
    not
    in
    a position
    to
    reweigh
    the
    evidence,
    but
    can merely determine
    if
    the
    decision
    is
    against
    the
    manifest
    weight
    of
    the
    evidence.
    Jackson
    v.
    Board
    of Review of the Department
    of Labor
    (1985),
    105
    Ill.2d
    501
    86
    Ill.Dec.
    500,
    475
    N.E.2d
    879;
    McKey
    & Poague,
    Inc.
    v.
    Stackler
    (1978),
    63
    Ill.App.3d 142
    20
    Ill.Dec.
    130,
    379 N.E.2d 1198.
    Fairview Area Citizens Taskforce v.
    IPCB,
    555 N.E.
    2d at
    1184,
    citing Tate v.
    PCB,
    188 Ill.App.3d 994, 544 N.E.2d
    1176,
    1195
    Thus,
    the Board must affirm the decision of the local
    governing body unless that decision
    is clearly contrary to the
    manifest weight of the evidence, regardless of whether the local
    board might have reasonably reached a different conclusion.
    See
    •also E&E Hauling
    v.
    PCB, 116 Ill.App.3d
    586, 451 N.E.2d 555
    (2d
    Dist.
    1983); City of Rockford v.
    IPCB and Frink’s
    Industrial
    Waste,
    125 I1l.App.3d 384,
    465 N.E.2d 996
    (2d Dist.
    1984);
    Waste
    Management
    of Illinois,
    Inc.
    v.
    IPCB,
    22 Ill.App.3d 639,
    461
    N.E.2d
    542
    (3d Dist.
    1984); Steinberg v. Petta,
    139 Ill.App.3d
    503,
    487 N.E.2d 1064
    (1st Dist.
    1985); Willowbrook Motel
    v.
    PCB,
    135 Ill.App.3d
    343,
    481 N.E.2d 1032
    (1st Dist. 1985).
    117—123

    —8—
    It should be noted that the Fairview court, citing
    Tate,
    defined the responsibilities of the hearing body
    in terms of
    weighing the evidence, resolving conflicts in testimony, and
    assessing the credibility of witnesses.
    It is not the local
    government’s burden to disprove or
    refute the applicant’s
    assertions.
    The decisionmaking authority rests solely with the local
    government.
    A local government’s consultant
    report, even if
    accurately characterized as urging approval,
    is not binding on
    the decisionmaker.
    McLean County Disposal Company,
    Inc.
    v. The
    County of McLean, PCB 89-108,
    105 PCB 203,
    207
    (November
    15,
    1989).
    The Bond County Board hired an engineer, Mr. Moose, who
    reviewed the D
    &
    L application and who testified at the public
    hearing.
    BCCC argues that the County Board’s engineer found
    certain criteria were not met by D
    & L and that the application
    lacked adequate information such that the engineer could not make
    a favorable recommendation on certain other criteria.
    See Pet.
    at pp. 7—11 and Tr. pp.
    16—36.
    Without addressing here each
    aspect of the testimony of the County Board’s expert,
    the Board
    again notes
    that the local government
    is not bound by the
    recommendations of its experts.
    The testimony of the County
    Board’s expert
    is, however,
    relevant to the Pollution Control
    Board’s decision as to whether the local government’s decision
    was against the manifest weight of the evidence.
    This Board will
    evaluate the testimony of the County Board’s engineer in that
    context only.
    Discussion
    The issue before the Board is whether or not the decision of
    the Bond County Board, finding that
    D
    &
    L proved that the
    proposed facility satisfies criteria 1,
    2,
    3,
    4,
    5,
    6,
    8, and 9,
    is against the manifest weight of the evidence.
    Criterion
    1:
    the facility is necessary to accommodate
    the waste
    needs of the area
    it
    is intended to serve.
    Pursuant to Section 39.2(a)(l)
    of the Act, the Bond County
    Board is required to review D
    & L’s application to ensure that
    the proposed facility is necessary to accommodate the waste needs
    of the area
    it
    is intended to serve.
    The applicant
    is not
    required to show absolute necessity
    in order
    to satisfy criterion
    1.
    Fairview Area Citizens Taskforce v.
    IPCB,
    555 N.E.2d at
    1185,
    citing Tate
    v. Macon County Board,
    544 N.E.2d 1176; Clutts
    v.
    Beasley,
    185 Ill.
    App.
    3d
    543,
    541 N.E.2d 844,
    846 (5th Dist.
    1989);
    A.R.F. Landfill,
    Inc.
    v. PCB,
    174 I1l.App.3d 82,
    528
    N.E.2d
    390, 396
    (2d Dist.
    1988); Waste Management of Illinois
    v.
    PCB, 122 Ill.App.3d 639,
    461 N.E.2d 542, 546
    (3d Dist.
    1984).
    The Third District has construed “necessary” as connoting
    a
    “degree of
    requirement or
    essentiality” and not just “reasonably
    convenient.”
    Waste Management of Illinois
    v.
    PCB,
    461 N.E.2d at
    546.
    The Second District adopted this construction of
    117—124

    —9—
    “necessary” with the additional requirement that the applicant
    demonstrate both an urgent need for, and the reasonable
    convenience of,
    the new facility.
    Waste Management of Illinois,
    v.
    PCB,
    530 N.E.2d 682,
    689
    (2d Dist.
    1988); A.R.F. Landfill,
    Inc.
    v.
    PCB,
    528 N.E.2d at 396; Waste Management of Illinois
    v.
    PCB,
    463 N.E.2d 969,
    976
    (2d Dist. 1984).
    The applicant defines the area to be served.
    Metropolitan
    Waste Systems,
    Inc.,
    Spicer,
    Inc.,
    et
    al.
    v IPCB,
    146 Ill. Dec.
    822,
    558 N.E.
    2nd 785
    (Third Dist.
    1990).
    D
    &
    L has discussed
    its service area in terms of the highly localized needs which the
    current facility serves,
    that is, primarily the needs of Bond
    County.
    This Board previously has found that this narrow
    approach alone does not warrant the Board’s reversal of the local
    government’s decision.
    Bond County Concerned Citizens,
    et al
    v.
    D
    & L Landfill,
    Inc., PCB 90—94, August 30, 1990.
    BCCC asserts that other facilities are available
    to meet
    Bond County’s disposal needs.
    BCCC also argues that the
    statutory •requirement,
    that the facility
    is necessary to meet the
    waste needs of the area intended to be served,
    has not been
    satisfied,
    in part,
    because the applicant did not introduce
    evidence on other available facilities.
    BCCC stated at this
    Board’s hearing that:
    “....there was simply the testimony of the engineer
    for
    the operator,
    Mr.
    Conner,
    that the landfill was full.
    He basically gave
    no testimony that there was....
    ....no other disposal site available.
    When questioned,
    they said that they made no study
    to determine what else or what other
    sites were
    available, and,
    therefore, nothing was
    in the
    application in that regard.
    No study was made as to what additional costs would
    be incurred with regard to putting the trash at some
    other
    site,
    at some other location.
    Bd. Tr. at p 9.
    BCCC argues that another hauler would be available to haul
    Bond County’s waste to other facilities, and that other
    communities using other disposal facilities were paying less than
    or equal
    to D
    & L’s disposal charges.
    Pet.
    at p.
    5,
    2 Tr.
    at pp.
    79—80.
    BCCC also relies on the testimony of the County Board’s
    consultant,
    who pointed out
    that while the existing facility had
    no remaining life, alternatives had not been explored, and,
    therefore,
    the need for
    the facility could not be determined.
    Pet.
    at pp. 7—8, citing
    2 Tr.
    at pp.
    21—22.
    BCCC attempted at this Board’s hearing to present evidence
    on available facilities
    by reference to certain documents
    attached
    to a letter which BCCC submitted as public comments for
    consideration by the County Board.
    D
    & L objected to the
    117—125

    —10—
    inclusion of those documents in the record before this Board
    since the attachment reportedly was submitted one day after the
    30 day comment period, even though the letter itself was timely
    filed.
    Bd.
    Tr. at pp.
    10—12.
    BCCC responded at hearing that the
    letter independently presented evidence that alternative
    facilities existed which would involve minimal or
    no additional
    disposal costs
    to Bond County.
    The Board finds that the
    statement at p.
    3 of
    D
    & L’s Response to Amendment
    to Petition
    that,
    “it appears as if counsel for the Petitioners has attempted
    to introduce into evidence various exhibits more than thirty
    (30)
    days after
    the date of the last public hearing on this matter”,
    did not sufficiently inform this Board of the matter
    to which D
    &
    L objected.
    The Board will not construe such general statements
    as an objection or motion
    to exclude.
    However, the Board has
    considered the objection raised by D
    & L at this Board’s hearing,
    and finds that the particular attachments should not be
    considered as part of the County Board’s record to be reviewed by
    this Board.
    D
    & L argues that its expert stated that D
    & L serves a
    three
    or four county area,
    that Bond County has no other
    landfills,
    that the nearest other landfill is
    in Litchfield,
    and
    that costs would increase to haul trash
    fa’rther.
    Bd.
    Tr.
    at
    41,
    citing Tr.
    at pp.
    48,
    82,
    83.
    See also
    2 Tr.
    at pp.
    93—99.
    D
    &
    L
    also focuses on the testimony of the County Board’s
    consultant,
    who observed that the current facility’s capacity is
    depleted and that the rate of disposal had been increasing
    for
    three or four years.
    Bd.
    Tr.
    at pp.
    41, citing
    2 Tr.
    at p.
    21.
    In addition to the assertions of need by D
    &
    L,
    the County
    Board also heard the testimony of
    its own consultant, who
    testified that as
    a practical matter
    trie existing facility had no
    remaining life.
    “Either they receive the vertical expansion;
    or,
    they will
    be forced to close by the IEPA.
    Right now.”
    2 Tr. at
    p.
    21.
    The County Board also heard the continuing testimony of
    its consultant,
    in which he noted that
    “I don’t think,
    in my
    opinion,
    this totally answers the need question.”
    2 Tr. at p.
    21.
    As BCCC notes, the consultant stated that the application
    did not present alternatives or
    cost, but that there were no more
    landfills in this county.
    2 Tr.
    at pp.
    22.
    After reviewing the application, hearing arguments from both
    D
    & L and BCCC, and hearing from its own consultant, Bond County
    concluded that the facility was necessary to accommodate the
    wastes needs of the area
    it was intended to serve.
    The County
    Board had an opportunity to consider BCCC’s assertions that
    alternative facilities would be available at little or no
    addi.tional expense to Bond County.
    It also had an opportunity
    to
    consider what the probable life of the proposed facility might
    be.
    Tr.
    at pp.
    25—26,
    123—124,
    2 Tr.
    at p.
    21.
    The County Board
    concluded that the proposed facility
    is necessary to serve the
    waste needs of the area,
    even though
    it might have reached a
    different conclusion.
    The Board finds that Bond County’s
    decision on criteria
    1 has support in the record and is not
    contrary to the manifest weight of the evidence.
    117—126

    —Il—
    Criterion
    2:
    the facility is
    so designed, located and proposed
    to be operated that the public health, safety and welfare will be
    protected.
    Criterion
    2 requires that the applicant demonstrate that the
    proposed facility
    is designed, located, and proposed to be
    operated
    in a manner
    in which the public health,
    safety, and
    welfare
    will
    be
    protected.
    The
    decision
    maker,
    here
    the
    County
    Board,
    has
    the
    duty
    to
    weigh
    the
    credibility
    of
    witnesses,
    where,
    as
    in the present
    case,
    the expert testimony of more than one
    witness
    is presented.
    See, Metropolitan Waste Systems,
    Inc.,
    Spicer
    Inc.,
    et
    al.
    v.
    PCB,
    146
    Ill.
    Dec.
    822,
    558
    N.E.
    2d
    785
    (3d Dist.
    1990), ARF Landfill,
    Inc.,
    v.
    PCB,
    174 Ill. App.
    3d 82,
    528 N.E.
    2d
    390
    (2d Dist.
    1988).
    BCCC argues that gas, leachate, and erosion problems create
    a potential hazard to the public health,
    safety, and welfare.
    BCCC offered Agency reports of distressed and dying
    trees
    in this
    connection.
    BCCC also raised the issue of past violations and
    fines
    paid
    by
    D
    &
    L
    in
    support
    of
    its
    position
    that
    the
    facility
    would
    not
    be
    operated
    consistent
    with
    criterion
    2.
    Tr.
    at
    pp.
    54,
    60—67,
    2
    Tr.
    at
    pp.
    104—105,
    131—139.
    In response to concerns raised about gas,
    D
    & L’s engineer
    testifed
    that
    detection
    of
    a
    possible
    escape
    of
    methane
    gas
    was
    to be based only on observation of vegetation.
    Tr. at pp.
    35—36,
    79—81,
    119—120.
    BCCC asserts that “there was no other detection
    method proposed or considered by them...”
    Bd.
    Tr.
    p.
    7.
    BCCC
    argues that there is little or
    no vegetation to monitor,
    and
    that,
    therefore, the proposed detection method is inadequate.
    Bd.
    Tr. at p.
    8;
    Tr.
    at 80—81.
    BCCC also referred
    to the testimony
    of the County Board’s engineer, Mr. Moose, who found that the
    detection system is “not adequate.”
    “...I don’t believe that
    there is any gas management plan collection detection system;
    and,
    I believe that one should be part of this expanded
    facility.”
    2 Tr.
    at pp.
    40,
    64—65.
    BCCC also challenges D
    & L’s claims regarding health,
    safety, and welfare based on possible groundwater contamination
    from leachate.
    Pet. at p.
    7—9.
    At hearing, BCCC stated that:
    ....the applicant,
    through testimony of his engineer,
    admited that there was leachate escaping from the site,
    and there had been leachate escaping from the site for
    some considerable years prior to this application.
    ***
    ....this is not a 10,
    not a 20,
    not a 50,
    not
    a 100
    excessive presence of chloride, boron, and iron
    contaminants
    in
    the area, but multiples of 7.4 and
    multiple of
    24 times, and a multiples of 3.6 times.
    * **
    With
    regard
    also
    to
    the
    affect
    on
    the
    environment
    and safety of the public,
    their engineer and the only
    evidence that we had from the applicant, and only thing
    117— 127

    —12—
    in the application was his admission that he made,
    no
    study,
    and
    I
    repeat, no study.
    That
    is his own testimony and the only testimony on
    behalf of the applicant with regard
    to
    the number and
    the location or its proximity of the homes to this site.
    Therefore
    I think
    it follows, the inevitable
    conclusion,
    that this is not part of the application,
    it
    is not
    in the application, even though by law
    it
    is
    required.
    He also admitted he did not count the ground wells
    at these home sites.
    Bd. Tr.
    at pp.
    13—15.
    (See also,
    2 Tr. at pp.
    84—86)
    BCCC points to the testimony of D
    & L’s engineer
    that the
    extent of the present leachate problem is unknown, and that,
    further, D
    & L’s application itself suggests that geologic
    conditions may
    be unfavorable for controlling the
    leachar.e
    problem.
    Tr. at
    p~
    101,
    2 Tr. at pp.
    81—82.
    BCCC further argues
    that the County Board’s consultant stated that the application
    did not present enough information on geologic formation,
    groundwater,
    wells and the containment berm to conclude that
    groundwater would be protected.
    Pet, at
    p.
    8—9,
    2 Tr. at pp.
    23—
    41.
    The County Board’s consultant raised many concerns regarding
    contamination of area wells,
    the lack of a liner,
    the
    effectiveness of the berm, and the area’s geology.
    The Board
    notes, however,
    that he also stated that
    “the little data that
    is
    in here
    (on geology)
    is conflicting.”
    2
    Tr.
    at
    p.
    25.
    D
    & L’s engineer discussed at length the various aspects of
    the proposed facility’s design and operating plan,
    including
    daily cover, the design of the berm and drainage plan, erosion
    control, methane gas detection,
    and monitoring wells, to support
    its position that the facility would protect the public health,
    safety, and welfare.
    Tr.
    pp.
    69—82, 95—120.
    Much of BCCC’s argument and the County Board’s consultant’s
    testimony is directed at monitoring,
    arresting, and remediating
    the pre—existing leachate problem.
    The apparent lack of
    a liner
    under the existing facility,
    for example, does raise concerns for
    the new facility, but primarily addresses a pre—existing
    problem.
    2 Tr. at
    p.
    27.
    Similarly,
    the erosion problems
    relate
    primarily
    to the existing facility.
    Pet.
    at
    p.
    7,
    2
    Tr. at
    pp.
    31—34.
    While the concerns expressed here may be relevant to an
    enforcement action, the weight of this information is diminished
    in the context of evaluating the design and operational aspects
    of
    the proposed facility.
    Additionally,
    “conflicting” evidence
    is to be resolved by the local government, and not by this
    Board.
    ARF Landfill, Inc.,
    v. PCB, 174 Ill. App.
    3d 82,
    528 N.E.
    2d
    390
    (2d Dist.
    1988).
    117—128

    —13—
    The Board finds
    that Bond County’s decision that D
    & L
    satisfied criterion
    2 was not against the manifest weight of the
    evidence.
    The statute requires that the local government review
    the design, location,
    and operational features of the proposed
    facility.
    These matters were raised before the County Board.
    Although the amount of detail left many questions unanswered for
    the County Board’s consultant,
    the decision ultimately
    rested
    with the County Board.
    Furthermore,
    the County Board should not
    be required
    to decide against D
    &
    L on the basis of prior
    problems at
    the site when the new facility is designed to protect
    the public health,
    safety, and welfare.
    Based on the record before it, including exhibits depicting
    location, height,
    side views,
    and monitoring wells,
    the Board
    finds that the County Board could reasonably decide that the new
    facility was designed, located and proposed to be operated so
    that the public health, safety and welfare will be protected.
    The possibility that another decision could also have been
    reached does not support reversal by the Board.
    Criterion
    3:
    the facility
    is located
    so as to minimize
    incompatibility with the character of the surrounding area and to
    minimize the effect on the value of the surrounding property.
    The applicant
    is required to minimize the incompatibility of
    the facility on the surrounding area and minimize the effect on
    property values.
    This requirement acknowledges that some effect
    is likely.
    However,
    the applicant
    is not required to choose the
    best possible location or
    to guarantee that no fluctuation
    in
    property values occurs.
    Clutts
    v. Beasley,
    185
    Ill.
    App.
    3d 543,
    541 N.E.
    2d 844,
    846
    (5th Dist.
    1989).
    BCCC argues that about 30 residents, some of whom may reside
    within 1,000 feet of the site, plus those living
    in a nearby
    public housing project, would be adversely affected by D
    &
    L’s
    alleged failure to minimize
    incompatibility with the character of
    the surrounding area and to minimize the effect on property
    values.
    Pet,
    at p.
    11, Tr.
    at
    p.
    68,
    2 Tr.
    at pp.
    82,
    92.
    BCCC
    relies on the testimony of the County Board’s consultant,
    who
    stated that the planned operating hours appeared excessive
    compared with other facilities and should be evaluated to decide
    whether it creates a nuisance
    in the surrounding area.
    Pet.
    at
    p.
    10,
    2 Tr. at
    p.
    42.
    In other respects the consultant
    found
    that the application did not give sufficient information
    to draw
    a conclusion regarding this criterion.
    2 Tr.
    at p.
    41.
    D
    &
    L seems to characterize the area as being much less
    residential
    in nature, making note of nearby agricultural uses,
    and suggesting that a number of residents live farther from the
    facility than BCCC indicates.
    Tr.
    at p.
    21,
    2 Tr. at
    pp.
    87—
    91.
    D
    & L offered a letter from a local realtor opining that
    property values would not be adversely affected.
    2 Tr.
    at
    pp.
    129—130 and D
    & L Ex.
    19.
    D
    &
    L
    also introduced evidence of a
    home purchased near the landfill in 1989 and of
    a home being
    built
    nearby.
    2 Tr. at pp.
    88—90.
    117—129

    —14—
    The Board finds that the record offers limited information
    on the issue of minimizing incompatibility with the surrounding
    •area and the effect on property values.
    The County Board clearly
    was presented with conflicting views and evidence.
    The Board
    finds that the County Board could find sufficient evidence
    in the
    record to conclude that the proposed vertical expansion of the
    existing landfill would pose only minimal impact on the
    surrounding area and on property values.
    The Board concludes
    that the County Board’s decision with respect
    to criterion
    3
    is
    not against the manifest weight of the evidence.
    Criterion
    4:
    the facility is located outside the boundary of the
    100 year flood plain or the site is flood—proofed.
    Criterion
    4 requires that the facility is located outside
    the boundary of the 100 year flood plain, or alternatively, that
    the site
    is flood—proofed.
    In its petition, BCCC raises the
    issue of
    location within the flood plain, stating,
    “he
    (the
    County Board’s consultant)
    states that the existing facility was
    constructed in the flood plane (plain).”
    Pet. at p.
    10, citing
    2
    Tr.
    at p.
    42.
    BCCC has,
    however, neglected to direct the Board’s
    attention to the consultant’s immediately preceding sentence.
    “I
    don’t believe that this,
    the vertical expansion is actually going
    to occur in the flood plain in any location.”
    2 Tr. at
    p.
    42.
    The consultant also stated that,
    “I see no plans
    to do excessive
    filling or any filling in the flood plain.”
    2 Tr. at p.
    43.
    D
    &
    L’s engineer’s testimony also indicates that the proposed
    facility
    is not within the 100 year flood plain.
    See Tr. at p.
    50;
    see also discussion at Tr.
    at
    p.
    92,
    The Board finds
    that the decision of the County Board that
    the facility is located outside the boundary of the 100 year
    flood plain or that the site
    is flood—proofed is not against the
    manifest weights of the evidence.
    Criterion
    5:
    the plan of operations
    for the facility
    is designed
    to minimize the danger
    to the surrounding area from fire,
    spills,
    and other operational accidents.
    The proposed facility must minimize, but not necessarily
    eliminate,
    the possibility of danger from fire,
    spills or other
    accidents.
    In support
    of its position that this criterion was
    satisfied,
    D
    & L offered the following testimony of its engineer:
    Q.
    Does the plan of operation of this vertical
    expansion of this landfill,
    is there any •danger
    to
    the surrounding area by way of fire or spills or
    any other operational accidents?
    A.
    Everything is done to minimize the danger with the
    use of essentially daily cover as one of the
    primary means.
    The containment berm that
    is
    constructed around there is another means,
    diversion ditches.
    So,
    there are means
    in place,
    right.
    117—130

    —15—
    Tr.
    at p.
    50.
    These statements were supported with more extensive testimony on
    cover requirements, the containment berm, and the drainage
    systems.
    Tr.
    at pp.
    22—45.
    D
    & L’s engineer also stated the
    following in closing comments at the second County Board hearing:
    We submit that the proposed vertical expansion
    doesn’t change the present condition.
    The facility
    is operated just as
    it was before.
    There is no
    greater cause for alarm
    for fire, spills or
    accidents than there ever has been at the
    landfill.
    And, we submit that there
    is the design
    as such is not shown to be hazardous to anybody’s
    health by reason of fire,
    spills and hazardous
    mater ia1.
    2 Tr.
    at p.
    130.
    The County Board’s consultant commented on the lack of
    a
    separate,
    formal plan to minimize the danger from fire,
    spills,
    and accidents:
    “Based on my review of the submitted information,
    I did find no spill reaction plan,
    no accident prevention plan or
    fire prevention plan or protection plan.”
    2
    Tr. at p.43—44.
    He
    further testified that there is
    a potential for fires
    or
    explosion from gas releases, and fires, explosions or
    accidents
    could occur.
    2 Tr.
    at pp.
    66—67,
    see also
    2 Tr. at p.
    83.
    Bond County concluded that D
    & L carried its burden with
    respect to criteria 5’s fire, spills, and accident issues.
    The
    Board finds
    that Bond County’s decision has support
    in the
    record, and is not contrary to the manifest weight
    of the
    evidence.
    The evidence submitted for the County Board’s review
    included extensive testimony and various exhibits, such as the
    application,
    a groundwater monitoring program, and hydrogeologic
    report.
    The Board finds that the absence of a separate document
    labelled as a spill reaction, accident prevention,
    or fire
    prevention plan does not warrant reversal by this Board where, as
    here,
    the record includes sufficient evidence on this criterion.
    Criterion
    6:
    the traffic patterns
    to or
    from the facility are so
    designed as to minimize the impact on existing traffic flows.
    D
    & L has a statutory obligation to minimize the traffic
    impact of the proposed facility, but that obligation has not been
    construed to mean that D
    & L must eliminate any additional
    traffic impact.
    See, Fairview Area Citizens Taskforce v.
    IPCB,
    144 Ill. Dec.
    659,
    555 N.E.
    2d 1178,
    1186
    (3d Dist.
    1990).
    BCCC asserts that D
    &
    L failed to satisfy the requirement
    that the traffic impact be minimized because D
    & L’s engineer
    simply asserted that the traffic flow would remain essentially
    unchanged.
    Bd. Tr. at
    p.
    13.
    BCCC argues that since D
    & L’s
    engineer testified that the cubic yards of waste would increase
    117—13 1

    from the previous 44,992 to cu.
    yds. per year,
    a plan to minimize
    the traffic impact should have been included, but was not.
    Bd.
    Tr.
    at p.13.
    BCCC notes that the County Board’s consultant
    commented that a detailed traffic study was not part of the
    original application.
    Pet.
    at pp. 10—11,
    citing
    2 Tr. at p.
    44.
    BCCC’s witness, Mr. Hediger
    (also a petitioner), testified
    that the roadway is not wide enough to handle the truck traffic
    and that the entrance is via very narrow pavement.
    He asserted
    that traffic conditions are very dangerous.
    2 Tr.
    at pp.
    83—84.
    At hearing, D
    &
    L’s engineer testified that the traffic flow
    is expected to be essentially unchanged.
    Tr. at
    p.
    51.
    He also
    referred to the Illinois Department of Transportation,
    1985
    Survey on traffic.
    Average daily traffic counts ranged from 850
    5,800 cars or trucks per day on the pertinent roadways.
    Tr. at
    p.
    51.
    The County Board found traffic impacts to be minimal, based
    on the application before it, and presumably based on the Board
    members’
    own knowledge and familiarity with local traffic
    conditions.
    See PCB 90—94, Bond County Concerned Citizens
    v.
    D
    &
    L Landfill,
    Inc., August 30,
    1990.
    Based on the minimal traffic
    information provided
    in the record,
    the Board finds that Bond
    County’s decision was not against the manifest weight
    of
    the
    evidence.
    As
    in the case of A.R.F.
    Landfill,
    Inc.
    v.
    IPCB and
    Lake County,
    174 Ill.App.3d 82,
    528 N.E.2d 390
    (2d Dist.
    1988),
    affirming the Board’s decision in PCB 87—51,
    the local government
    is in the best position to weigh conflicting evidence.
    The Board
    will not substitute its
    judgment in such a circumstance.
    See
    also McHenry County Landfill,
    Inc.
    v.
    IPCB,
    154 Ill.App.3d 89,
    506 N.E.2d
    372,
    381
    (2d Dist.
    1987), affirming the PCB and the
    county board’s conclusion regarding traffic.
    Criterion
    8:
    if the facility is to be located
    in a county where
    the county board has adopted
    a solid waste management plan,
    the
    facility
    is consistent with that plan.
    Bond County’s consultant indicated at the County hearing
    that Bond County has not completed a Solid Waste Management Plan,
    and that therefore, this criterion is not applicable.
    2 Tr.
    at
    p.
    44.
    Similarly,
    D
    & L’s consultant testified that criterion
    8
    would not be an issue.
    Tr.
    at p.
    51.
    This Board concludes that
    the County Board’s decision is not against the manifest weight of
    the evidence with respect to the requirement that the proposed
    facility be consistent with the area’s local Solid Waste
    Management Plan.
    Criterion
    9:
    if the facility will be located within a regulated
    recharge area, any applicable requirements specified by the Board
    for such areas have been met.
    As was the case with criterion
    8, Bond County’s consultant
    testified at hearing that there is no regulated recharge area
    in
    the vicinity of this facility.
    2 Tr.
    at p.
    44.
    D
    & L’s engineer
    testified the same.
    Tr.
    at
    p.
    51.
    The Board
    finds no evidence
    that the facility will be located within
    a regulated recharge
    117—132

    —17—
    area for which the Board would have issued applicable
    requirements.
    The Board finds that the County Board’s decision
    is not against the manifest weight of the evidence with respect
    to this criterion.
    Conclusion
    For the above-stated reasons, the Board finds that the
    decision of the Bond County Board of Supervisors, Bond County,
    Illinois granting approval to D
    & L Landfill,
    Inc.
    for a regional
    pollution control facility pursuant to the statutory requirements
    of Section 39.2(a) of the Act was not against the manifest weight
    of the evidence.
    This Opinion constitutes the Board’s findings of fact and
    conclusions of law in this matter.
    ORDER
    The Board hereby affirms the decision of the Bond County
    Board of Supervisors, County of Bond,
    Illinois, granting site
    location suitability approval for a regional pollution control
    facility to D
    & L Landfill,
    Inc.
    Section 41 of the Environmental Protection Act,
    Ill. Rev.
    Stat.
    1987,
    ch. l1l~,par.
    1041, provides for appeal of final
    Orders of the Board within 35 days.
    The Rules of the Supreme
    Court of Illinois establish filing requirements.
    IT IS SO ORDERED.
    Board Member
    J. Dumelle dissented.
    I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby cer~ifythatthe ab~pveOpinion and Order was
    adopted on the
    ~7~5Z4
    day ~
    ,
    1990,
    by a
    voteof
    ~.—/
    ~
    ~7.
    4~
    Dorothy M. Gy4~h,Clerk
    Illinois Poll.ótion Control Board
    117—133

    Back to top