ILLINOIS POLLUTION CONTROL BOARD
    September
    30, 1971
    BUCKLER FOUNDRY COMPANY,
    INC.
    v.
    )
    PCB 71-189
    ENVIRONMENTAL PROTECTION AGENCY
    William
    E.
    Buckler,
    Jr.
    for Buckler Foundry Company,
    Inc.
    Delbert Haschemeyer
    for the Environmental Protection Agency
    Opinion and Order of the Board
    (by Samuel
    R, Aldrich):
    On July
    12,
    1971, Buckler Foundry Company,
    Inc.
    (“Buckler”)
    requested
    a variance
    from applicable air pollution regulations
    for its East Alton,
    Illinois, plant.
    Petitioner seeks exemption from the rules
    for
    a period
    of nine months in order
    to operate
    a cupola as necessary while
    a
    recently installed electric
    arc furnace
    is being debugged.
    Buckler operates
    a jobbing semi-production gray iron casting plant
    which employs approximately
    18
    people.
    Approximately
    8
    tons of iron
    are melted and poured every other ~ay.
    Until June of this year
    a
    coke—Lired cupola has been employed exclusively for the melting
    operation
    (R.
    56).
    William E.
    Buckler,
    Jr., Vice-President and
    Superintendent of Buckler, estimated particulate emissions from the
    cupola to be
    17 pounds per ton of iron melted
    (R.
    66).
    An Agency
    engineer indicated the calculated figure was actually 3,4~when
    the
    process weight is taken into account
    (R.
    68).
    This
    is approximately
    twice the allowable rate specified by Rule 2—2.54 of
    the Pules and
    Regulations Governing
    the Control
    of Air
    Pollution
    (R.
    71).
    Buckler
    had
    been
    operating
    with
    an
    Air
    Contaminant
    Emission
    Reduction
    Program
    (ACERP)
    approved
    by
    one
    of
    our
    predecessors,
    the
    Air
    Pollution
    Control Board,
    During tho
    pertod
    of
    the
    ACER?
    the
    Company
    was
    to
    replace
    the cupola with
    an electric arc furnace.
    In June of
    1970,
    Buckler
    requested
    an
    extension
    until
    September
    30,
    1970,
    to
    permit
    installation of
    a bag house
    and co:npletion of
    a charging device
    (Pet.
    Ex.
    2).
    In October the Company requested another extension,
    this
    time for
    90 days
    to complete installation of
    the bag~house
    (Pet.
    Ex.
    3).
    The Agency indicates
    in its recommendation that
    no
    action was taken on the
    laiter request.
    On May
    7,
    1971,
    Buckler
    asked the Agency for
    an
    ndditional period of nine months in which
    to
    debug
    the
    ethctric
    arc
    furnace
    (Pet.
    Ex.
    4)
    .
    We here consider
    erscntialiy
    the
    same
    request.
    tenors
    indrcates
    tsat the electric arc rurnace was
    to be ready
    ~on requLar operation
    in early September,
    1971
    (R.
    62).
    Petitioner
    ftr nine monthn
    tine, beginning May
    7,
    1971,
    for debugging.

    Juring this
    interval the furnace would be operated every other day and
    the cupola would be used only in the event of
    a major breakdown
    (R.23,
    25
    At
    the end of
    the nine-month period the cupola would be made inoperable
    and the furnace used on an every day basis
    (R.
    14,
    38).
    The Agency initially recommended that Buckler’s petition be granted
    for
    a period not
    to exceed
    30
    days.
    Mr.
    Buckler pointed out that the
    Company melts iron only 10 or 11 days
    in
    a one-month period
    (R.
    25).
    The period recommended by the Agency would
    thus give the Company only
    ten working days in which to debug the new equipment and train operating
    personnel.
    There
    is evidence
    that
    such procedures may take from six
    months
    to a year
    (Pet.
    Ex.
    5).
    Mr.
    Buckler
    indicated that he
    and
    his
    personnel were inexperienced
    in these matters, making the adjustment
    particularly
    difficult
    (R.
    16).
    The maximum number of operating days
    under the Company’s proposed plan would be
    99,
    although Mr. Buckler
    indicated that the cupola would not be employed on these days unless
    a major breakdown
    were to occur
    (R.
    25).
    At the close of the hearing
    the Agency modified its original position, recommending that
    a variance
    be
    granted for
    a period not to exceed nine months
    (R.
    80).
    The Environmental Protection Act requires that for
    a variance to be
    granted,
    it must be shown that an arbitrary and unreasonable hardship
    would result should the petition be denied,
    In the instant case we
    find
    that Buckler has met its burden of proof.
    The record indicates
    that
    the debugging process and training procedures will require
    a
    considerable amount of
    time,
    Were we to deny the petition or grant
    a lesser period of time
    than that requested, petitioner’s entire
    operation would be placed in jeopardy.
    Denial of permission
    to use
    the cupola on
    a standby basis could seriously hamper petitioner’s
    efforts
    to fill orders on time,
    Mr.
    Buckler indicated that this might
    cause the Company to go out of business
    (R.
    15).
    The amount of parti-
    culate matter released
    if Buckler is allowed
    to operate the cu~La is
    uncertain,
    However,
    the cupola is to be used strictly on a standby
    basis and indeed may never be used,
    Three families interviewed by
    the Agency had no complaints about the emissions from the foundry.
    In
    our judgment
    the hardship on petitioner would be unreasonable
    and is
    not offset by the potential damage
    to the environment.
    In
    a similar
    case
    (Chambers,
    Bering, Quinlan
    Co.
    v.
    EPA, PCB 71-102, August 13,
    1971)
    we denied
    a variance
    on the grounds
    that:
    1)
    petitioner had already
    had ample time
    for debugging and
    2)
    petitioner requested permission
    to use cupolas indefinitely,
    albeit on
    a standby basis.
    Neither of
    these
    facts
    is true
    in the instant case.
    Buckler’s electric furnace
    was
    not ready
    for
    operation until September
    of
    1971,
    and
    a variance
    is requested only until February
    7,
    1972.
    We will, therefore,
    grant
    Buckler a variance for
    the period of time requested.
    Counsel for the Agency pointed out that the conversion project has
    been going on
    since
    1968 and that since then Buckler has failed to
    meet
    a number of deadlines
    for completing it
    (R.
    80).
    However, based
    on the facts elicited
    at the hearing he recommended that no substan-
    tial penalty be
    imposed.
    It is true that the Company has failed to
    meet several projected completion dates
    in the past.
    Nevertheless,
    we are persuaded that petitioner has been confronted with real diffi-
    culties in converting
    from cupola to electhic arc furnace and has made
    a good faith effort to abate pollution.
    We thus impose no monetary
    penalty.
    2—
    544

    In granting
    a variance until February
    7,
    1972, we will
    take steps to
    ensure that the cupola is not used excessively.
    Petitioner has approxi-
    mately four months remaining in which
    to achieve full compliance with
    the air pollution regulations.
    We will limit
    the number of days
    within this period during which Buckler may operate the cupola to 20.
    This should be sufficient time
    to allow for major repairs
    to the
    furnace while ensuring continued operation of the plant.
    We will
    require petitioner
    to make
    the cupola inoperable
    at the end of
    the
    variance period.
    This opinion constitutes
    the Board~s findings of fact and conclusions
    of
    law.
    -
    ORDER
    1.
    Buckler Foundry Company,
    Inc.
    ,
    may use
    its cupOla
    to me-It
    iron
    in the event of major breakdown of theelectric arc furnace,
    such use
    to be limited to 20 days during the period from the
    date
    of this order until February
    7,
    1972.
    2,
    Buckler Foundry Company,
    Inc.,
    shall cease
    the
    use of the cupola
    on February
    7,
    1972,
    and at that
    time shall take whatever steps
    are necessary
    to make the cupola inoperable.
    3.
    By March
    1,
    1972,
    Buckler Foundry Company,
    Inc.,
    shall submit
    to the Environmental Protection Agency and to the Pollution
    Control Board
    a written report indicating
    the dates subsequent
    tO
    the
    filing of this order
    on which the cupola
    was used.
    The
    report is also to indicate what
    steps were taken subsequent
    to
    February
    7,
    1972,
    to
    make
    the cupola inoperable.
    4.
    By
    February
    7,
    1972,
    Buckler Foundry Company,
    Inc.,
    shall
    be in
    full compliance with the Rules
    and Regulations
    Governing the
    Control of Air Pollution.
    I dissent
    I, Regina E.-Ryan, Clerkof
    the Pollution Control Board, hereby
    certify
    that the
    Board adopted the above opinion and order this
    3Oday of
    Septemier’
    1971.
    2
    545

    Back to top