ILLINOIS POLLUTION CONTROL BOARD
October
28, 1971
ENVIRONMENTAL PROTECTION AGENCY
v,
)
PCB 71—108
MODERN FOUNDRY
AND
MANUFAC-
TURING COMPANY
Jim D, Keehner, Attorney
for the Environmental Protection Agency
William D.
Stiehi, Attorney
for Modern Foundry and Manufacturing
Co.
Opinion of the Board
(by Mr. Kissel):
On May
13,
1971,
the Environmental Protection Agency
(the
“Agency”)
filed
a Complaint with
the
Board alleging that
the Modern
Foundry and Manufacturing Company
(“Modern Foundry”)
has since
July
18,
1967 emitted certain contaminants
into the atmosphere
so
as to violate the Air Pollution Control Act,
the Environmental
Protection Act and the rules and regulations promulgated there-
under.
The Agency requested that
a cease and desist order be
entered against Modern Foundry requiring
it to stop all the alleged
violations
and further,the Agency requested that money penalties
be assessed against Modern Foundry.
A hearing on the Complaint
was held in Belleville,
Illinois on August
12 and 13,
1971, before
George Faber,
the duly appointed hearing officer.
Modern Foundry operates
a gray
iron casting shop in Mascoutah,
Illinois,
In this process it uses
a
#5 Whiting cupola in which scrap
iron is melted after being charged with coke.
The melted iron is
then poured into sand molds,
allowed to harden;
then the molds
are
shaken out.
The principal problem from
a pollution standpoint in
the operation of the Modern Foundry plant has been the emissions
from the cupola.
Based upon
the computations made by
the Agency,
and testified
to by Mr. Telford, Modern Foundry emits 65 pounds per
hour of particulate matter, when the regulations only permit them
to emit 17 pounds per hour.
See
Rules and Regulations Governing the
Control
of Air Pollution, Rule 2-2.54. Modern Foundry did not deny
that it had violated the law at least since 1967 when the regulations
went into effect;
in
fact,
it admitted on the record that it was
guilty of air pollution from 1967
to the date of the hearing.
The
only reservation which it imposed was that it felt that because of
the statute of limitations the Board could not impose penalties
on
2
/21
paragraph
12 relating to the completion of plans and specifications
18 months before the completion date
for tertiary facilities
and
award of the construction contracts
12 months before the completion
date.
In other words, the City is under
a requirement to provide
tertiary treatment by July,
1972
and it is under
a further re-
quirement to submit plans by January,
1971
and award construction
contracts by July,
1971.
Under the regulations the City has
a legal
duty at this
time to
let contracts and commence construction
to
meet
the BOD and suspended solids effluent standards and the chlorina-
tion requirement
by ~uly,
1972.
With
its petition, the City asked
for
a six-month extension of the SWB-l4 timetable
for construction
of needed facilities.
The organic load on the plant is more than twice the designed
capacity
(R.37,44)
.
The plant
is handling an average monthly popula-
tion equivalent of 97,000
(EPA Ex,
3)
although
the city engineer
estimated that it was currently
at 80,000
(R.37)
industrial waste surges sometime peak the plant
at
a popula-
tion equivalent
of 150,000
(R,44)
.
The facilities
are thus stressed
by an incursion of up to 400
of the contaminants which
the plant
was designed to handle,
The problem at the plant is one of industrial waste
loading.
In an effort to deal with
the difficulty and redistribute the
cost of treatment,the
City passed an industrial waste ordinance
on February
11,
1970.
Mr.
Jack Faggetti,
the
City Engineer,
stated
that “If all the plants would comply with the Industrial Waste Ordi-
nance,
we would be below the design population equivalent of the
plant,”
(R.45)
There
are three principal industrial waste dischargers
to the
Olney plant.
A chicke~.processing plant,
Kralis Poultry Company,
Inc.
(Kralis)
;
a
dairy
products
company, Prairie Farmer Dairy,
Inc.
(Prairie)
and
a
metal
fabricating
plant,
AMF
Incorporated
(AMP)
Kralis dresses 16,000 chickens
per
day, employs
100 persons
(P.12)
and is responsible for
a population equivalent load of
26,000
on
the treatment plant
(R.44)
The company’s effluent contains
£ at
and
grease and chicken viscera
(P.11)
.
Kralis
is proceeding
to
install pretreatment facilities which
are due
to be operational
in
the early part
of December,
1971.
AMP
is also presently working
on its
pretreatment
~iant
and
plans
to
be
operational
by
December,
1971,
too
(P.10,
33-34)
.
Prairie has apparently done nothing.
Mr.
Cloren Jourdan,
the treatment plant superintendent,
testified
at
the hearing
of
a recent sample
of Prairie’s effluent which contained
a suspended solids concentration of 12,000 mg/I
(P.79)
probably due
to
a loss of sugar.
Obviously,
the City must take some steps
to be
assured that abatement through pretreatment will be effected at
Prairie.
The City must pursue the matter assiduously
for its pro-
posed program to succeed.
2
—
722
Modern Foundry did not meet the
date of September,
1970,
for
the installation and operation of the wet scrubber system on
the
cupola.
It wasn’t until recently that they did have the equipment
installed and operating.
The Board was advised by letter from
Modern Foundry that all pollution control equipment was installed
by September
15,
1971, and recently advised the Board that stack
tests
on the facility indicate that the emissions were within the
permissible limit of the regulations,
Since the pollution control equipment has been installed,
and is apparently operating properly, the only issue before the
Board at this
time is whether a money penalty should be assessed
against Modern Foundry.
The evidence in the record establishes
that the operation of the Modern Foundry plant did have an effect
on the life
and property of the neighbors.
Although there was
some dispute about this, one witness was quite emphatic about the
dust emissions from the plant and he described
the odor from the
plant as “rancid and sulfurous”.
(R.
95)
Other witnesses, mostly
employees
of the plant, said they had never heard complaints
about the operation of the plant.
While we
are certain this testi-
mony was made in good faith,
it must certainly be somewhat dis-
counted when weighed against the testimony of an independent
witness who brought pictures
to prove
his allegations.
In addition
to the testimony from the neighbor, Modern Foundry admitted the
fact that they were in violation of the statute
and the applicable
regulations,
and further, didn’t contest the calculations of the
Agency witness that the emissions from the cupola were 65 pounds
per hour and the allowable particulate emissions by regulation was,
and is,
17 pounds per hour based upon the process weight of Modern
Foundry.
Based upon the foregoing,
a penalty
is called for in this
case, but the question still remains as to the
amount.
We have
long held that, while
an ACER?
is not valid for longer
than one year,
it is
a defense in an action for penalties against
the person holding the ACER?,
EPA
v. Commonwealth Edison Co.,
PCB 70-4,
dated February
17,
1971.
In this
case Modern Foundry
did have an effective ACERP which allowed it until September of 1970
to install and have in operation the pollution control devices;
therefore,
until
that date no penalty can be assessed
for Modern
Foundry’s
failure to complete its program.
While
the record does
show that Modern Foundry did
“drag its
feet” during this time,
the
fact is they hired
a contractor to do
the job and were proceeding
with
the program.
The ACERP also required that Modern Foundry
submit “periodic reports” which
it forgot about,
But the record
does show that Modern Foundry did send letters
to the Agency and
its
predecessor advising the Agency,
et al,
of the progress of the
2
—
723
installation of the wet scrubber.
Certainly,
this is minimal com-
pliance with
the requirement to submit “periodic reports”, but
nevertheless,
it was
an attempt of
the kind that would say that
Modern Foundry was not consciously avoiding and not following the
terms of the ACERP,
If they had so avoided the conditions
of the
ACERP,
the ACER? would no longer be
a defense to any action
for
penalties.
If penalties
are to be assessed, it must b~ for the
period
of time beginning in September,
1970
to September,
1971,
II
when
the equipment was finally installed.
The
ACER?
ran
out in
1970,
and
although Modern Foundry was specifically advised by
the Agency that
it
must
file
for a variance,
it didn’t.
This
is
a conscious dis-
regard for the
law and forms
the
basis
for the imposition
of
a
penalty since during this period Modern Foundry, by
its own admission
and the evidence previously described,
was emitting contaminants
which were
in excess
of the regulation and causing “air pollution”.
Modern Foundry attempted to explain the delay
in installation and
operation of the equipment on these ground:
first,
it said that
it
discovered
that the ~ity would not be able
to supply sufficient
quantities of water and
this caused Modern Foundry to install
a
water tank
which
took an additional month
or
so;
second,
the con’~
tractor changed the design of
the wet scrubber; and third, the
equipment was
not
delivered on time.
We think that none
of these
reasons are valid
after the
fact,
Modern Foundry should have,
as it was
advised
to do,
filed for
a variance long
ago.
These
may,
or may not, have been reasons for granting
of
the
variance
at that time, but are not reasons for not imposing
a penalty
now,
But the penalty must
indeed
be
a
small one because of the financial
condition of the company.
In 1971,
for example,
the company
sus-
tained
a loss of $10,140.69,
and the equipment which has
just been
installed will impose an additional financial burden on the company.
Further,
we
take into account that
some teetimony indicated that
the effect of the emissions
on the community were negligible.
We,
therefore, after consideration of all circumstances outlined in this
opinion impose
a penalty of $1,000.
If the financial circumstances
of the company were different the penalty would be higher,
1
Since the time period
for the penalty involves only the
last year,
it is not necessary to deal with
the point made by
Modern Foundry’s attorney that the statute of limitations applicable
to penalties under the Environmental Protection Act is
18 months,
2
—
724
This opinion constitutes
the findings
of fact and conclusions
of law of the
Board.
ORDER
Based upon the evidence and exhibits
in the record,
the Board
hereby makes
the following orders:
1.
Modern Foundry shall cease and desist from the
operation of its cupola at Mascoutah,
Illinois,
so
as
to violate the Act or the applicable regulations.
2.
Modern Foundry shall submit to the Board and
the Agency the final specific results of the stack
test recently done on the stack with
the pollution
control equipment.
3.
Modern Foundry shall pay a penalty to the
State in
the amount of $1,000 for the reasons
stated in the opinion,
I, Regina
E.
Ryan,
Clerk of the Pollution Control Board,
certify that the Board adopted the above Opinion and Order this
28
day of
October
,
1971,
~-
~
~E.Ryan,Clerk
2
—
725