ILLINOIS POLLUTION CONTROL BOARD
February
5, 1987
JOLIET SAND AND GRAVEL COMPANY,
Petitioner,
v..
)
PCB 86—159
ILLINOIS ENVIRONMENTAL
PROTECTION AGENCY,
Respondent..
JOHN
L..
PARKER
(JOHN
L..
PARKER &
ASSOC..) APPEARED ON BEHALF OF
PETITIONER, AND
MICHAEL 3. MAHER,
ASSISTANT ATTORNEY GENERAL, AND JOSEPH
R..
PODLEWSKI APPEARED ON BEHALF OF RESPONDENT..
OPINION AND ORDER OF THE BOARD
(by 3.
Anderson):
This matter
comes before
the Board on the September 30,
1986
petition
filed by Joliet Sand and Gravel
Co..
(Joliet)
seeking
review of
the denial by the Illinois Environmental Protection
Agency (Agency)
of
a renewal
of the facility’s operating
permit..
Joliet’s sand
and gravel processing plant
is located at
2509 Mound Road
in Joliet,
Illinois,
and engages
in primary and
secondary limestone crushing and related
activities..
Although hearing was authorized
by the Board’s Order
of
October
9, 1986,
evidentiary hearings did not take place
until
January 13—14,
1987.
Hearings which
had previously been set for
November
19
and 25 and December 10, 1986 were convened but
progressed as on—record, pre—hearing conferences at which
discovery—related matters were discussed..
The discovery process
in this matter was unusually lengthy and contested,
resulting
in
truncation of
the time available
in which
to put on evidence at
hearing
for review by the
Board..
These matters are chronicled
in
the Board’s Orders
in response
to various “emergency”
and routine
motions, and will not again
be set forth
in detail
here.
The
Board
incorporates by reference the following:
Orders of
November
6
and
20,
1986; Orders of December
18 and 23,
1986;
and
Orders of January 12,
22 and
26,
1987..
Pursuant
to leave granted
by Order
of January 26,
1987,
the parties simultaneously filed
briefs on February
2,
1987..
Finally,
the
Board notes that decision was originally due
on
January
28, 1987 pursuant
to the 120 day decision deadline
established
in Section 40(a)(l)
of the Environmental Protection
Act
(Act)..
Joliet waived this deadline
until February 5
at the
75-228
—2—
commencement of the January 14 hearing, confirmed this waiver
in
writing on January 22,
and then later on the same day extended
the waiver
through February
12..
On January 26, Joliet further
extended the decision deadline through March
5,
in the context of
a request
for
additional
hearings..
As the hearing request was
denied
for the reasons set forth in the Board’s January 26 Order,
decision
is being rendered consistent with the waiver
through
February 12
to avoid
issuance of a permit by operation of
law..
PRELIMINARY MATTERS
Pending Written Motions
The earliest filed motion still pending
is the Agency’s
December
30, 1986 motion
for
costs and
a January 7,
1987
supplement
thereto..
Joliet
filed
responses in opposition
on
January
5 and
12..
The motion seeks award of
$l54..77
to the
Agency,
these being
the costs
and
salaries
of three employees who
appeared
for
hearing on November 25 pursuant
to notice served
November
24..
At
the pre—hearing
conference held November
19,
the
Hearing Officer had stated that it was necessary to at least open
the hearing scheduled
for November
25
in order
to comply with
notice
of hearing requirements..
The Hearing Officer additionally
noted, however, that
in
the event discovery was incomplete,
that
if either party or both parties were unable
to proceed that the
hearing would
be
continued..
R..
11—19—86,
p..
36,
38_39*..
At the
November
25 hearing, counsel
for Joliet stated that he was not
in
a position
to state that “we have enough discovery to permit
us
to properly present our case
at this hearing....,
and therefore
I
ask that this hearing
be
continued”..
R..
p..
63—64..
This request
was granted and none of the three witnesses were called..
It is
the Agency’s position that Joliet knew that it would
not need
to
“put on”
its case on November
25,
and that it had “needlessly
caused
the wasted
and
futile appearance
of three Agency personnel
who had rescheduled
their workload
to attend the scheduled
hearing”..
Motion,
14..
While
the
Board believes that the imposition of the costs
requested would
be appropriate,
the Board
finds
it impossible
to
do
so..
The Act specifically provides
for the shifting
of costs
from one party to another
in two
instances..
The first is
pursuant
to Section 42(f), authorizing payment of costs incurred
by the Attorney General
or State’s Attorney by
a person found
to
have committed “a willful, knowing,
or repeated violation of the
*
The
transcript of
the November
19 hearing
is numbered pages
1
through
79..
The transcript of the November 25 hearing begins
again
at page
1;
the transcripts of the December
8 and January
13—14 continue pagination
in sequence after
the November 25
tranScript..
Reference
to the November
19 hearing
transcript
is
to
“R..
11—19—86,
p..
____“
and
to
all others
“P..
____
75-229
—3—
Act..”
The second
is pursuant
to Section 31.1,
authorizing
payment of costs
incurred by a person who has unsuccessfully
appealed
the issuance of an administrative citation..
These
specific grants of authority
to shift costs militate against
a
finding
that the Board
has some general,
inherent authority to
shift
these costs
in cases which are not enforcement actions..
The Agency’s motion
is therefore denied
on the basis that
it
seeks relief beyond the Board’s authority
to grant..
However, as
this authority issue has not been fully briefed, the Board will
entertain further argument
in the context of
a motion for
reconsideration..
The next filed motion
is the Agency’s January 12,
1987
motion for dismissal with prejudice,
to which Joliet filed
a
response
on January
20..
The motion asserts that Joliet has
failed
to comply with Hearing Officer Orders
to provide both
answers
to interrogatories and production of documents, that this
conduct was
intentional
and wrongful, and that as
a result
Respondent’s case has been
so prejudiced that the only
appropriate remedy
is dismissal of the action with prejudice..
In relation
to this motion,
the Agency on January
27
applied
to the Hearing Officer
for
an Order finding non—compliance with
an Order
to answer
interrogatories..
Joliet filed
a response
in
opposition on January
28..
The Hearing Officer referred the
matter
to
the Board
on February
4..
The Board
finds that Joliet
made
a literal response
to the interrogatory as drafted..
While
Joliet could have been more forthcoming,
the Board cannot find
that it did not comply with the Order..
In additional
response
to the motion
to dismiss,
the Board
notes
the described sequence of events may well have impeded the
Agency’s preparation and presentation of its
case..
Yet, based
on
the Board’s review of
thc~
hear~nr~
-i--
of
specific al!~
w~.,.Cfl
tne
Agency’s case was prejudiced,
the Board does not
find that the
extreme relief requested is warranted..
The motion to dismiss
is
denied..
The next filed motion
is Joliet’s February 2,
1987 motion
to
correct typographical errors
in the January 13—14,
1987 hearing
transcripts..
A similar motion
to correct errors
in the November
25 and December
8 transcripts was filed on February
4..
The Board
agrees with Joliet’s characterization of these errors, and grants
the motion
to correct..
The Clerk
is directed
to delete the words
“proposed”
from
the errata sheets
included
in
the motions,
and
to
bind copies thereof
in the originals of the hearing
transcripts..
The Board notes that its review of these changes
was greatly facilitated by Joliet’s submittal of copies of the
transcript pages with corrections
inserted by hand..
75-230
—4—
Finally, on February
4,
1987,
Joliet filed
a reply brief
accompanied by
a motion for leave
to file instanter..
The Agency
filed
a reply in opposition which asserts that
a reply brief
is
procedurally improper under
these circumstances, particularly
since Joliet had
filed
no main brief,
and requests that decision
be made on the basis of the Record
and its brief..
It
is clear
that,
for whatever reason,
the Agency has not received Joliet’s
brief
filed with
the
Board February
2.
This disturbs some of the
factual premises of the Agency’s opposition..
Notwithstanding,
the Agency
is correct that the simultaneous briefing schedule
established
by the Board does not provide for
reply briefs..
To
accept
a reply brief
filed on the day before decision under
circumstances where
the Agency could not be given
a reply
opportunity because
it had not received Joliet’s brief would
be
unfair..
It
is additionally onerous
to the Board to receive
additional briefs
on the day before
a scheduled decision..
The
motion
is denied..
Evidentiary Issues and
Scope of Review
The
remaining preliminary matters worthy of the Board’s
attention at this point are various assertions of error
in regard
to
the Hearing Officer’s conduct of the hearing..
While some of
these were reiterated
in the final briefs, most are reflected
only
in
the hearing
transcript.
The Board will not address all
objections
in detail, affirming all rulings not otherwise
addressed..
The Board again
affirms the procedures established
by the
Hearing Officer
for presentation of
testimony and evidence at
the
two—day hearing..
The Board
has repeatedly and exhaustively
rejected Joliet’s assertions that its due process
rights have
been violated, and will not here repeat
the rationale stated
in
those Orders which have been incorporated herein by reference.
Before address~rg
the
various evidentiarv issues, the Board
will briefly reiterate the scope of review of permit appeals
~ex~:r~.lv,
and more specifically as they relate
to
the
sequence
of events involved
in the
instant permit denial..
The Board’s historic approach to permit denial hearings was
best stated
in Oscar Mayer
and
Co..
v.
IEPA, PCB 78—14,
30 PCB
397,
398
(1978):
“Under
the
statute,
all
the Board
has authority to
do
in
a
hearing
and determination
on
a
Section
40
petition
is
to decide after
a hearing
in
accordance
with
Sections
32
and
33(a)
whether
or
not,
based
upon
the
facts
of
the
application,
the
applicant
has
provided
proof
that
the
activity
in
question
will
not
cause
a
violation
of
the
Act
or
of
the
regulations..
75-231
—5—
In
a
hearing
on
a
Section
40
petition,
the
applicant must verify
the
facts of his application
as
submitted
to
the
Agency,
and,
having
done
so,
must
persuade
the
Board
that
the
activity
will
comply
with
the
Act
and
regulations..
At
hearing,
the
Agency
may
attempt
to
controvert
the
applicant’s
facts
by
cross—examination
or
direct
testimony;
may
submit
argument
on
the
applicable
law
and
regulations
and
may
urge
conclusions
therefrom;
or,
it may
choose
to
do either;
or,
it
may choose
to present
nothing.
The written
Agency
statement
to
the
applicant
of
the
specific,
detailed
reasons
that
the
permit
application
was
denied
is not evidence of the truth of
the material
therein
nor
do
any Agency
interpretations
of
the
Act
and
regulations
therein
enjoy
any presumption
before
the
Board..”
The Illinois Supreme Court,
and various appellate courts
have confirmed the validity of this approach,
e..g.. Waste
Management,
Inc..
v.
IEPA, PCB 84—45,61,68, Opinion and Order
of
October
1,
1984 and
Supp..
Opinion and Order of November 26, 1984,
aff’d sub nom.
IEPA
v..
IPCB,
138 Ill.
App. 3d 550
(3rd Dist.
1985), aff’d
_____
Ill.2d
___,
No..
63062
(December
19,
1986)
(Board need
not apply manifest weight of the evidence standard
in
reviewing Agency permitting
decisions)..
In its permit denial
letter, the Agency must specify all
reasons
for
its denial
of
a
permit,
and
is precluded from raising new reasons
for the first
time before the
Board..
IEPA v.
IPCB,
86
Ill..2d 390,
404—405,
427
N,E..2D 162
(1981)..
The Board must consider the application as
submitted
to
the Agency, and may not be persuaded by new material
not before the Agency that the permit should be granted.. IEPA v.
IPCB and Album,
Inc.,
118
Ill..
App..3d 772, 455 N..E.2d 194
(1983).
To
the extent that the Agency has relied upon
information beyond
that contained
in the application, such
information must be
included
in the permit record
filed with the
Board;
if
it
is not,
the applicant may properly submit such
information
to the Board during the course of the Board’s
hearing..
Additionally,
if there was information
in the Agency’s
possession upon which
it reasonably should have relied, the
applicant may also submit such information to
the Board
for the
Board’s consideration. Waste Management, supra,
Frinks Industrial
Waste,
Inc..
v..
IEPA, PCB 83—10, June 30, 1983;
Sherex Chemical
Co..
Inc.
v..
IEPA, PCB 80—66,
39 PCB 527—528
(1980),
aff’d sub
nom..
IEPA
v..
Sherex Chemical
Co. and
IPCB,
100
Ill..
App..3d 735
(1981)..
While
the permitting
chronology for
the Joliet site will
be
discussed
later
in more detail,
for the nonce the salient facts
are as
follows..
Joliet’s initial operating permit was issued
on
December 30,
1980,
to expire on December
21, 1985,
Joliet
applied for renewal
of this permit on December
16,
1985..
The
75-232
—6—
Agency denied
the
renewal on March 7,
1986.
Joliet submitted
additional information on June
16, 1986 and again requested
renewal
of the permit.
This renewal application was denied on
August 26,
1986..
The Agency asserts that the correctness of the Agency’s
first permit denial
on March
7,
1986 is not at issue
here..
The
Agency argues that by failing
to appeal that denial within 35
days as required by Section 40,
Joliet
has waived any right
to
contest error
(P.
332—335, Agency Brief
at 7—8).
The Board
agrees,
and does not find persuasive Joliet’s arguments that the
first denial was not ripe
for review until
after
the second
denial
(P.
333—334)..
The
Board agrees with Joliet that
there
is
a
“continuum”
between the information considered by the Agency on March
7 and
August
26: Joliet’s June
16
letter
in response
to the March
7
denial
(Pet.
Exh..
21,
R..
Exh.
3)
clearly indicates that
it was
intended to
be supplemental
to
the December
16,
1985 application
for renewal
(Pet..
Exh..
3).
The Hearing Officer was correct
in
admitting evidence concerning
the March
7 denial
to the extent
that such evidence could
be relevant to correctness of the August
26 denial..
The Hearing Officer
excluded several
exhibits identified
and
offered by Joliet which consist of documents contained
in the
Agency’s file relating
to the original operating and construction
permits issued
for the Joliet facility.
These
are Petitioner’s
Exhibits
5,
6,
8,
9,
10,
11,
12,
13,
14, as marked
for
identification,
and submitted
to the Board by way of offer of
proof..
The Hearing Officer’s exclusion
of these exhibits
is
reversed,
and they are admitted
as evidence.
As Joliet argued
(see
e..g..
P.288—291),
the application
for renewal
of an operating
permit provides for incorporation of data from prior permits and
requires certification that previously submitted information
remains true and correct.
The expiring operating permit
in turn
references
the construction permit, which was issued
on the basis
of the application and information submitted
in
1980.
Without
regard
to
the probative value
to be assigned
to this data
concerning
prior permitting history, Joliet has persuaded the
Board
that it cannot be excluded on relevancy grounds..
The Hearing Officer
also excluded from evidence, but
received offers of proof concerning,
documents marked
as
Petitioners Exhibits 25,
26
and 27 for
identification.
These
documents consist of calculations estimating
emissions from
Joliet’s facility prepared by Andrew Rathsack, Joliet’s
consulting
engineer..
These exhibits were denied admission based
upon the Agency’s objection that the witness had not previously
been made available for deposition concerning
the calculations
or
other matters..
R.
590—591.
While the Board appreciates
this
75-233
—7—
rationale,
the Board will admit
the calculations, which are self—
explanatory.
PERMIT CHRONOLOGY
Witnesses
Seven witnesses were called by the parties.
They are listed
below with a brief description of their qualifications and
relation
to the permit
issues..
Harish
B..
Desai, IEPA
In 1986,
unit manager
in the Agency’s air permit section and
supervisor of Anton Telford,
who reviewed and initialed the
permit denial
letters drafted by Telford and signed by Mathur
March
7 and August
26,
1986..
Conducted
no independent review of
permit
record..
P.
543—547..
Bharat Mathur,
IEPA
Between 1980—1986,
Manager of the Agency’s Air Permit
Section.
Signer
of 1986 permit denial letters drafted by
Telford..
Conducted
no independent review of permit
record..
Named author
and
signer of memo of October
9, 1986 prepared by
Telford designating
items in Agency permit record
for this
appeal..
Pet..
Exh,
2.
Conducted
no independent review..
P..
535—
542..
Andrew Rathsack, Andrews Environmental Engineering,
Inc..
Involved
in preparation of Joliet’s permit applications
since
1980.
R.
585—609..
Christopher Romaine, IEPA
Manager
of
the New Source Review (NSR) Unit
in
the Agency’s
air permit
section..
As
it related
to NSR, reviewed
and initialed
August
26 denial letter drafted by Telford..
Conducted
no
independent
review of accuracy of calculations.
P.
619—638..
Anton Telford,
IEPA
Permit Engineer
in the Agency’s air permit section.
Analyzed Joliet’s December, 1985
and June, 1986 permit renewal
applications and drafted denial letters.
Generated calculations
relied on by other Agency personnel.
Designated documents
filed
with the Board
on October
24,
1986
as Agency Record.
75-234
—8--
Martin Tippin, IEPA
William Zenisck,
IEPA
Each is an environmental protection specialist
in the
Agency’s
air permit section, and
a certified smoke
reader.
Each
has conducted compliance inspections at the Joliet facility
within the past three years,
and has made visual opacity
readings..
The Joliet Permits
Joliet Sand and Gravel
Co..,
then owned by Rein, Schultz and
Dahi
of Illinois,
Inc..,
filed its application
to construct and
operate
a sand and gravel
processing plant on May
29,
1980..
Pet..
Group Exh.
14..
The equipment referenced
in the application was
a
primary jaw—crusher
identified
as Pioneer Model
3042,
a secondary
roll crusher identified as Pioneer Model 2454,
and
a Pioneer
Model
526
F
screen.. Resp.
Exh.
l4—L..
The Agency denied
the
permit on July
28, 1980 due
to Joliet’s failure
to submit
calculations for projected, uncontrolled and controlled
particulate emissions and fugitive emissions..
Pet..
Exh.
12,13..
Joliet submitted
a revised construction permit application on
September 24,
1980..
Pet. Group
Exh..
11..
In reviewing this
application,
the Agency’s permit analyst, based
on the use of AP—
42,
a calculation method published by USEPA
in 1975, calculated
uncontrolled emissions as 72
tons per
year
(TPY)
allowable
emissions as 113 TPY,
and controlled
(actual) emissions as
7.2
TRY,
and suggested restrictions
in the
facility’s operations.
Pet..
Exh..
9.
A construction permit was issued on October
24,
1980,
which
contained conditions restricting
operations to 3600 hours per
year,
controlling process weight rate
to 400 tons per hour, and
requiring
a
10
moisture content
in raw materials “to keep all
emissions small”,
Pet.
Exh..
8.
Joliet again applied for
an operating permit on November
6,
1980..
Pet.
Exh.
6—7..
The Agency’s permit analyst calculated
uncontrolled emissions as
72 TPY, allowed emissions as
112 TPY,
and controlled emissions as
7.2 TRY..
Pet..
Exh.
5..
The Agency
operating permit was issued on December
30,
1980, subject
to the
same conditions as
in the construction permit..
The expiration
date
of the permit was December
21,
1985.
Pet..
Exh.
4..
Five days before expiration of this operating permit, Joliet
filed
a
two page application
for
renewal of
its prior permit
which certified that the operation had not been modified and that
it was
in compliance with all
regulations.
Pet.
Exh.
3..
Telford’s “Calculation Sheet” analyzing the application noted
that
5 warning letters had been issued
since 1982 concerning
alleged excessive particulate emissions and opacity readings
caused
by operation
of the “Spokane”
and “Steadman”
crushers.
75-235
—9—
Telford recommended denial “because of excess emissions from the
Steadman Crusher on 5—14—85”..
Pet.
Exh..
15.
(It
is nowhere
in
this record explained when,
or under what authority,
these
crushers manufactured by Spokane and Steadman replaced or were
added
to
the permitted crushers manufactured
by Pioneer..)
On March
7, 1986,
the Agency denied
the renewal permit.
Pet.
Exh..
16..
The denial letter
specified the following reasons for
denial:
1)
particulate emissions
in excess of the 30
opacity
limitation of 35
Ill..
Adm.. Code 212.123 based
on field
inspections;
2—3) particulate emissions
in excess of those
allowed by 35
Ill..
Adm.. Code 212.321 for both the Steadman and
Spokane Crushers, based
on calculated emissions levels since
actual emissions data had not been provided;
4) violations of
fugitive particulate limitations of
35
Ill.
Adm.
Code 212.301,
based
on field observations;
arid
5)
failure to provide
information of compliance with Special Condition
3 of the
operating permit, requiring 10
moisture
in raw materials..
The
letter noted that the Agency would
be pleased
to reevaluate the
application on receipt of written request and additional
documentation.
At hearing, Telford
testified that the calculations
referenced
in reasons
2
and
3 had been made on the basis of the
1975 AP—42;
this document had been superseded by
a revised AP—42
issued by USEPA
in September,
1985..
Pet,
Exh.
19,20..
In response
to this denial, on June
16,
1987,
Joliet’s
engineer Rathsack submitted
a letter
requesting issuance of
a
renewal permit.
The
letter proposed replacement of the Steadman
and Spokane crushers which together have
a rated capacity of 575
tons per
hour
(TPH)
with
a new Spokane crusher with
a rated
capacity
of 600 TPH.
Emissions for the new crusher were
calculated
by Rathsack pursuant
to the 1985 AP—42 emission
factor
to be within the allowable rate..
Deletion of the 10
moisture
condition was also requested, on the basis that the raw materials
were classified by AP—42
as “wet material” by virtue of their
2
moisture content, and
that supplemental spraying would
be used.
It was further explained that
a new well had been drilled to
supply water
to
the spray bars on the process line
to control
excess opacity and particulate emissions,
and that a water
truck
had been purchased
to spray site roads to control those fugitive
emissions..
Telford’s calculation
sheets
(Pet.
Exh..
22)
express concerns
prompting him
to recommend denial, which concerns were
incorporated
in
the August
26 denial
letter..
Pet..
Exh..
22..
The
permit was denied because of potential violations of 35
Ill..
Adm.
Code 201.142,
201.157,
212,321,
203..201 and 203.770.
The letter
additionally stated that
in general,
the application failed
to
contain
the minimum information required by Board
rules
to allow
the Agency
to determine compliance with the Act and regulations,
75-236
—10—
and more specifically that
1)
the informational requirements
of
Section 230..770 regarding compliance of the new crusher and any
new conveyors with respective
10
and 15
opacity limits were not
met,
2)
calculations of particulate emissions
for the primary
and secondary crushers indicated that particulate emissions
limitations would
be exceeded, based on
a calculated 50
effectiveness rate for
use of water
in the spray bars
rather
than
a surfactant, and
3)
that construction of the new crusher would
involve
a
major
modification
of
a
major
particulate
emission
source
located
in
a non—attainment area,
requiring a submission
of various information required
by 35
Ill.
Adm. Code Part
200..
REASONS FOR DENIAL
At
the
outset,
the
Board
must
comment
that
dealing
with
this
record poses some difficulty because of the lack of clarity
concerning
the precise identity of the crushers
involved..
It
is
clear
only that on June
16
Joliet
proposed
to
operate
a primary
and secondary crusher of some manufacture on the site
(Pet,
Exh..
21 L), and
that
a Steadman and Spokane crusher were
in operation
on that date
(Pet..
Exh..
2lA).
It appears that one or both of the
originally permitted Pioneer crushers have been replaced
(R..
605—
606),
Section 201.157:
Contents of Application
35
Ill.
Adm. Code
20l..l57 specifies that, as
a minimum,
the
operating permit
shall contain the data specified
in
Section
20l..l52
“Contents of Application
For Construction Permit”,
That
section requires,
among other things,
information concerning the
“nature
of the emission source”, and
“type, size,
efficiency,
and
specifications..,of the proposed emission
source”..
The Agency
correctly determined
that an application for
an
operating permit
is deficient where the
identity of the equipment proposed
to be
operated
is nowhere specified
in
the application..
This reason
for denial
is affirmed..
Section 201.142:
Required Construction Permit
Section 201.142, which
is cited
in
the first
sentence of the
denial
letter,
provides that “no person shall...,cause or allow
the modification of any existing emission
source... .without first
obtaining
a construction permit..”
The evidence is uncontroverted
that no construction permit relating
to the new 600 TPH Steadman
crusher was ever applied
for, let alone
issued.
This reason
for
denial
is
affirmed..
Section 203.770:
Opacity Standards
35
Ill.
Adm..
Code
203..770 incorporates 40 CFR Part 60 which
is entitled Standards of Performance For New Statutory Sources,
Nonmetallic Mineral Processing Plants.
Final Rule 40 CFR 60
75-237
—11—
promulgates
standards
of
performance
for
new
emission
sources..
Because
such
facilities
contribute
significantly
to
air
pollution,
the
intended
effect
of
these
standards
is
to
require
all new, modified and reconstructed mineral processing plants
to
achieve
emission
levels
that
reflect
the
best demonstrated
systems of emission reductions,
40
CFR
Part
60,
Summary,
Vol.
50
No. 148, Thursday, August
1,
1985,
Section 60.676
CI
limits
fugitive
emissions
from
crushers
to
a maximum of 15 opacity and 60.676
BI
limits these emissions
from all other
sources
to
a maximum of 10
capacity..
No data was presented
in the application regarding the
Joliet operations’
ability,
using
the proposed new crusher
and
new conveyors,
to comply with these limitations,
Joliet has not
argued
that these limitations do not apply to its facility.
For
these reasons, this reason
for denial
is affirmed.
In so
holding,
the Board
has given
no weight
to the facility’s alleged
opacity violations relating
to operation of ~
crushers,
as this
is
1rrc~l~
(See also Wast.~.
...
_____
~
supra,
and Fr~tz
Enterprises,
Inc..
v..
IEPA,
PCB 86—76,
September
11,
1986
concerning alleged violations and the Agency’s permit
determinations.)
Section 203.201:
Major Modification of
a Major Emission Source
35
Ill, Adm. Code
203.201 provides
in pertinent part that:
“No person
shall cause or allow the construction of
a new majo~stationary source or major modification
in
an
area designated
as
nonattainment’ as
defined
at
Section
171(2)
of
the
Clean
Air
Act
42
USC
7501.21...except
as
in
compliance
with
this
part
for
that pollutant.”
It
is undisputed
that Troy Township, Will County,
Illinois,
where Joliet’s facility
is located
is designated as
a non—
attainment area for particulate emissions,
that is,
the national
ambient air quality standard
for this pollutant has not been met,
The dispute
is whether Joliet is a major source seeking
to make
a
major modification..
Such sources located
in non—attainment areas
are subject
to more stringent permitting and emission control
requirements known as the “New Source Review”
rules, than are
such sources located
in attainment areas,
since
the clean
air
goals
for the
area have not been achieved.
For purposes of this discussion,
a major source
is one which
has
a “potential
to emit” 100 tons per year,
or more,
of any
pollutant..
35 Ill.
Adin.
Code
203..206..
“Potential
to emit”
is
defined as a source’s maximum capacity
to emit pollutants under
its physical
and operational design;
in determining this design
75-238
—12--
capability
a source may take into account any enforceable limits
(such as those contained in permit conditions)
on hours of
operation, amount of materials processed
or required air
pollution control equipment.
35
Ill,
Adm.
Code 203.128.
This record does not contain calculations specifically
labelled as “potential
to emit”,
although it does contain
calculations of “allowable emissions”.
Section 203.107 defines
“allowable emissions”
in essence as the maximum emissions capable
of being produced by
a source taking into account operations
limitations
imposed by permit conditions.
The uncontroverted
evidence
in this record
is that Joliet’s allowable emissions rate
would be used
in determining
the applicability of Part 203.
P.
630.
The Agency’s calculation sheets for the original permits
show an allowable emissions rate of 112
TPY..
Pet,
Exh..
5,9..
At
hearing,
Joliet’s
engineer
Rathsack calculated
the maximum
a~~abl~
~
oliet’s
primary crusher
as
112
TRY..
Telford
did
not rely upon these figures at the
time of
permit denial, but instead upon
a maximum allowable emissions
limit
of 156 TPY,
a
figure which he obtained by consulting
the
Agency’s Total Air System
(TAS)
computer
system..
No witness
presented
at hearing was able
to testify as to
the derivation of
that number..
For this reason, Joliet asserts that this reason
for denial should
be reversed..
While Telford
relied
on an unverified allowable emissions
rate over 100 TPY, Joliet has presented
no evidence
that
contravenes other
evidence
in this record that its allowable
emissions rate is over 100
TPY..
Joliet’s references
to its
projected controlled
(actual) emissions rate are irrelevant to
its potential
to emit.
The Board
finds that the Agency was
correct in determining
that Joliet
is
a major source.
The next issue
is whether Joliet had proposed
a major
modification..
For particulate emissions,
a major modification
is
one which would result
in
an increase
in actual emissions of
25
TPY.
35
Ill. Adm. Code 203,207,
203..208,
203.209.
As Joliet had
not supplied actual emissions data, calculations were made using
the
1985
AP—42 emissions
factor..
Pet.
Exh..
22.
AP—42, Table 8,19.2—1,
sets
forth
an emission factor of 0.28
pounds per
ton
for primary or secondary crushing
of dry material,
and 0,018 pounds
per ton
for wet material.
A factor
of 1.85 is
assigned
to tertiary crushing of dry material.
Wet material
is
that which contains either naturally,
or after moistening, “1,5
to
4 weight
“..
Footnote b notes that typical
control
efficiencies
for wet spray systems are 70—90.
75-239
—13—
In his June 16 letter, Rathsack stated
that the moisture
content of Joliet’s
rock is
2.0..
Consequently,
he used the
0.018
figure
to
calculate
the
actual
emissions
from
the
proposed
new shredder
to be 10,8 lb/hr.
In analyzing the permit request on his calculation sheet,
Telford
had
noted
Joliet’s
maximum
emissions
as
156
TRY
and
average emissions as
88 TRY,
based
on the data
in
the TAS
computer.
In calculating emissions,
Telford first
used the 0.28
dry material
factor and
the tertiary factor of 1.85;
at hearing.
Telford
explained
that
he
had
used
the
dry
material
factor
for
the primary crusher because “there was
no
spray
bar
in
the
crusher,
because
there
is
no
guarantee
that
the
moisture
will
be
sufficient
to
adequately
suppress
dust
that
will
arise
in
the
crushing
operation
(R..772)..
He
arrived at a
total of 263.14 TRY
of uncontrolled emissions, as compared
to allowable emissions of
77.33 TRY.
Telford then calculated uncontrolled
(actual)
emissions using
the
same 0,28 factor but giving credit
for spray
bars using
surfactant spray (which were not proposed)
and arrived
at
a 65,67 TRY increase.
Telford did
not give credit for use
of
water sprays as he felt that these are less than 50
effective..
At hearing, Telford
testified
that even
if
a wet emission
factor
had been used
that Joliet’s proposed modification would
still be
a
major
one,
although
he
did
not
provide
his
calculations
(P.775),
Finally, Telford also made calculations using
the “old
Permit Manual Method”.
Joliet asserts that the permit manual method of calculation
is improper,
as that manual
is
an unpublished, in—house
document.
The
Board will not address
this contention,
as the
Agency has relied upon only the AP—42 calculations
in defending
the denial.
Joliet further
asserts that use of the dry factor was clear
error since Joliet’s material
is
“wet”, having
a natural moisture
content of
2..
It argues, that AP—42 gives
the permit analyst
no
discretion
to use the significantly higher “dry”
factor..
Joliet
calculates
that, based
on 4992 hours of production, that its
maximum controlled emissions would be 13.47 TRY Pet.
Exh..
25,
Based
on
the production limits
in its current permit,
of 2,440
hours,
it calculates that its maximum emissions would be 18.14
TRY,
Ret,
Exh.
26.
It
compares
these
figures
with
calculations
using the new AP—42 factors as applied
to the equipment permitted
in
1980, which would
result in maximum emissions of 14.26 TRY.
Pet.
Exh..
27.
Thus,
Joliet asserts
it
is not
a source which even
after
the proposed modification can be calculated
to emit
25 TRY,
let alone one which is seeking
to make
a modification resulting
in
a net emission increase of
25 TRY.
In its application, Joliet provided the natural 2
moisture
content of its raw materials,
information allowing for
calculation of its emissions,
and some calculations
using
the
75-240
—14—
1985
AR—42
“wet”
factor.
Joliet
carried
its
preliminary
burden
of proving that its controlled (actual) emissions did not result
in
a 25 TRY net increase, and
that it was therefore not proposing
a
major
modification.
The Board cannot find
that the Agency has made a valid
use
of the AP—42 “dry rock” calculation factor.
There is
no
information
in
this record which substantiates a finding that the
Agency was correct in determining that Joliet’s proposed
modification was “major”
in the meaning
of the new source review
rules,
and the Agency’s determination is hereby reversed.
Section 212.321:
Rarticulate Emissions Limitations
The Agency’s calculations of the allowable particulate
emissions
for both the primary and secondary crushers were made
on the basis
of the invalid use
of AP—42
discussed above.
This
reason
for denial was accordingly also improper.
Joliet’s Additional Arguments and Closing Offer
of Proof
The Board wishes
to make explicit
that in reaching
its
determination, the Board
has considered the offer of proof made
by Joliet at
the time that the Hearing Officer required Joliet
to
close
its
case..
P..
611—614..
Joliet
has
made
no
offer
of
proof
regarding
the
denial
reasons which the Board has sustained, which
are
failure
to
obtain
a
construction
permit,
failure
to
specify
exactly what equipment
it was seeking
to operate, and
failure
to
provide
data
concerning
opacity
of
fugitive
emissions
from
the
proposed new equipment.
The evidence Joliet placed
in
the record
was sufficient
to persuade the Board that calculations derived
from
a
misapplication
of
AP—42
were
invalid.
One
issue
not heretofore specifically addressed
is the
incompleteness of the record
as filed by the Agency in October,
1986..
It
is
true
that
the
record
was
incomplete
as
indicated
by
exhibits submitted by petitioner
and
entered into the record.
One
purpose
of
the
hearing before
the Board
is
to allow
for
completion of the Agency record, as has been done here.
The
filing
of
an
incomplete record by the Agency provides
no grounds
in and of
itself for reversal
of the Agency’s permitting
decisions,
particularly
where,
as
here,
the
omissions
are
not
major
and
there
is
no
indicia
of
any
bad
faith
“cover—up”..
Moreover,
the
Agency’s
filing
omission
most
certainly
pales
in
comparison to Joliet’s failure
to file timely
arid
complete
applications
for construction and operating permits.
SUMMARY
In summary, the
Board finds that the Agency correctly denied
the permit on the basis
of Joliet’s
failure
to provide sufficient
information
to demonstrate
that its facility would
not cause
75-241
—15--
violations
of
Sections
201.142,
201.157,
and
203.770.
The
Agency
incorrectly denied
the permit on the basis of Sections 212.321
and
203..20l.
However,
as
there
were
three
valid
reasons
for
denial of this renewed operating permit, the Agency’s denial
is
affirmed..
FINAL
REMARK
The
Board
must
make
one
final
remark
concerning
the
manner
in
which
this
appeal
has
been
pursued.
The
Section
40
decision
deadline
was
enacted
to
shield
the
regulated
community
from
bureaucratic
delay
in
decisionmaking;
in
this
case
it
has
been
used
by
petitioner
as a sword against the
Agency
and
the
Board.
Any
time
problems
experienced
by
petitioner
at
the
close
of
this
case
have
been
of
its
own
making
as
a result of pursuit of objectives largely unrelated
to the
issues which have been here addressed.
It appears
to
the Board that discovery
in this permit appeal
action has been sought
for
use
in
the pending PCB 86—108
enforcement
action..
In any event,
it
is clear
that petitioner
has
attempted
to
put
the
Agency
“on
trial”
in
this
action,
rather
than
shouldering
its
burden
to
prove
that
the
permit
information
it
had
supplied
to
the
Agency
was
sufficient
to
show
compliance
with
the
Act
and
Board
regulations.
As
a
result,
petitioner’s
discovery
demands
and
repeated requests for immediate Board
rulings thereon have placed excessive burdens on the scarce
personnel
and
fiscal
resources
of
the
Agency,
the
Attorney
General,
and
tlie Board,
and particularly when viewed
in light of
the
irrelevant arguments which much of the information has been
used
to support.
The Board cautions against employment of such
procedures
in any future permit appeal proceeding.
This Opinion constitutes the Board’s findings of
facts and
conclusions of law in
this matter..
ORDER
The Agency’s August 26,
1986 denial
of
the
June
16,
1986
application by Joliet Sand and Gravel
Co.
for
renewal
of
its
operating
permit
is
hereby
affirmed.
IT
IS
SO
ORDERED.
J..
T.
Meyer
dissented..
75-242
—16—
I,
Dorothy
M.
Gum,
Clerk
of
the
Illinois
Pollution
Control
Board,
hereby certify that the above Op~nionand Order was
adopted on
the
5~Z
day
of
___________________________,
1987
by a vote of
_____________________.
/7
~
Dorothy
M.
dunn,
Clerk
Illinois Pollution Control Board
75-243