ILLINOIS POLLUTION CONTROL BOARD
    March
    6,
    1975
    MORTELL COMPANY,
    Petitioner,
    v.
    )
    PCB 74—416
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    Respondent.
    Mr. Patrick J. Phillips, attorney for Petitioner.
    Mr. Peter E. Orlinsky, attorney for Respondent.
    OPINION
    AND
    ORDER OF THE BOARD
    (by Dr. Odell)
    On November 8,
    1974,
    the Mortell Company filed its
    Petition for Variance with the Pollution Control Board
    (Board).
    Petitioner sought a variance from Rules 102,
    622,
    651,
    and 652
    of the Air Pollution Regulations (Chapter Two)
    for its asbestos-
    emitting ribbon and caulk mixers at its Kankakee, Illinois plant.
    The variance was requested until November
    1,
    1975,
    to enable it
    to install
    13 bag houses to limit the asbestos emissions
    to
    levels set out in Chapter Two.
    Rule 102 prohibits air pollution;
    Rule
    622 requires
    an operating permit from the Environmental
    Protection Agency
    (Agency); Rule 652 and 651 of Chapter Two
    require pollution control equipment for asbestos exhausts and
    limit
    emissions of asbestos fibers to
    2 fibers per cubic centi-
    meter of air and prohibits visual emissions of asbestos.
    Rule
    651 of Chapter Two became effective on June 30, 1972.
    The Mortell facility manufactures sealants and coatings
    through the operation of ten
    (10) ribbon mixers and seven
    (7)
    caulk mixers.
    The coatings, blended in the ten ribbon mixers,
    are used for sound insulation and in automobile undercoating.
    If all mixers are operated simultaneously,
    16,676 pounds of
    coatings per hour containing 2.93
    asbestos fibers are processed.
    The sealants, blended in the double—arm caulk mixers, are used
    by the automobile industry and for general household repairs.
    If all mixers are operated simultaneously,
    3,167 pounds of
    sealants per hour containing 47.14
    asbestos fibers can be pro-
    cessed.
    Petitioner alleged that the ten ribbon mixers emit 3.57
    pounds/hour of particulate matter and that the seven caulk mixers
    emit 0.0274 pound of particulate matter per hour.
    Petitioner
    also alleged that
    it did not become aware until July
    5,
    1974,
    that it was violating the limitations set out in Rule 651 of
    Chapter Two.
    Stack tests on June 13 and 14, 1974, revealed
    emission rates ranging from 56.29 fibers per cc to 285.4 fibers
    per cc.
    Visual emissions were also observed.
    16—25

    —2—
    The Environmental Protection Agency
    (Agency)
    filed an
    objection to the grant of the variance on November 26, 1974;
    it moved that a hearing be held purusant to Section 37 of the
    Environmental Protection Act.
    On December 5,
    1974,
    the Board
    decided that a hearing should be held for this case.
    On January
    7,
    1975,
    several we~ksbefore the scheduled
    hearing,
    the Agency filed its Recommendation stating that it
    opposed the variance because,
    in light of the potential harm
    from asbestos emissions,
    the timetable of achieving compliance
    by November
    1975 was inordinately long.
    The Agency believed
    that the 13 bag houses to be installed by Petitioner to control
    emissions would bring the facility into compliance.
    The Agency
    stated that were Petitioner to hire outside contractors and
    shut down more than one line at
    a time,
    the. entire project could
    be completed by the end of May 1975.
    Agency visits during 1974
    noted housekeeping deficiencies in possible violation of Rule
    621 (b),
    (c), and
    (d).
    Improvement in housekeeping practices
    during the last few months of 1974 was noted.
    On February
    5,
    1975, Petitioner waived the 90-day decision
    requirement until 30 days after the transcript of the hearing was
    filed with the Board.
    The transcript was filed on February
    5,
    1975.
    The hearing was held on January
    21,
    1975,
    in Kankakee,
    Illinois.
    No citizens came forward to testify concerning the
    variance.
    The evidence at the hearing went primarily to the
    issue of whether Mortell
    is also in violation of Rule 621(b),
    Cc), and
    (d) of Chapter Two as alleged by the Agency in its
    Recommendation.
    Near the close of the hearing, the Agency
    admitted that Mortell has a valid program for compliance with
    Rule 621(b),
    (c),
    and
    Cd)
    (R.55).
    WhilePetitioner’s testimony
    was helpful to show its efforts to comply with Rule 621, such
    testimony did not answer the main issue of whether Petitioner’s
    program of compliance
    is excessively long.
    Some evidence was offered on the issue of the reasonable-
    ness of the November 1,
    1975, deadline.
    A construction permit
    to install the 13 bag houses to achieve compliance was received
    from the Agency on November 21,
    1974.
    The total cost of the
    project is approximately $60,000
    (R.
    26).
    The first installment
    of bag houses, scheduled to arrive by January
    1,
    1975, has been
    delayed
    (R.
    38).
    At the present time the bag houses are to be
    delivered according to the following schedule
    (Pet.
    Ex.
    20):
    Number of Bag Houses
    Expected Delivery Date
    First 4 units
    February 1,
    1975
    Next 4 units
    April 30, 1975
    Final
    5 units
    July 31, 1975
    Petitioner estimated that using its own personnel,
    it would take
    until the end of 1975 to have all the bag houses installed and
    properly operating
    CR.
    42).
    On cross examination,
    the witness
    16—26

    —3—
    stated that
    90 days from the date of delivery was sufficient
    time to complete installation
    (R.
    43).
    While Petitioner’s claim
    of actual notice of violations was not refuted, the evidence in-
    dicates that the Agency noted possible violations
    in its transmittal
    letter of April
    26,
    1974,
    (Pet. Ex.
    1).
    We grant the variance according to the time schedule set
    out in our Order.
    While Petitioner has made good faith efforts
    to comply since it became aware of the violations, the potential
    harm from the asbestos emissions mandates a tighter compliance
    schedule than that suggested by the Petitioner.
    Mortell has had
    constructive notice of its violations since the June 30,
    1972,
    date requiring compliance.
    The delay
    is partially self-imposed.
    While the ordered schedule of compliance may necessitate hiring
    outside help to install the bag houses, Petitioner’s reluctance
    to fulfill its legal obligations means that additional expenses
    result from its own past inaction.
    Although the record discloses
    that Mortell’s facility is located in
    a primarily industrial area,
    there are also nearby residents who deserve protection as soon as
    possible because of the hazardous nature of the asbestos emissions.
    We are giving Petitioner
    75 days to install each of the three
    groups of bag houses after their projected delivery dates.
    This
    is sufficient time under the circumstances of this
    case.
    This Opinion constitutes the findings of fact and con-
    clusions of law of the Board.
    ORDER
    IT IS THE ORDER of the Pollution Control Board that
    Petitioner is hereby granted a Variance from Rules
    102,
    622,
    651,
    and 652 of Chapter Two from November
    8,
    1974,
    to October
    15, 1975,
    except to the extent and subject to the conditions set out below:
    1.
    Petitioner shall install and have operational by April
    15,
    1975,
    the bag houses scheduled for delivery on February 1,
    1975.
    2.
    Petitioner shall install and have operational by July
    15, 1975,
    the bag houses scheduled for delivery on April
    30,
    1975.
    3.
    Petitioner shall install and have operational by
    October 15,
    1975,
    the bag houses scheduled for delivery on July
    31,
    1975.
    4.
    During the installation of the first eight bag houses,
    Petitioner shall utilize mixers which have been equipped
    with
    bag
    houses before using mixers without bag houses.
    5.
    Upon the completion of the first eight bag houses,
    Petitioner shall operate only those mixers which are equipped
    with bag houses.
    16—27

    —4—
    6.
    Petitioner shall require every employee associated
    with asbestos handling to vacuum clothing before leaving
    Petitioner’s facility.
    7.
    Commencing
    30 days after the Order herein, and on
    or before the 15th of each month ther~after,Petitioner shall
    submit reports to the Agency detailing all progress made toward
    compliance.
    Said reports shall include delivery dates, in-
    stallation dates, and reports of mixers used during the report-
    ing period.
    Reports shall be sent to:
    Environmental Protection
    Agency, Control Program Coordinator,
    2200 Churchill Road,
    Springfield, Illinois
    62706.
    8.
    Within
    30 days of the Order herein, Petitioner shall
    execute a performance bond in the amount of $30,000 in a form
    acceptable to the Agency.
    The purpose of said bond is to assure
    compliance.
    Bond should be sent to:
    Environmental Protection
    Agency, Fiscal Services,
    2200 Churchill Road, Springfield,
    Illinois 62706.
    9.
    Within
    30 days of the installation of the final bag
    house, Petitioner shall have stack tests performed by an inde-
    pendent testing company.
    The Agency shall be notified at least
    five
    (5)
    days prior to the tests and shall have the right to
    witness all tests.
    Test results shall be sent to the Agency at
    its paragraph 7 address as soon as they become available.
    10.
    Petitioner shall obtain all necessary Agency permits.
    Mr. Dumelle dissents.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify that the ab ye Opinion and Order was
    adopted on the
    Q~
    day of
    “fl~
    ,
    1975, by a vote of
    3
    to
    __.
    Christan L. Mo
    ett
    16—28

    Back to top