ILLINOIS POLLUTION CONTROL BOARD
December 20, 1973
NASHUA CORPORATION
Petitioner,
vs.
)
PCB 73—419
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
OPINION
AND
ORDER OF
THE
BOARD
(by Mr. Seaman):
On October
2,
1973,
Petitioner, Nashua Corporation,
filed its Petition requesting
a variance until April
30,
1974,
from Rule
205(f)
of the Air Pollution Control Regulations
(effective January
1,
1974)
in order to allow operation
of its Pressure Sensitive Tape Coating Operation at its
Industrial Tape Division Plant located at 7800 South
Woodlawn Avenue,
Chicago,
County of Cook,
Illinois.
Petitioner also requested,
therein,
a variance from
Rules 103(b)
(2)
and 103(b) (1)
in order to allow the
operation of said Pressure Sensitive Tape Coating Operation
and of new air pollution control equipment without an
Agency operating permit.
By
a Motion dated December
4, 1973,
Petitioner withdrew its request for a variance from Rules
103(b) (1)
and 103(b) (2).
Petitioner~sprincipal place of hu’~inessis in
Nashua, New Hampshire.
Petitioner manufactures and sells,
nationally and internationally,
electrostatic copy paper,
label papers, pressure sensitive tapes and computer disk
packs, and petitioner, additionally,
is in the photo-finishing
business and engages in various other operations outside
the United States.
In 1970,
Petitioner acquired a plant at 7800 South
Woodlawn Avenue,
in Chicago, Illinois, which had been
constructed many years previously
(such plant being now
known as the Industrial Tape Division Plant and hereinafter
referred to as the “Plant”)
.
Petitioner has since operated
the Plant to produce pressure sensitive tape and pressure
sensitive label papers.
A total of 200 hourly employees
10
—
457
—2—
and 65 salaried employees are employed at the Plant,
representing
an annual payroll of approximately $3.5
million.
The annual sales volume of products manufactured
at the
Plant
is approximately $17 million; and approximately
$11 million thereof represents pressure sensitive tape
and pressure sensitive label papers processed through the
aforementioned Pre~sureSensitive Tape Coating Operation
(hereinafter referred to as the “Coating Operation”)
at
the Plant.
The Coating Ooeration is only one of the various
production
facilities utilized at the Plant for production
of the finished products there manufactured.
The Coating
Operation
is located in a large enclosed area of the
Plant.
The production equipment consists, essentially,
of a series of machines called “coaters”.
The adhesive
coating liquid used i3 produced at the Plant through
earlier production
steps and consists, principally,
of
rubbers
(natural and synthetic)
,
resins,
solvents, pigments,
plasticizers, and special property chemicals.
The Plant
operates on a 24-hour day schedule for five days
a week,
plus frequent overtime operations.
In the coating process,
in an average 24—hour day
operation,
approximately 88,000 pounds of raw material
are utilized in the production process consisting of
approximately 40,000 pounds of web material and about
48,000 pounds of adhesive coating liquid made up of approx-
imately 30,000 pounds of solvents,
14,000 pounds of rubber
compounds,
4,000 pounds
of resins,
50 pounds of pigments,
50 pounds of plasticizers
and 200 pounds of special property
chemicals.
The solvents used, and the average approximate
daily use thereof,
are: naptha
—
18,000 pounds; toluene
6,000
pounds; hexane
-
3,000 pounds; and heptane
-
3,000
pounds.
There
is no measurable emission of~rticu1atematter
from the Coating Operation.
Approximately
98 percent of the
solvents in the aforementioned adhesive coating liquid
are removed by evaporation in the Coating Operation.
Of
the solvents involved, only toluene is
a photochemically
reactive material as that term is defined in Rule
201 of
the Board’s Air Pollution Control Regulations.
The estimated
hourly emission of toluene in the course of an average
daily operation of the Coating Operation
is approximately
250 pounds.
The average hourly emission of organic material
represented by the other solvents in an average daily
operation of the Coating Operation is approximately 1,000
pounds.
The emission of solvents from the Coating Operation
does not involve an odor nuisance and, therefore,
under
10—458
—3—
the terms of Rule 205(f),
the limitations of Rule
205(f)
apply only to the photochemically reactive
material,
to wit, the toluene.
The estimated rate
of discharge
of toluene of 250 pounds per hour
is
clearly far in excess of the prescribed limitation
in Rule 205(f)
of eight pounds per hour.
Petitioner
alleges that in all other respects the Coating
Operation is and will be in compliance with the Illinois
Environmental Protection Act and the rules and regulations
of the Board thereunder,
as is true of the other operations
at Petitioner’s Plant.
There
is no substantial emission
of solvents from any other operation at the Plant.
At present,
there
is no air pollution control
equipment in place for the controlling of the emission
of solvents from the Coating Operation.
On December 20,
1972, Petitioner filed with the
Agency its application for a construction permit for the
construction of an air pollution control facility at
the Coating Operation consisting of three carbon absorption
units designed to remove about
95 per cent of all the
solvents emitted by the Coating Operation and thereby to
comply with the standards for emission of organic materials
set forth in Rule 205(f)
as effective January
1,
1974.
Petitioner concurrently filed with the EPA a compliance
plan relating to
such air pollution control equipment,
and a project completion schedule for the installation of
the system.
The costs are presently projected at $730,000
for equipment and $656,000 for installation,
in addition
to which engineering costs in connection with the particular
project are projected at approximately $135,000,
or
a
total projected cost of $1,521,000.
In addition,
the
installation of this air pollution control equipment has
required the expansion of the existing boiler house
facilities at the Plant at an overall cost of approximately
$700,000.
The initially scheduled date for completion of
installation of the air pollution control equipment was
December
1,
1973 and the initially scheduled date for
placing the same in full operation was December 31,
1973.
On February
1,
1973,
the EPA issued to Petitioner its permit
for the construction of said air pollution control equipment.
Petitioner alleges that it has pursued with all
diligence the procurement and installation
of such air
pollution control equipment, but,
for reasons allegedly
beyond its control, Petitioner has encountered delays which
10—459
—4—
prevent Petitioner from meeting the aforesaid scheduled
dates for completion and operation of said equipment.
Petitioner alleges that subsequent
to the filing
of the construction permit application, the project
completion schedule and the project compliance plan,
ongoing more detailed engineering and design study and
analysis revealed substantial, unanticipated design problems
in two principal areas.
First,
such study and analysis
showed the need for major structural changes in the building
housing the Coating Operation in order to accommodate the
air pollution control system.
Second,
such study and
analysis showed the necessity to expand the ?xisting boiler
house
facility in order to generate sufficient steam
capacity to handle the additional requirements of steam for
the adsorption system.
The emergence of these two factors
in turn expanded the necessary design work of Petitioner’s
consulting engineers about threefold and this
in turn
increased the time needed for completion of the design
work by about eight weeks.
This
time delay in turn
allegedly caused corresponding delay in the execution of
construction contracts and the commencement of construction
work on the project.
In its Recommendation,
the Agency states that the
construction permit was granted because the Agency believes
that Petitioner’s proposed.control program will bring
the Coating Operation into compliance with Rule 205(f).
Petitioner alleges that denial of the requested variance
would cause an arbitrary and unreasonable hardship since
it would necessitate closing down the coating operation
which would result in the layoff of
190 employees,
loss of
$210,000 of production per week,
and loss of business to
competitors.
The Agency feels that the hardship that
Petitioner would suffer if the variance from Rule
205(f)
is not granted coupled with Petitioner’s diligence in
establishing a control program, outweighs any possible
harm to the public which would result from Petitioner’s
violation of Rule
205(f)
for four months after its effective
date.
We are disposed to grant the variance as requested
by the Petitioner and as recommended by the Agency.
However,
this has been
a most difficult decision.
The discharge
of 250 pounds of toluene per hour over
a period of four
months cannot conceivably be characterized as having
negligible or insignificant impact on the quality of our
environment.
As
in similarly difficult cases in the past, we have
reached our decision by an analysis and balancing of the
respective hardships.
We emphasize to Petitioner that although
this Board have given it the right to operate for the period
10 —460
—5—
of the variance, Petitioner must recognize what is at
least
a moral duty to exercise the utmost diligence to
complete its control program
as quickly as possible.
This Opinion constitutes the findings of
fact and
conclusions of law of the Board.
ORDER
IT IS THE ORDER of the Pollution Control Board
that Petitioner, Nashua Corporation, be granted
a
variance from Rule 205(f)
of the Air Pollution Regulations
until April
30,
1974,
for its Pressure Sensitive Tape
Coating Operation,
subject to the following conditions:
1.
Petitioner shall obtain all necessary
operating permits from the Agency;
2.
Petitioner shall notify the Agency upon
completion of its control program.
I,
Christan L. Moffett, Clerk of the Illinois Pollution
Control Board, certify that the abov
Opinion and Order
was adopted on the ~
day of
_______________,
1973
byavoteof
~
to
~
10
—461