ILLINOIS
    POLLUTION CONTROL BOARD
    February
    14, 1972
    DECATUR MEMORIAL HOSPITAL
    V.
    )
    #
    71—359
    ENVIRONMENTAL PROTECTION AGENCY
    Opinion of the Board
    (by Mr.
    Currie):
    Decatur Memorial Hospital
    seeks
    a variance
    to permit operation
    of
    a coal—fired boiler
    ~which has emitted smoke
    in excess of
    Ringelmann
    #2” until April
    15,
    1972, when the boiler will be con-
    verted to oil
    and gas.
    Continued operation during the conversion
    is alleged to
    be necessary
    “to insure
    a reserve boiler during the
    cold season
    to April
    15, and to allow operation of
    a coal boiler
    as
    the primary boiler during actual conversion.”
    A reserve
    is
    required by
    the Hospital Licensing Act.
    The Agency recommends
    the petition be granted on certain conditions with which we agree,
    except that
    the time remaining
    is so short as to make
    the posting
    of bond hardly worth the trouble.
    The Agency also
    “notes with
    displeasure”
    that neither
    a letter of intent nor
    an emission control
    program was submitted under the 1967 regulations, butwe
    do not
    have enough information to determine whether or not there was
    a
    particulate violation such that filing was required.
    We cannot
    therefore
    impose
    a penalty as
    a condition of the variance as we
    have done
    in cases
    of unjustified failure to file.
    E.g., Molex
    Corp.
    v.
    EPA,
    #71—200
    (Jan.
    6,
    1972).
    We agree with the Agency that
    there is an evident need
    for operation
    of the boiler during the
    interim to avoid possible interruption of hospital service,
    and
    that the apparent harm from continued operation during that time
    is not so great as to justify
    a shutdown.
    We note that we do not
    expressly or impliedly sanction the use of any coal-fired boilers
    for reserve
    or other purposes after April
    15,
    1972.
    Once again we observe that
    the Agency’s recommendation was
    received on the
    90th day after the petition was
    filed,
    the very
    day on which we are expccted
    to make
    a decision.
    We do not
    believe this practice
    of late filing permits
    is ample time to make
    intelligent decisions, much
    less to seek additional information if
    the recommendation indicates the need.
    Moreover,
    the 90-day rule
    prescribes the outside limit for decision; we should in fairness
    to the parties do what we
    can to decide cases
    in less
    time whenever
    possible.
    Simple cases
    like this
    one should not require
    90 days
    to decide.
    3
    633

    ORDER
    Decatur Memorial Hospital,
    Inc.,
    is hereby granted
    a variance to
    permit smoke emissions
    in excess of regulation limits from a coal
    fired Lasker boiler until April
    15,
    1972, provided the following
    conditions
    are met:
    1.
    The Hospital shall obtain
    an installation permit from
    the Agency as required by
    the regulations;
    and
    2.
    No later than May
    1,
    1972,
    the Hospital
    shall submit to
    the Agency and to the Board
    a report indicating
    the date
    of completion and
    the number of hours
    the boiler was
    operated from receipt
    of this order until
    the project
    is
    completed.
    I, Christan Moffett, Clerk of
    the Pollution Control Board, certify
    that the Board adopted the above Opinion of the Board this
    14th
    day of February,
    1972 by
    a vote of
    5-0.
    3
    634

    Back to top