ILLINOTh
    ~OLNUTION
    CONTROL
    BOARD
    Fehr~:av
    28,
    1974
    i~oo~
    be
    tina~
    PCB
    73—482
    ~~7j~’T~T
    PRO’i
    AGENCY,
    Respondea.
    ~r.
    ~b~Idon
    A.
    ZaP~G, Attorney,
    on behalf of Petitioner;
    Mr.
    JoLn
    T. Bernb~, Attorney,
    on behalf of
    Respondent.
    JNL~N
    ~GN,ORDER OF THE BOARD
    (by Mr.
    Seaman):
    ~vember
    14,
    1973,
    Illinois Power Company filed
    a
    ~aI~:a(~
    for Variance which this Board found to be
    so
    lackPn~
    in
    substance
    and detail that Petitioner was
    ordered
    tD
    f~e an amended petition.
    Petitioner
    submitted
    the
    roqn~rect
    information
    on January
    14,
    1974.
    Petitioner
    is the owner and operator
    of
    a coal—fired
    tOectric power generating station near Hennepin,
    Putnam
    onnty1
    Illinois.
    Petitioner requests
    a three—month variance
    ~:om
    tTh December
    31,
    1973 compliance date required by Rule
    (raspended and total dissolved solids)
    of Chapter
    3:
    vinter
    Pollution Regulations
    of Illinois.
    The
    Agency,
    in
    its Recommendation,
    states that wastewater
    from
    otitioner~s generating
    station
    is presently discharged
    Gii:ec~1~v into
    the Illinois
    River via two separate waste
    ~t~oans.
    One waste
    stream
    is made up of untreated wastewater
    from Pntitioner~s demineralizer regenerant,
    ash hopper overflowr
    from Unit
    I and
    2 Boilers,
    and non—contact condenser
    cooling
    water.
    The second waste stream is composed of wastewater
    from Petitioner’s
    Unit
    1 and
    2 ash basin lagoons.
    Petitioner
    suomits
    no information on this point.
    The Agency Recommendation informs
    us that Petitioner’s
    ash basin lagoons rarely discharge
    an effluent due to evapo-
    ration and due
    to percolation attributable
    to the permeable,
    sandy soil
    of the locale and that Petitioner’s
    untreated
    wastewater discharge does not have
    a noticeable adverse en-
    vironmental
    impact upon the
    Illinois
    River.
    We note
    thth
    broad conclusions of this nature would better aid our de-
    liberations
    if supported by specific
    data.
    The term “manly”
    is not helpful
    in this context and the effluent percolated
    through sandy soil might well reach the river by
    a
    different
    route,
    Test
    results
    of
    recent Agency
    effluc:nt:
    qr
    P
    550Oles
    i.naiicate
    the
    following:

    —2—
    Suspended
    Total
    Dissolved
    Date
    Solids
    (mg/i)
    Solids
    (mg/i)
    Jan 1/73
    8
    360
    Sep 25/73
    85
    480
    Petitioner obtained Agency approval of Project Completion
    Schedules and an Agency Construction Permit for re—routing
    and collecting of the Unit
    1
    &
    2 ash hopper overflows and
    demineralized regenerant wastewater into the Unit
    1
    &
    2
    ash basin lagoons for treatment prior to release into the
    River.
    The Agency believes that the completion of these
    projects will assure compliance with Rule 408.
    The permits and associated Project Completion Schedules.
    show the anticipated completion date to be December 31,
    1973.
    Petitioner alleges that the mechanical work associated with
    its project cannot be completed before March
    31,
    1974,
    and
    variance is sought to that date.
    The primary reason advanced by Petitioner to justify
    the grant of the subject variance is the alleged delay
    encountered in procuring materialsand equipment.
    On
    May 1,
    1972, Petitioner issued a work order to its consulting
    engineer to begin the work intended to comply with Rule 408.
    By July of 1972, Petitioner determined in principle to proceed
    with certain changes and began preparing the necessary
    mechanical design and engineering.
    By May 11,
    1973, Petitioner
    submitted a permit application to the Agency for the Hennepin
    facility.
    The Agency notes that though delay in filing
    a
    permit application until May of 1973 appears unusually long,
    Petitioner apparently believed at the time of this submittal
    that timely compliance was possible.
    A permit for the
    Hennepin facility was issued on August
    8,
    1973.
    The Agency believes that Petitioner reasonably anticipated
    that timely compliance could be met if contracts were awarded
    by September
    1,
    1973.
    On August 14,
    1973,
    a piping contract
    was awarded.
    The Agency notes that pumps for the Hennepin
    project were ordered as early
    as March
    19, 1973.
    The
    shipping date for the pumps was scheduled for October 1973.
    As of the date of the Amended petition
    (January 11,
    1974)
    the pumps had not yet been shipped.
    Similar delays were
    experienced in the shipment of piping.
    Though substantial
    portions of the piping are presently on site,
    the balance of
    the piping had not been delivered as of the date of the Amended
    Petition.
    Delays in the shipment of pumps resulted in delays
    in the installation of related electrical equipment.
    Petitioner
    attempted to mitigate delays be refurbishing existing electrical
    equipment.
    We are satisfied that the facts as presented by Petitiore::
    indicate that the delays encountered were substantially
    beyond its control and that the Petitioner took reasonable
    measures to avoid delay.
    11—392

    —3—
    This
    Opinion
    constitutes
    the
    findings
    of
    fact
    and
    conclusions
    of
    law
    of
    the
    Board.
    ORDER
    ~T IS
    THE
    ORDER of the Pollution Control
    Board that
    Illinois Power Company be granted
    a variance,
    as
    regards
    its Hennecin facility,
    from Rule
    408
    of
    Chapter
    3:
    Water
    Pollution Renulations, until March
    31,
    1974.
    IT
    IS SO ORDERED.
    I, Christan
    L. Moffett, Clerk of the Illinois Pollution
    Control Board, certify ttht
    the
    above Oninion and Order
    was
    adopted
    on
    this
    ~
    day of
    ~
    by
    a
    vote
    of
    ~

    Back to top