ILLINOIS POLLUTION CONTROL BOARD
April
4,
1975
ENVIRONMENTAL PROTECTION AGENCY,
Complainant,
vs.
)
PCB 74—477
HANDSCHY CHEMICAL COMPANY,
)
Respondent.
Steven Weiss, Assistant Attorney General for the EPA
John Harris, Attorney for Respondent
OPINION AND ORDER OF THE BOARD
(by Mr.
Henss):
Handschy Chemical Company
is charged by the Environmental
Protection Agency with operating an air pollution source without
Agency permit from January
1,
1973
to December 17, 1974,
the
date of Complaint.
Such operation
is alleged to be a violation
of Rule 103(b) (2)
of the Air Pollution Control Regulations and
Section
9(b)
of
the
Environmental
Protection
Act~.
At the public hearing in this matter the parties submitted
a Stipulation of Fact in lieu of oral testimony.
No member of
the public testified at the hearing.
Handschy owns and operates a paint and ink manufacturing
facility
at
its Farac Oil and Chemical Division, Riverdale,
Cook County,
Illinois.
Equipment
at
this
facility
includes
varnish
cooking
vessels,
bail
mills
and.
storage
tanks
These
emission
sources
were
placed
in
operation
prior
to
September
2,
1971.
This
plant
produces
975,000
lbs.
of
ink
and
4,200~003
lbs.
of
varnish per year~ Emissions from the varnish
cooking
vessels are contro:Lied by two Venturi-type ~jet scrubbers~
On
August
ii,
1972
Respondent
requested
permit
applications
from
the
Agency
for
its
operation.
Some
two
months
later
Respondent
submitted
its
permit
application
to
the Agency.
This application
was
rejected
November
3,
1972
because the Company had failed
to
file
a
process flow diagram or its equivalent, had failed to
file
a compliance plan and progress completion schedu1e~and had failed
to file more than 15 other required documents.
16
—309
—2—
Handschy resubmitted its application for permit on
February 15,
1973 and it was rejected by the Agency on March
14,
1973.
This time the Company had failed to submit corporate
authorization for the signature on the p~rmitapplication,
an
adequate flow diagram and six other required documents.
Thereafter,for
a period in excess of
18 months,Respondent
did not file any other application or reapplication for an
operating permit.
On September 23,
1974 an Agency engineer visited
Respondent’s facility to discuss requirements
to obtain
a permit.
In
a
letter
dated
October
3,
1974 the Agency’s Region II Manager
notified
Handschy
of
certain
informational
requirements
which
were
to he met in a new permit application.
Respondent was also advised
that
the
Agency
was
considering
legal
action
for
certain
alleged
violations.
Three
weeks
later
Respondent
was
sent
another
“warning
letter” by the Agency which advised that correspondence within 14
days was required or the Agency would immediately initiate prose-
cution proceedings.
Respondent submitted its re-application for permit on
November 19,
1974 for which an operating permit was granted on
December
2,
1974.
Handschy
states
that
it was at all times
financially able to obtain a permit or variance and that the
permit was obtained without modification or replacement of any
existing equipment or addition of new equipment.
In its closing argument at the public hearing, Respondent
points out that it was diligent in its pursuit of
the
permit
from August 1972 to February 1973 after which
a “dormant period”
was entered.
Respondent believes that both parties are partially
responsible for the dormant period——Respondent for its inaction
and the Agency
for not contacting Respondent.
Respondent also claims it
is
a mitigating fact that the
Agency did not file its Complaint until after the permit had
been issued.
The fact that Handschy was able to secure the permit
without the addition of any equipment,
is said to be conclusive
proof that Handschy was not contributing
to any air pollution during
the time period involved.
Respondent believes that no monetary
p~na1ty should be imposed because of Respondent’s
acts of good
faith and “reasonable amount of diligence”
(R.
8).
This record clearly shows
that Handschy had full knowledge
of its lawful requirement to obtain an operating permit.
Efforts
to secure this required permit started over 4
1/2 months before
it was required to have such permit.
The record further shows
that Respondent’s initial applications were incomplete and that
16—310
—3—.
Handschy abandoned its efforts after two rejections.
The 18
month delay does not indicate diligence or any great concern
for compliance with the
law.
We find that Hancisehy was
dilatory and for approximately
1 1/2 years was
in deliberate
violation of the permit requirement.
The fact that no additional control equipment was required
when Handschy finally did obtain the operating permit does
indicate that there was compliance with emission standards.
This
is
a mitigating factor.
The Illinois Supreme Court has recently held that this
Board does not have authority to impose a monetary penalty for
punitive purposes and the imposition of a monetary penalty will
not be sustained unless it will aid in the enforcement of
the Act.
Southern Illinois Asphalt Company vs. Pollution Control Board,
~
de
where it appeared that the failure to obtain permit was inadvertent,
the Respondent was not dilatory or recalcitrant and had come into
compliance prior to the time the EPA commenced its prosecution.
We
impose a monetary penalty in cases
such as
this
one
as
an
aid
to
the enforcement
of
the
Act.
The
permit
program
is
crucial
for pollution control in Illinois.
If
an
emission
source
could
avoid
penalty by obtaining a permit at
any
future date then there
is no incentive
tc comply with essential deadlines.
The emission
source could delay filing
a permit application until. its omission.
was discovered by the Agency.
For
a
deliberate
omission
the
penalty
must
be
imposed.
The
Supreme
Court
implies
that
a
penalty
can
be
imposed
where
necessary
to
aid
enforcement
of
the
Act
and
where the Respondent has been dilatory
or
recalcitrant
as
Handschy
was
in
this
instance,
I a~
ir~
ons
merE
t
e~
t
LrC
~c
~r
ii
L
T~
tL’~
tinting
or
the
Board
that
mandscny
Cnemicaa
vioratec
Rule
1a3 (h
(2
of the Regu±ationsand Section
9(b)
of the ~ct from
$anuary
1,
1973
until December
2,
1974.
A civil penaLty in the amount of $500 is
appropriate.
This Opinion constitutes the findings of fact and conclusions
of law of the Illinois Pollution Control Board.
ORDER
It is the Order of the Pollution Control Board that Handschy
Chemical Company shall pay to the State of Illinois by April
31,
1975 the
sum
of
$500 as a penalty for the violations
found in this
proceeding.
Penalty payment by certified check or money order
payable to the State of Illinois shall be made to:
Fiscal Services
Division, Illinois EPA,
2200 Churchill Road,
Springfield, Illinois
62706.
16—311
—4—
I,
Christan
L.
Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the
bove Opinion and Order was adopted
this
L.~1~’
day of
-
,
1975 by a vote of ~
to_____
16—312