ILLINOIS POLLUTION CONTROL BOARD
    February
    5, 1987
    JOLIET SAND AND GRAVEL COMPANY,
    Petitioner,
    v..
    )
    PCB 86—159
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    Respondent..
    JOHN
    L..
    PARKER
    (JOHN
    L..
    PARKER &
    ASSOC..) APPEARED ON BEHALF OF
    PETITIONER, AND
    MICHAEL 3. MAHER,
    ASSISTANT ATTORNEY GENERAL, AND JOSEPH
    R..
    PODLEWSKI APPEARED ON BEHALF OF RESPONDENT..
    OPINION AND ORDER OF THE BOARD
    (by 3.
    Anderson):
    This matter
    comes before
    the Board on the September 30,
    1986
    petition
    filed by Joliet Sand and Gravel
    Co..
    (Joliet)
    seeking
    review of
    the denial by the Illinois Environmental Protection
    Agency (Agency)
    of
    a renewal
    of the facility’s operating
    permit..
    Joliet’s sand
    and gravel processing plant
    is located at
    2509 Mound Road
    in Joliet,
    Illinois,
    and engages
    in primary and
    secondary limestone crushing and related
    activities..
    Although hearing was authorized
    by the Board’s Order
    of
    October
    9, 1986,
    evidentiary hearings did not take place
    until
    January 13—14,
    1987.
    Hearings which
    had previously been set for
    November
    19
    and 25 and December 10, 1986 were convened but
    progressed as on—record, pre—hearing conferences at which
    discovery—related matters were discussed..
    The discovery process
    in this matter was unusually lengthy and contested,
    resulting
    in
    truncation of
    the time available
    in which
    to put on evidence at
    hearing
    for review by the
    Board..
    These matters are chronicled
    in
    the Board’s Orders
    in response
    to various “emergency”
    and routine
    motions, and will not again
    be set forth
    in detail
    here.
    The
    Board
    incorporates by reference the following:
    Orders of
    November
    6
    and
    20,
    1986; Orders of December
    18 and 23,
    1986;
    and
    Orders of January 12,
    22 and
    26,
    1987..
    Pursuant
    to leave granted
    by Order
    of January 26,
    1987,
    the parties simultaneously filed
    briefs on February
    2,
    1987..
    Finally,
    the
    Board notes that decision was originally due
    on
    January
    28, 1987 pursuant
    to the 120 day decision deadline
    established
    in Section 40(a)(l)
    of the Environmental Protection
    Act
    (Act)..
    Joliet waived this deadline
    until February 5
    at the
    75-228

    —2—
    commencement of the January 14 hearing, confirmed this waiver
    in
    writing on January 22,
    and then later on the same day extended
    the waiver
    through February
    12..
    On January 26, Joliet further
    extended the decision deadline through March
    5,
    in the context of
    a request
    for
    additional
    hearings..
    As the hearing request was
    denied
    for the reasons set forth in the Board’s January 26 Order,
    decision
    is being rendered consistent with the waiver
    through
    February 12
    to avoid
    issuance of a permit by operation of
    law..
    PRELIMINARY MATTERS
    Pending Written Motions
    The earliest filed motion still pending
    is the Agency’s
    December
    30, 1986 motion
    for
    costs and
    a January 7,
    1987
    supplement
    thereto..
    Joliet
    filed
    responses in opposition
    on
    January
    5 and
    12..
    The motion seeks award of
    $l54..77
    to the
    Agency,
    these being
    the costs
    and
    salaries
    of three employees who
    appeared
    for
    hearing on November 25 pursuant
    to notice served
    November
    24..
    At
    the pre—hearing
    conference held November
    19,
    the
    Hearing Officer had stated that it was necessary to at least open
    the hearing scheduled
    for November
    25
    in order
    to comply with
    notice
    of hearing requirements..
    The Hearing Officer additionally
    noted, however, that
    in
    the event discovery was incomplete,
    that
    if either party or both parties were unable
    to proceed that the
    hearing would
    be
    continued..
    R..
    11—19—86,
    p..
    36,
    38_39*..
    At the
    November
    25 hearing, counsel
    for Joliet stated that he was not
    in
    a position
    to state that “we have enough discovery to permit
    us
    to properly present our case
    at this hearing....,
    and therefore
    I
    ask that this hearing
    be
    continued”..
    R..
    p..
    63—64..
    This request
    was granted and none of the three witnesses were called..
    It is
    the Agency’s position that Joliet knew that it would
    not need
    to
    “put on”
    its case on November
    25,
    and that it had “needlessly
    caused
    the wasted
    and
    futile appearance
    of three Agency personnel
    who had rescheduled
    their workload
    to attend the scheduled
    hearing”..
    Motion,
    14..
    While
    the
    Board believes that the imposition of the costs
    requested would
    be appropriate,
    the Board
    finds
    it impossible
    to
    do
    so..
    The Act specifically provides
    for the shifting
    of costs
    from one party to another
    in two
    instances..
    The first is
    pursuant
    to Section 42(f), authorizing payment of costs incurred
    by the Attorney General
    or State’s Attorney by
    a person found
    to
    have committed “a willful, knowing,
    or repeated violation of the
    *
    The
    transcript of
    the November
    19 hearing
    is numbered pages
    1
    through
    79..
    The transcript of the November 25 hearing begins
    again
    at page
    1;
    the transcripts of the December
    8 and January
    13—14 continue pagination
    in sequence after
    the November 25
    tranScript..
    Reference
    to the November
    19 hearing
    transcript
    is
    to
    “R..
    11—19—86,
    p..
    ____“
    and
    to
    all others
    “P..
    ____
    75-229

    —3—
    Act..”
    The second
    is pursuant
    to Section 31.1,
    authorizing
    payment of costs
    incurred by a person who has unsuccessfully
    appealed
    the issuance of an administrative citation..
    These
    specific grants of authority
    to shift costs militate against
    a
    finding
    that the Board
    has some general,
    inherent authority to
    shift
    these costs
    in cases which are not enforcement actions..
    The Agency’s motion
    is therefore denied
    on the basis that
    it
    seeks relief beyond the Board’s authority
    to grant..
    However, as
    this authority issue has not been fully briefed, the Board will
    entertain further argument
    in the context of
    a motion for
    reconsideration..
    The next filed motion
    is the Agency’s January 12,
    1987
    motion for dismissal with prejudice,
    to which Joliet filed
    a
    response
    on January
    20..
    The motion asserts that Joliet has
    failed
    to comply with Hearing Officer Orders
    to provide both
    answers
    to interrogatories and production of documents, that this
    conduct was
    intentional
    and wrongful, and that as
    a result
    Respondent’s case has been
    so prejudiced that the only
    appropriate remedy
    is dismissal of the action with prejudice..
    In relation
    to this motion,
    the Agency on January
    27
    applied
    to the Hearing Officer
    for
    an Order finding non—compliance with
    an Order
    to answer
    interrogatories..
    Joliet filed
    a response
    in
    opposition on January
    28..
    The Hearing Officer referred the
    matter
    to
    the Board
    on February
    4..
    The Board
    finds that Joliet
    made
    a literal response
    to the interrogatory as drafted..
    While
    Joliet could have been more forthcoming,
    the Board cannot find
    that it did not comply with the Order..
    In additional
    response
    to the motion
    to dismiss,
    the Board
    notes
    the described sequence of events may well have impeded the
    Agency’s preparation and presentation of its
    case..
    Yet, based
    on
    the Board’s review of
    thc~
    hear~nr~
    -i--
    of
    specific al!~
    w~.,.Cfl
    tne
    Agency’s case was prejudiced,
    the Board does not
    find that the
    extreme relief requested is warranted..
    The motion to dismiss
    is
    denied..
    The next filed motion
    is Joliet’s February 2,
    1987 motion
    to
    correct typographical errors
    in the January 13—14,
    1987 hearing
    transcripts..
    A similar motion
    to correct errors
    in the November
    25 and December
    8 transcripts was filed on February
    4..
    The Board
    agrees with Joliet’s characterization of these errors, and grants
    the motion
    to correct..
    The Clerk
    is directed
    to delete the words
    “proposed”
    from
    the errata sheets
    included
    in
    the motions,
    and
    to
    bind copies thereof
    in the originals of the hearing
    transcripts..
    The Board notes that its review of these changes
    was greatly facilitated by Joliet’s submittal of copies of the
    transcript pages with corrections
    inserted by hand..
    75-230

    —4—
    Finally, on February
    4,
    1987,
    Joliet filed
    a reply brief
    accompanied by
    a motion for leave
    to file instanter..
    The Agency
    filed
    a reply in opposition which asserts that
    a reply brief
    is
    procedurally improper under
    these circumstances, particularly
    since Joliet had
    filed
    no main brief,
    and requests that decision
    be made on the basis of the Record
    and its brief..
    It
    is clear
    that,
    for whatever reason,
    the Agency has not received Joliet’s
    brief
    filed with
    the
    Board February
    2.
    This disturbs some of the
    factual premises of the Agency’s opposition..
    Notwithstanding,
    the Agency
    is correct that the simultaneous briefing schedule
    established
    by the Board does not provide for
    reply briefs..
    To
    accept
    a reply brief
    filed on the day before decision under
    circumstances where
    the Agency could not be given
    a reply
    opportunity because
    it had not received Joliet’s brief would
    be
    unfair..
    It
    is additionally onerous
    to the Board to receive
    additional briefs
    on the day before
    a scheduled decision..
    The
    motion
    is denied..
    Evidentiary Issues and
    Scope of Review
    The
    remaining preliminary matters worthy of the Board’s
    attention at this point are various assertions of error
    in regard
    to
    the Hearing Officer’s conduct of the hearing..
    While some of
    these were reiterated
    in the final briefs, most are reflected
    only
    in
    the hearing
    transcript.
    The Board will not address all
    objections
    in detail, affirming all rulings not otherwise
    addressed..
    The Board again
    affirms the procedures established
    by the
    Hearing Officer
    for presentation of
    testimony and evidence at
    the
    two—day hearing..
    The Board
    has repeatedly and exhaustively
    rejected Joliet’s assertions that its due process
    rights have
    been violated, and will not here repeat
    the rationale stated
    in
    those Orders which have been incorporated herein by reference.
    Before address~rg
    the
    various evidentiarv issues, the Board
    will briefly reiterate the scope of review of permit appeals
    ~ex~:r~.lv,
    and more specifically as they relate
    to
    the
    sequence
    of events involved
    in the
    instant permit denial..
    The Board’s historic approach to permit denial hearings was
    best stated
    in Oscar Mayer
    and
    Co..
    v.
    IEPA, PCB 78—14,
    30 PCB
    397,
    398
    (1978):
    “Under
    the
    statute,
    all
    the Board
    has authority to
    do
    in
    a
    hearing
    and determination
    on
    a
    Section
    40
    petition
    is
    to decide after
    a hearing
    in
    accordance
    with
    Sections
    32
    and
    33(a)
    whether
    or
    not,
    based
    upon
    the
    facts
    of
    the
    application,
    the
    applicant
    has
    provided
    proof
    that
    the
    activity
    in
    question
    will
    not
    cause
    a
    violation
    of
    the
    Act
    or
    of
    the
    regulations..
    75-231

    —5—
    In
    a
    hearing
    on
    a
    Section
    40
    petition,
    the
    applicant must verify
    the
    facts of his application
    as
    submitted
    to
    the
    Agency,
    and,
    having
    done
    so,
    must
    persuade
    the
    Board
    that
    the
    activity
    will
    comply
    with
    the
    Act
    and
    regulations..
    At
    hearing,
    the
    Agency
    may
    attempt
    to
    controvert
    the
    applicant’s
    facts
    by
    cross—examination
    or
    direct
    testimony;
    may
    submit
    argument
    on
    the
    applicable
    law
    and
    regulations
    and
    may
    urge
    conclusions
    therefrom;
    or,
    it may
    choose
    to
    do either;
    or,
    it
    may choose
    to present
    nothing.
    The written
    Agency
    statement
    to
    the
    applicant
    of
    the
    specific,
    detailed
    reasons
    that
    the
    permit
    application
    was
    denied
    is not evidence of the truth of
    the material
    therein
    nor
    do
    any Agency
    interpretations
    of
    the
    Act
    and
    regulations
    therein
    enjoy
    any presumption
    before
    the
    Board..”
    The Illinois Supreme Court,
    and various appellate courts
    have confirmed the validity of this approach,
    e..g.. Waste
    Management,
    Inc..
    v.
    IEPA, PCB 84—45,61,68, Opinion and Order
    of
    October
    1,
    1984 and
    Supp..
    Opinion and Order of November 26, 1984,
    aff’d sub nom.
    IEPA
    v..
    IPCB,
    138 Ill.
    App. 3d 550
    (3rd Dist.
    1985), aff’d
    _____
    Ill.2d
    ___,
    No..
    63062
    (December
    19,
    1986)
    (Board need
    not apply manifest weight of the evidence standard
    in
    reviewing Agency permitting
    decisions)..
    In its permit denial
    letter, the Agency must specify all
    reasons
    for
    its denial
    of
    a
    permit,
    and
    is precluded from raising new reasons
    for the first
    time before the
    Board..
    IEPA v.
    IPCB,
    86
    Ill..2d 390,
    404—405,
    427
    N,E..2D 162
    (1981)..
    The Board must consider the application as
    submitted
    to
    the Agency, and may not be persuaded by new material
    not before the Agency that the permit should be granted.. IEPA v.
    IPCB and Album,
    Inc.,
    118
    Ill..
    App..3d 772, 455 N..E.2d 194
    (1983).
    To
    the extent that the Agency has relied upon
    information beyond
    that contained
    in the application, such
    information must be
    included
    in the permit record
    filed with the
    Board;
    if
    it
    is not,
    the applicant may properly submit such
    information
    to the Board during the course of the Board’s
    hearing..
    Additionally,
    if there was information
    in the Agency’s
    possession upon which
    it reasonably should have relied, the
    applicant may also submit such information to
    the Board
    for the
    Board’s consideration. Waste Management, supra,
    Frinks Industrial
    Waste,
    Inc..
    v..
    IEPA, PCB 83—10, June 30, 1983;
    Sherex Chemical
    Co..
    Inc.
    v..
    IEPA, PCB 80—66,
    39 PCB 527—528
    (1980),
    aff’d sub
    nom..
    IEPA
    v..
    Sherex Chemical
    Co. and
    IPCB,
    100
    Ill..
    App..3d 735
    (1981)..
    While
    the permitting
    chronology for
    the Joliet site will
    be
    discussed
    later
    in more detail,
    for the nonce the salient facts
    are as
    follows..
    Joliet’s initial operating permit was issued
    on
    December 30,
    1980,
    to expire on December
    21, 1985,
    Joliet
    applied for renewal
    of this permit on December
    16,
    1985..
    The
    75-232

    —6—
    Agency denied
    the
    renewal on March 7,
    1986.
    Joliet submitted
    additional information on June
    16, 1986 and again requested
    renewal
    of the permit.
    This renewal application was denied on
    August 26,
    1986..
    The Agency asserts that the correctness of the Agency’s
    first permit denial
    on March
    7,
    1986 is not at issue
    here..
    The
    Agency argues that by failing
    to appeal that denial within 35
    days as required by Section 40,
    Joliet
    has waived any right
    to
    contest error
    (P.
    332—335, Agency Brief
    at 7—8).
    The Board
    agrees,
    and does not find persuasive Joliet’s arguments that the
    first denial was not ripe
    for review until
    after
    the second
    denial
    (P.
    333—334)..
    The
    Board agrees with Joliet that
    there
    is
    a
    “continuum”
    between the information considered by the Agency on March
    7 and
    August
    26: Joliet’s June
    16
    letter
    in response
    to the March
    7
    denial
    (Pet.
    Exh..
    21,
    R..
    Exh.
    3)
    clearly indicates that
    it was
    intended to
    be supplemental
    to
    the December
    16,
    1985 application
    for renewal
    (Pet..
    Exh..
    3).
    The Hearing Officer was correct
    in
    admitting evidence concerning
    the March
    7 denial
    to the extent
    that such evidence could
    be relevant to correctness of the August
    26 denial..
    The Hearing Officer
    excluded several
    exhibits identified
    and
    offered by Joliet which consist of documents contained
    in the
    Agency’s file relating
    to the original operating and construction
    permits issued
    for the Joliet facility.
    These
    are Petitioner’s
    Exhibits
    5,
    6,
    8,
    9,
    10,
    11,
    12,
    13,
    14, as marked
    for
    identification,
    and submitted
    to the Board by way of offer of
    proof..
    The Hearing Officer’s exclusion
    of these exhibits
    is
    reversed,
    and they are admitted
    as evidence.
    As Joliet argued
    (see
    e..g..
    P.288—291),
    the application
    for renewal
    of an operating
    permit provides for incorporation of data from prior permits and
    requires certification that previously submitted information
    remains true and correct.
    The expiring operating permit
    in turn
    references
    the construction permit, which was issued
    on the basis
    of the application and information submitted
    in
    1980.
    Without
    regard
    to
    the probative value
    to be assigned
    to this data
    concerning
    prior permitting history, Joliet has persuaded the
    Board
    that it cannot be excluded on relevancy grounds..
    The Hearing Officer
    also excluded from evidence, but
    received offers of proof concerning,
    documents marked
    as
    Petitioners Exhibits 25,
    26
    and 27 for
    identification.
    These
    documents consist of calculations estimating
    emissions from
    Joliet’s facility prepared by Andrew Rathsack, Joliet’s
    consulting
    engineer..
    These exhibits were denied admission based
    upon the Agency’s objection that the witness had not previously
    been made available for deposition concerning
    the calculations
    or
    other matters..
    R.
    590—591.
    While the Board appreciates
    this
    75-233

    —7—
    rationale,
    the Board will admit
    the calculations, which are self—
    explanatory.
    PERMIT CHRONOLOGY
    Witnesses
    Seven witnesses were called by the parties.
    They are listed
    below with a brief description of their qualifications and
    relation
    to the permit
    issues..
    Harish
    B..
    Desai, IEPA
    In 1986,
    unit manager
    in the Agency’s air permit section and
    supervisor of Anton Telford,
    who reviewed and initialed the
    permit denial
    letters drafted by Telford and signed by Mathur
    March
    7 and August
    26,
    1986..
    Conducted
    no independent review of
    permit
    record..
    P.
    543—547..
    Bharat Mathur,
    IEPA
    Between 1980—1986,
    Manager of the Agency’s Air Permit
    Section.
    Signer
    of 1986 permit denial letters drafted by
    Telford..
    Conducted
    no independent review of permit
    record..
    Named author
    and
    signer of memo of October
    9, 1986 prepared by
    Telford designating
    items in Agency permit record
    for this
    appeal..
    Pet..
    Exh,
    2.
    Conducted
    no independent review..
    P..
    535—
    542..
    Andrew Rathsack, Andrews Environmental Engineering,
    Inc..
    Involved
    in preparation of Joliet’s permit applications
    since
    1980.
    R.
    585—609..
    Christopher Romaine, IEPA
    Manager
    of
    the New Source Review (NSR) Unit
    in
    the Agency’s
    air permit
    section..
    As
    it related
    to NSR, reviewed
    and initialed
    August
    26 denial letter drafted by Telford..
    Conducted
    no
    independent
    review of accuracy of calculations.
    P.
    619—638..
    Anton Telford,
    IEPA
    Permit Engineer
    in the Agency’s air permit section.
    Analyzed Joliet’s December, 1985
    and June, 1986 permit renewal
    applications and drafted denial letters.
    Generated calculations
    relied on by other Agency personnel.
    Designated documents
    filed
    with the Board
    on October
    24,
    1986
    as Agency Record.
    75-234

    —8--
    Martin Tippin, IEPA
    William Zenisck,
    IEPA
    Each is an environmental protection specialist
    in the
    Agency’s
    air permit section, and
    a certified smoke
    reader.
    Each
    has conducted compliance inspections at the Joliet facility
    within the past three years,
    and has made visual opacity
    readings..
    The Joliet Permits
    Joliet Sand and Gravel
    Co..,
    then owned by Rein, Schultz and
    Dahi
    of Illinois,
    Inc..,
    filed its application
    to construct and
    operate
    a sand and gravel
    processing plant on May
    29,
    1980..
    Pet..
    Group Exh.
    14..
    The equipment referenced
    in the application was
    a
    primary jaw—crusher
    identified
    as Pioneer Model
    3042,
    a secondary
    roll crusher identified as Pioneer Model 2454,
    and
    a Pioneer
    Model
    526
    F
    screen.. Resp.
    Exh.
    l4—L..
    The Agency denied
    the
    permit on July
    28, 1980 due
    to Joliet’s failure
    to submit
    calculations for projected, uncontrolled and controlled
    particulate emissions and fugitive emissions..
    Pet..
    Exh.
    12,13..
    Joliet submitted
    a revised construction permit application on
    September 24,
    1980..
    Pet. Group
    Exh..
    11..
    In reviewing this
    application,
    the Agency’s permit analyst, based
    on the use of AP—
    42,
    a calculation method published by USEPA
    in 1975, calculated
    uncontrolled emissions as 72
    tons per
    year
    (TPY)
    allowable
    emissions as 113 TPY,
    and controlled
    (actual) emissions as
    7.2
    TRY,
    and suggested restrictions
    in the
    facility’s operations.
    Pet..
    Exh..
    9.
    A construction permit was issued on October
    24,
    1980,
    which
    contained conditions restricting
    operations to 3600 hours per
    year,
    controlling process weight rate
    to 400 tons per hour, and
    requiring
    a
    10
    moisture content
    in raw materials “to keep all
    emissions small”,
    Pet.
    Exh..
    8.
    Joliet again applied for
    an operating permit on November
    6,
    1980..
    Pet.
    Exh.
    6—7..
    The Agency’s permit analyst calculated
    uncontrolled emissions as
    72 TPY, allowed emissions as
    112 TPY,
    and controlled emissions as
    7.2 TRY..
    Pet..
    Exh.
    5..
    The Agency
    operating permit was issued on December
    30,
    1980, subject
    to the
    same conditions as
    in the construction permit..
    The expiration
    date
    of the permit was December
    21,
    1985.
    Pet..
    Exh.
    4..
    Five days before expiration of this operating permit, Joliet
    filed
    a
    two page application
    for
    renewal of
    its prior permit
    which certified that the operation had not been modified and that
    it was
    in compliance with all
    regulations.
    Pet.
    Exh.
    3..
    Telford’s “Calculation Sheet” analyzing the application noted
    that
    5 warning letters had been issued
    since 1982 concerning
    alleged excessive particulate emissions and opacity readings
    caused
    by operation
    of the “Spokane”
    and “Steadman”
    crushers.
    75-235

    —9—
    Telford recommended denial “because of excess emissions from the
    Steadman Crusher on 5—14—85”..
    Pet.
    Exh..
    15.
    (It
    is nowhere
    in
    this record explained when,
    or under what authority,
    these
    crushers manufactured by Spokane and Steadman replaced or were
    added
    to
    the permitted crushers manufactured
    by Pioneer..)
    On March
    7, 1986,
    the Agency denied
    the renewal permit.
    Pet.
    Exh..
    16..
    The denial letter
    specified the following reasons for
    denial:
    1)
    particulate emissions
    in excess of the 30
    opacity
    limitation of 35
    Ill..
    Adm.. Code 212.123 based
    on field
    inspections;
    2—3) particulate emissions
    in excess of those
    allowed by 35
    Ill..
    Adm.. Code 212.321 for both the Steadman and
    Spokane Crushers, based
    on calculated emissions levels since
    actual emissions data had not been provided;
    4) violations of
    fugitive particulate limitations of
    35
    Ill.
    Adm.
    Code 212.301,
    based
    on field observations;
    arid
    5)
    failure to provide
    information of compliance with Special Condition
    3 of the
    operating permit, requiring 10
    moisture
    in raw materials..
    The
    letter noted that the Agency would
    be pleased
    to reevaluate the
    application on receipt of written request and additional
    documentation.
    At hearing, Telford
    testified that the calculations
    referenced
    in reasons
    2
    and
    3 had been made on the basis of the
    1975 AP—42;
    this document had been superseded by
    a revised AP—42
    issued by USEPA
    in September,
    1985..
    Pet,
    Exh.
    19,20..
    In response
    to this denial, on June
    16,
    1987,
    Joliet’s
    engineer Rathsack submitted
    a letter
    requesting issuance of
    a
    renewal permit.
    The
    letter proposed replacement of the Steadman
    and Spokane crushers which together have
    a rated capacity of 575
    tons per
    hour
    (TPH)
    with
    a new Spokane crusher with
    a rated
    capacity
    of 600 TPH.
    Emissions for the new crusher were
    calculated
    by Rathsack pursuant
    to the 1985 AP—42 emission
    factor
    to be within the allowable rate..
    Deletion of the 10
    moisture
    condition was also requested, on the basis that the raw materials
    were classified by AP—42
    as “wet material” by virtue of their
    2
    moisture content, and
    that supplemental spraying would
    be used.
    It was further explained that
    a new well had been drilled to
    supply water
    to
    the spray bars on the process line
    to control
    excess opacity and particulate emissions,
    and that a water
    truck
    had been purchased
    to spray site roads to control those fugitive
    emissions..
    Telford’s calculation
    sheets
    (Pet.
    Exh..
    22)
    express concerns
    prompting him
    to recommend denial, which concerns were
    incorporated
    in
    the August
    26 denial
    letter..
    Pet..
    Exh..
    22..
    The
    permit was denied because of potential violations of 35
    Ill..
    Adm.
    Code 201.142,
    201.157,
    212,321,
    203..201 and 203.770.
    The letter
    additionally stated that
    in general,
    the application failed
    to
    contain
    the minimum information required by Board
    rules
    to allow
    the Agency
    to determine compliance with the Act and regulations,
    75-236

    —10—
    and more specifically that
    1)
    the informational requirements
    of
    Section 230..770 regarding compliance of the new crusher and any
    new conveyors with respective
    10
    and 15
    opacity limits were not
    met,
    2)
    calculations of particulate emissions
    for the primary
    and secondary crushers indicated that particulate emissions
    limitations would
    be exceeded, based on
    a calculated 50
    effectiveness rate for
    use of water
    in the spray bars
    rather
    than
    a surfactant, and
    3)
    that construction of the new crusher would
    involve
    a
    major
    modification
    of
    a
    major
    particulate
    emission
    source
    located
    in
    a non—attainment area,
    requiring a submission
    of various information required
    by 35
    Ill.
    Adm. Code Part
    200..
    REASONS FOR DENIAL
    At
    the
    outset,
    the
    Board
    must
    comment
    that
    dealing
    with
    this
    record poses some difficulty because of the lack of clarity
    concerning
    the precise identity of the crushers
    involved..
    It
    is
    clear
    only that on June
    16
    Joliet
    proposed
    to
    operate
    a primary
    and secondary crusher of some manufacture on the site
    (Pet,
    Exh..
    21 L), and
    that
    a Steadman and Spokane crusher were
    in operation
    on that date
    (Pet..
    Exh..
    2lA).
    It appears that one or both of the
    originally permitted Pioneer crushers have been replaced
    (R..
    605—
    606),
    Section 201.157:
    Contents of Application
    35
    Ill.
    Adm. Code
    20l..l57 specifies that, as
    a minimum,
    the
    operating permit
    shall contain the data specified
    in
    Section
    20l..l52
    “Contents of Application
    For Construction Permit”,
    That
    section requires,
    among other things,
    information concerning the
    “nature
    of the emission source”, and
    “type, size,
    efficiency,
    and
    specifications..,of the proposed emission
    source”..
    The Agency
    correctly determined
    that an application for
    an
    operating permit
    is deficient where the
    identity of the equipment proposed
    to be
    operated
    is nowhere specified
    in
    the application..
    This reason
    for denial
    is affirmed..
    Section 201.142:
    Required Construction Permit
    Section 201.142, which
    is cited
    in
    the first
    sentence of the
    denial
    letter,
    provides that “no person shall...,cause or allow
    the modification of any existing emission
    source... .without first
    obtaining
    a construction permit..”
    The evidence is uncontroverted
    that no construction permit relating
    to the new 600 TPH Steadman
    crusher was ever applied
    for, let alone
    issued.
    This reason
    for
    denial
    is
    affirmed..
    Section 203.770:
    Opacity Standards
    35
    Ill.
    Adm..
    Code
    203..770 incorporates 40 CFR Part 60 which
    is entitled Standards of Performance For New Statutory Sources,
    Nonmetallic Mineral Processing Plants.
    Final Rule 40 CFR 60
    75-237

    —11—
    promulgates
    standards
    of
    performance
    for
    new
    emission
    sources..
    Because
    such
    facilities
    contribute
    significantly
    to
    air
    pollution,
    the
    intended
    effect
    of
    these
    standards
    is
    to
    require
    all new, modified and reconstructed mineral processing plants
    to
    achieve
    emission
    levels
    that
    reflect
    the
    best demonstrated
    systems of emission reductions,
    40
    CFR
    Part
    60,
    Summary,
    Vol.
    50
    No. 148, Thursday, August
    1,
    1985,
    Section 60.676
    CI
    limits
    fugitive
    emissions
    from
    crushers
    to
    a maximum of 15 opacity and 60.676
    BI
    limits these emissions
    from all other
    sources
    to
    a maximum of 10
    capacity..
    No data was presented
    in the application regarding the
    Joliet operations’
    ability,
    using
    the proposed new crusher
    and
    new conveyors,
    to comply with these limitations,
    Joliet has not
    argued
    that these limitations do not apply to its facility.
    For
    these reasons, this reason
    for denial
    is affirmed.
    In so
    holding,
    the Board
    has given
    no weight
    to the facility’s alleged
    opacity violations relating
    to operation of ~
    crushers,
    as this
    is
    1rrc~l~
    (See also Wast.~.
    ...
    _____
    ~
    supra,
    and Fr~tz
    Enterprises,
    Inc..
    v..
    IEPA,
    PCB 86—76,
    September
    11,
    1986
    concerning alleged violations and the Agency’s permit
    determinations.)
    Section 203.201:
    Major Modification of
    a Major Emission Source
    35
    Ill, Adm. Code
    203.201 provides
    in pertinent part that:
    “No person
    shall cause or allow the construction of
    a new majo~stationary source or major modification
    in
    an
    area designated
    as
    nonattainment’ as
    defined
    at
    Section
    171(2)
    of
    the
    Clean
    Air
    Act
    42
    USC
    7501.21...except
    as
    in
    compliance
    with
    this
    part
    for
    that pollutant.”
    It
    is undisputed
    that Troy Township, Will County,
    Illinois,
    where Joliet’s facility
    is located
    is designated as
    a non—
    attainment area for particulate emissions,
    that is,
    the national
    ambient air quality standard
    for this pollutant has not been met,
    The dispute
    is whether Joliet is a major source seeking
    to make
    a
    major modification..
    Such sources located
    in non—attainment areas
    are subject
    to more stringent permitting and emission control
    requirements known as the “New Source Review”
    rules, than are
    such sources located
    in attainment areas,
    since
    the clean
    air
    goals
    for the
    area have not been achieved.
    For purposes of this discussion,
    a major source
    is one which
    has
    a “potential
    to emit” 100 tons per year,
    or more,
    of any
    pollutant..
    35 Ill.
    Adin.
    Code
    203..206..
    “Potential
    to emit”
    is
    defined as a source’s maximum capacity
    to emit pollutants under
    its physical
    and operational design;
    in determining this design
    75-238

    —12--
    capability
    a source may take into account any enforceable limits
    (such as those contained in permit conditions)
    on hours of
    operation, amount of materials processed
    or required air
    pollution control equipment.
    35
    Ill,
    Adm.
    Code 203.128.
    This record does not contain calculations specifically
    labelled as “potential
    to emit”,
    although it does contain
    calculations of “allowable emissions”.
    Section 203.107 defines
    “allowable emissions”
    in essence as the maximum emissions capable
    of being produced by
    a source taking into account operations
    limitations
    imposed by permit conditions.
    The uncontroverted
    evidence
    in this record
    is that Joliet’s allowable emissions rate
    would be used
    in determining
    the applicability of Part 203.
    P.
    630.
    The Agency’s calculation sheets for the original permits
    show an allowable emissions rate of 112
    TPY..
    Pet,
    Exh..
    5,9..
    At
    hearing,
    Joliet’s
    engineer
    Rathsack calculated
    the maximum
    a~~abl~
    ~
    oliet’s
    primary crusher
    as
    112
    TRY..
    Telford
    did
    not rely upon these figures at the
    time of
    permit denial, but instead upon
    a maximum allowable emissions
    limit
    of 156 TPY,
    a
    figure which he obtained by consulting
    the
    Agency’s Total Air System
    (TAS)
    computer
    system..
    No witness
    presented
    at hearing was able
    to testify as to
    the derivation of
    that number..
    For this reason, Joliet asserts that this reason
    for denial should
    be reversed..
    While Telford
    relied
    on an unverified allowable emissions
    rate over 100 TPY, Joliet has presented
    no evidence
    that
    contravenes other
    evidence
    in this record that its allowable
    emissions rate is over 100
    TPY..
    Joliet’s references
    to its
    projected controlled
    (actual) emissions rate are irrelevant to
    its potential
    to emit.
    The Board
    finds that the Agency was
    correct in determining
    that Joliet
    is
    a major source.
    The next issue
    is whether Joliet had proposed
    a major
    modification..
    For particulate emissions,
    a major modification
    is
    one which would result
    in
    an increase
    in actual emissions of
    25
    TPY.
    35
    Ill. Adm. Code 203,207,
    203..208,
    203.209.
    As Joliet had
    not supplied actual emissions data, calculations were made using
    the
    1985
    AP—42 emissions
    factor..
    Pet.
    Exh..
    22.
    AP—42, Table 8,19.2—1,
    sets
    forth
    an emission factor of 0.28
    pounds per
    ton
    for primary or secondary crushing
    of dry material,
    and 0,018 pounds
    per ton
    for wet material.
    A factor
    of 1.85 is
    assigned
    to tertiary crushing of dry material.
    Wet material
    is
    that which contains either naturally,
    or after moistening, “1,5
    to
    4 weight
    “..
    Footnote b notes that typical
    control
    efficiencies
    for wet spray systems are 70—90.
    75-239

    —13—
    In his June 16 letter, Rathsack stated
    that the moisture
    content of Joliet’s
    rock is
    2.0..
    Consequently,
    he used the
    0.018
    figure
    to
    calculate
    the
    actual
    emissions
    from
    the
    proposed
    new shredder
    to be 10,8 lb/hr.
    In analyzing the permit request on his calculation sheet,
    Telford
    had
    noted
    Joliet’s
    maximum
    emissions
    as
    156
    TRY
    and
    average emissions as
    88 TRY,
    based
    on the data
    in
    the TAS
    computer.
    In calculating emissions,
    Telford first
    used the 0.28
    dry material
    factor and
    the tertiary factor of 1.85;
    at hearing.
    Telford
    explained
    that
    he
    had
    used
    the
    dry
    material
    factor
    for
    the primary crusher because “there was
    no
    spray
    bar
    in
    the
    crusher,
    because
    there
    is
    no
    guarantee
    that
    the
    moisture
    will
    be
    sufficient
    to
    adequately
    suppress
    dust
    that
    will
    arise
    in
    the
    crushing
    operation
    (R..772)..
    He
    arrived at a
    total of 263.14 TRY
    of uncontrolled emissions, as compared
    to allowable emissions of
    77.33 TRY.
    Telford then calculated uncontrolled
    (actual)
    emissions using
    the
    same 0,28 factor but giving credit
    for spray
    bars using
    surfactant spray (which were not proposed)
    and arrived
    at
    a 65,67 TRY increase.
    Telford did
    not give credit for use
    of
    water sprays as he felt that these are less than 50
    effective..
    At hearing, Telford
    testified
    that even
    if
    a wet emission
    factor
    had been used
    that Joliet’s proposed modification would
    still be
    a
    major
    one,
    although
    he
    did
    not
    provide
    his
    calculations
    (P.775),
    Finally, Telford also made calculations using
    the “old
    Permit Manual Method”.
    Joliet asserts that the permit manual method of calculation
    is improper,
    as that manual
    is
    an unpublished, in—house
    document.
    The
    Board will not address
    this contention,
    as the
    Agency has relied upon only the AP—42 calculations
    in defending
    the denial.
    Joliet further
    asserts that use of the dry factor was clear
    error since Joliet’s material
    is
    “wet”, having
    a natural moisture
    content of
    2..
    It argues, that AP—42 gives
    the permit analyst
    no
    discretion
    to use the significantly higher “dry”
    factor..
    Joliet
    calculates
    that, based
    on 4992 hours of production, that its
    maximum controlled emissions would be 13.47 TRY Pet.
    Exh..
    25,
    Based
    on
    the production limits
    in its current permit,
    of 2,440
    hours,
    it calculates that its maximum emissions would be 18.14
    TRY,
    Ret,
    Exh.
    26.
    It
    compares
    these
    figures
    with
    calculations
    using the new AP—42 factors as applied
    to the equipment permitted
    in
    1980, which would
    result in maximum emissions of 14.26 TRY.
    Pet.
    Exh..
    27.
    Thus,
    Joliet asserts
    it
    is not
    a source which even
    after
    the proposed modification can be calculated
    to emit
    25 TRY,
    let alone one which is seeking
    to make
    a modification resulting
    in
    a net emission increase of
    25 TRY.
    In its application, Joliet provided the natural 2
    moisture
    content of its raw materials,
    information allowing for
    calculation of its emissions,
    and some calculations
    using
    the
    75-240

    —14—
    1985
    AR—42
    “wet”
    factor.
    Joliet
    carried
    its
    preliminary
    burden
    of proving that its controlled (actual) emissions did not result
    in
    a 25 TRY net increase, and
    that it was therefore not proposing
    a
    major
    modification.
    The Board cannot find
    that the Agency has made a valid
    use
    of the AP—42 “dry rock” calculation factor.
    There is
    no
    information
    in
    this record which substantiates a finding that the
    Agency was correct in determining that Joliet’s proposed
    modification was “major”
    in the meaning
    of the new source review
    rules,
    and the Agency’s determination is hereby reversed.
    Section 212.321:
    Rarticulate Emissions Limitations
    The Agency’s calculations of the allowable particulate
    emissions
    for both the primary and secondary crushers were made
    on the basis
    of the invalid use
    of AP—42
    discussed above.
    This
    reason
    for denial was accordingly also improper.
    Joliet’s Additional Arguments and Closing Offer
    of Proof
    The Board wishes
    to make explicit
    that in reaching
    its
    determination, the Board
    has considered the offer of proof made
    by Joliet at
    the time that the Hearing Officer required Joliet
    to
    close
    its
    case..
    P..
    611—614..
    Joliet
    has
    made
    no
    offer
    of
    proof
    regarding
    the
    denial
    reasons which the Board has sustained, which
    are
    failure
    to
    obtain
    a
    construction
    permit,
    failure
    to
    specify
    exactly what equipment
    it was seeking
    to operate, and
    failure
    to
    provide
    data
    concerning
    opacity
    of
    fugitive
    emissions
    from
    the
    proposed new equipment.
    The evidence Joliet placed
    in
    the record
    was sufficient
    to persuade the Board that calculations derived
    from
    a
    misapplication
    of
    AP—42
    were
    invalid.
    One
    issue
    not heretofore specifically addressed
    is the
    incompleteness of the record
    as filed by the Agency in October,
    1986..
    It
    is
    true
    that
    the
    record
    was
    incomplete
    as
    indicated
    by
    exhibits submitted by petitioner
    and
    entered into the record.
    One
    purpose
    of
    the
    hearing before
    the Board
    is
    to allow
    for
    completion of the Agency record, as has been done here.
    The
    filing
    of
    an
    incomplete record by the Agency provides
    no grounds
    in and of
    itself for reversal
    of the Agency’s permitting
    decisions,
    particularly
    where,
    as
    here,
    the
    omissions
    are
    not
    major
    and
    there
    is
    no
    indicia
    of
    any
    bad
    faith
    “cover—up”..
    Moreover,
    the
    Agency’s
    filing
    omission
    most
    certainly
    pales
    in
    comparison to Joliet’s failure
    to file timely
    arid
    complete
    applications
    for construction and operating permits.
    SUMMARY
    In summary, the
    Board finds that the Agency correctly denied
    the permit on the basis
    of Joliet’s
    failure
    to provide sufficient
    information
    to demonstrate
    that its facility would
    not cause
    75-241

    —15--
    violations
    of
    Sections
    201.142,
    201.157,
    and
    203.770.
    The
    Agency
    incorrectly denied
    the permit on the basis of Sections 212.321
    and
    203..20l.
    However,
    as
    there
    were
    three
    valid
    reasons
    for
    denial of this renewed operating permit, the Agency’s denial
    is
    affirmed..
    FINAL
    REMARK
    The
    Board
    must
    make
    one
    final
    remark
    concerning
    the
    manner
    in
    which
    this
    appeal
    has
    been
    pursued.
    The
    Section
    40
    decision
    deadline
    was
    enacted
    to
    shield
    the
    regulated
    community
    from
    bureaucratic
    delay
    in
    decisionmaking;
    in
    this
    case
    it
    has
    been
    used
    by
    petitioner
    as a sword against the
    Agency
    and
    the
    Board.
    Any
    time
    problems
    experienced
    by
    petitioner
    at
    the
    close
    of
    this
    case
    have
    been
    of
    its
    own
    making
    as
    a result of pursuit of objectives largely unrelated
    to the
    issues which have been here addressed.
    It appears
    to
    the Board that discovery
    in this permit appeal
    action has been sought
    for
    use
    in
    the pending PCB 86—108
    enforcement
    action..
    In any event,
    it
    is clear
    that petitioner
    has
    attempted
    to
    put
    the
    Agency
    “on
    trial”
    in
    this
    action,
    rather
    than
    shouldering
    its
    burden
    to
    prove
    that
    the
    permit
    information
    it
    had
    supplied
    to
    the
    Agency
    was
    sufficient
    to
    show
    compliance
    with
    the
    Act
    and
    Board
    regulations.
    As
    a
    result,
    petitioner’s
    discovery
    demands
    and
    repeated requests for immediate Board
    rulings thereon have placed excessive burdens on the scarce
    personnel
    and
    fiscal
    resources
    of
    the
    Agency,
    the
    Attorney
    General,
    and
    tlie Board,
    and particularly when viewed
    in light of
    the
    irrelevant arguments which much of the information has been
    used
    to support.
    The Board cautions against employment of such
    procedures
    in any future permit appeal proceeding.
    This Opinion constitutes the Board’s findings of
    facts and
    conclusions of law in
    this matter..
    ORDER
    The Agency’s August 26,
    1986 denial
    of
    the
    June
    16,
    1986
    application by Joliet Sand and Gravel
    Co.
    for
    renewal
    of
    its
    operating
    permit
    is
    hereby
    affirmed.
    IT
    IS
    SO
    ORDERED.
    J..
    T.
    Meyer
    dissented..
    75-242

    —16—
    I,
    Dorothy
    M.
    Gum,
    Clerk
    of
    the
    Illinois
    Pollution
    Control
    Board,
    hereby certify that the above Op~nionand Order was
    adopted on
    the
    5~Z
    day
    of
    ___________________________,
    1987
    by a vote of
    _____________________.
    /7
    ~
    Dorothy
    M.
    dunn,
    Clerk
    Illinois Pollution Control Board
    75-243

    Back to top