ILLINOIS POLLUTION CONTROL BOARD
March
6,
1975
MORTELL COMPANY,
Petitioner,
v.
)
PCB 74—416
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
Mr. Patrick J. Phillips, attorney for Petitioner.
Mr. Peter E. Orlinsky, attorney for Respondent.
OPINION
AND
ORDER OF THE BOARD
(by Dr. Odell)
On November 8,
1974,
the Mortell Company filed its
Petition for Variance with the Pollution Control Board
(Board).
Petitioner sought a variance from Rules 102,
622,
651,
and 652
of the Air Pollution Regulations (Chapter Two)
for its asbestos-
emitting ribbon and caulk mixers at its Kankakee, Illinois plant.
The variance was requested until November
1,
1975,
to enable it
to install
13 bag houses to limit the asbestos emissions
to
levels set out in Chapter Two.
Rule 102 prohibits air pollution;
Rule
622 requires
an operating permit from the Environmental
Protection Agency
(Agency); Rule 652 and 651 of Chapter Two
require pollution control equipment for asbestos exhausts and
limit
emissions of asbestos fibers to
2 fibers per cubic centi-
meter of air and prohibits visual emissions of asbestos.
Rule
651 of Chapter Two became effective on June 30, 1972.
The Mortell facility manufactures sealants and coatings
through the operation of ten
(10) ribbon mixers and seven
(7)
caulk mixers.
The coatings, blended in the ten ribbon mixers,
are used for sound insulation and in automobile undercoating.
If all mixers are operated simultaneously,
16,676 pounds of
coatings per hour containing 2.93
asbestos fibers are processed.
The sealants, blended in the double—arm caulk mixers, are used
by the automobile industry and for general household repairs.
If all mixers are operated simultaneously,
3,167 pounds of
sealants per hour containing 47.14
asbestos fibers can be pro-
cessed.
Petitioner alleged that the ten ribbon mixers emit 3.57
pounds/hour of particulate matter and that the seven caulk mixers
emit 0.0274 pound of particulate matter per hour.
Petitioner
also alleged that
it did not become aware until July
5,
1974,
that it was violating the limitations set out in Rule 651 of
Chapter Two.
Stack tests on June 13 and 14, 1974, revealed
emission rates ranging from 56.29 fibers per cc to 285.4 fibers
per cc.
Visual emissions were also observed.
16—25
—2—
The Environmental Protection Agency
(Agency)
filed an
objection to the grant of the variance on November 26, 1974;
it moved that a hearing be held purusant to Section 37 of the
Environmental Protection Act.
On December 5,
1974,
the Board
decided that a hearing should be held for this case.
On January
7,
1975,
several we~ksbefore the scheduled
hearing,
the Agency filed its Recommendation stating that it
opposed the variance because,
in light of the potential harm
from asbestos emissions,
the timetable of achieving compliance
by November
1975 was inordinately long.
The Agency believed
that the 13 bag houses to be installed by Petitioner to control
emissions would bring the facility into compliance.
The Agency
stated that were Petitioner to hire outside contractors and
shut down more than one line at
a time,
the. entire project could
be completed by the end of May 1975.
Agency visits during 1974
noted housekeeping deficiencies in possible violation of Rule
621 (b),
(c), and
(d).
Improvement in housekeeping practices
during the last few months of 1974 was noted.
On February
5,
1975, Petitioner waived the 90-day decision
requirement until 30 days after the transcript of the hearing was
filed with the Board.
The transcript was filed on February
5,
1975.
The hearing was held on January
21,
1975,
in Kankakee,
Illinois.
No citizens came forward to testify concerning the
variance.
The evidence at the hearing went primarily to the
issue of whether Mortell
is also in violation of Rule 621(b),
Cc), and
(d) of Chapter Two as alleged by the Agency in its
Recommendation.
Near the close of the hearing, the Agency
admitted that Mortell has a valid program for compliance with
Rule 621(b),
(c),
and
Cd)
(R.55).
WhilePetitioner’s testimony
was helpful to show its efforts to comply with Rule 621, such
testimony did not answer the main issue of whether Petitioner’s
program of compliance
is excessively long.
Some evidence was offered on the issue of the reasonable-
ness of the November 1,
1975, deadline.
A construction permit
to install the 13 bag houses to achieve compliance was received
from the Agency on November 21,
1974.
The total cost of the
project is approximately $60,000
(R.
26).
The first installment
of bag houses, scheduled to arrive by January
1,
1975, has been
delayed
(R.
38).
At the present time the bag houses are to be
delivered according to the following schedule
(Pet.
Ex.
20):
Number of Bag Houses
Expected Delivery Date
First 4 units
February 1,
1975
Next 4 units
April 30, 1975
Final
5 units
July 31, 1975
Petitioner estimated that using its own personnel,
it would take
until the end of 1975 to have all the bag houses installed and
properly operating
CR.
42).
On cross examination,
the witness
16—26
—3—
stated that
90 days from the date of delivery was sufficient
time to complete installation
(R.
43).
While Petitioner’s claim
of actual notice of violations was not refuted, the evidence in-
dicates that the Agency noted possible violations
in its transmittal
letter of April
26,
1974,
(Pet. Ex.
1).
We grant the variance according to the time schedule set
out in our Order.
While Petitioner has made good faith efforts
to comply since it became aware of the violations, the potential
harm from the asbestos emissions mandates a tighter compliance
schedule than that suggested by the Petitioner.
Mortell has had
constructive notice of its violations since the June 30,
1972,
date requiring compliance.
The delay
is partially self-imposed.
While the ordered schedule of compliance may necessitate hiring
outside help to install the bag houses, Petitioner’s reluctance
to fulfill its legal obligations means that additional expenses
result from its own past inaction.
Although the record discloses
that Mortell’s facility is located in
a primarily industrial area,
there are also nearby residents who deserve protection as soon as
possible because of the hazardous nature of the asbestos emissions.
We are giving Petitioner
75 days to install each of the three
groups of bag houses after their projected delivery dates.
This
is sufficient time under the circumstances of this
case.
This Opinion constitutes the findings of fact and con-
clusions of law of the Board.
ORDER
IT IS THE ORDER of the Pollution Control Board that
Petitioner is hereby granted a Variance from Rules
102,
622,
651,
and 652 of Chapter Two from November
8,
1974,
to October
15, 1975,
except to the extent and subject to the conditions set out below:
1.
Petitioner shall install and have operational by April
15,
1975,
the bag houses scheduled for delivery on February 1,
1975.
2.
Petitioner shall install and have operational by July
15, 1975,
the bag houses scheduled for delivery on April
30,
1975.
3.
Petitioner shall install and have operational by
October 15,
1975,
the bag houses scheduled for delivery on July
31,
1975.
4.
During the installation of the first eight bag houses,
Petitioner shall utilize mixers which have been equipped
with
bag
houses before using mixers without bag houses.
5.
Upon the completion of the first eight bag houses,
Petitioner shall operate only those mixers which are equipped
with bag houses.
16—27
—4—
6.
Petitioner shall require every employee associated
with asbestos handling to vacuum clothing before leaving
Petitioner’s facility.
7.
Commencing
30 days after the Order herein, and on
or before the 15th of each month ther~after,Petitioner shall
submit reports to the Agency detailing all progress made toward
compliance.
Said reports shall include delivery dates, in-
stallation dates, and reports of mixers used during the report-
ing period.
Reports shall be sent to:
Environmental Protection
Agency, Control Program Coordinator,
2200 Churchill Road,
Springfield, Illinois
62706.
8.
Within
30 days of the Order herein, Petitioner shall
execute a performance bond in the amount of $30,000 in a form
acceptable to the Agency.
The purpose of said bond is to assure
compliance.
Bond should be sent to:
Environmental Protection
Agency, Fiscal Services,
2200 Churchill Road, Springfield,
Illinois 62706.
9.
Within
30 days of the installation of the final bag
house, Petitioner shall have stack tests performed by an inde-
pendent testing company.
The Agency shall be notified at least
five
(5)
days prior to the tests and shall have the right to
witness all tests.
Test results shall be sent to the Agency at
its paragraph 7 address as soon as they become available.
10.
Petitioner shall obtain all necessary Agency permits.
Mr. Dumelle dissents.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify that the ab ye Opinion and Order was
adopted on the
Q~
day of
“fl~
,
1975, by a vote of
3
to
__.
Christan L. Mo
ett
16—28