ILLINOIS POLLUTION CONTROL BOARD
    January
    21,
    1988
    MCLEAN COUNTY DISPOSAL
    COMPANY,
    INC.,
    Petitioner,
    v.
    )
    PCB 87—133
    COUNTY OF ~4CLEAN
    Respondent.
    DISSENTING OPINION
    (by J.D.
    Dumelle,
    R.
    Flemal and B.
    Forcade):
    The majority holds that
    a county board lacks
    the power
    to
    manage its docket.
    In sum,
    the majority holds that the reason a
    county board lacks
    the power
    to manage its docket
    is that the
    Environmental Protection Act,
    which mandates
    the county board’s
    serving
    as
    an administrative agency
    in these cases,
    has been
    narrowly construed
    in other contexts.
    Concerned Boone Citizens
    v.
    ~4.I.G. Investments,
    Inc.,
    144
    Ill. App.
    3d
    334,
    494 N.E.2d
    180
    2nd
    Dist.
    1986,
    County of
    Lake
    v.
    PCB, 120 Ill. App.
    3d 89,
    457
    N.E.2d
    1309
    2nd
    Dist.
    1983
    Petitioner originally submitted its application on January
    22, 1987.
    On February
    19,
    1987 the County Board’s Pollution
    Control Site Hearing Committee notified Petitioner that the
    application failed
    to adhere
    to county informational
    requirements;
    the committee discovered seventeen
    (17) pro forma
    deficiencies.
    This notiFication of pro forma deficiencies was
    not an evaluation of the substance of Petitioner’s application;
    rather,
    it simply addressed Petitioner’s failure to adhere
    to the
    County’s procedural
    rules,
    to wit:
    1)
    Failure to provide maps of other,
    known water
    wells within one and one—half miles
    of the
    proposed site
    in violation of county procedural
    rule Section 33.28(B);
    2)
    Failure
    to provide adequate and accurate maps
    related
    to nearby land uses and homes located
    within one and one—half miles of the site
    in
    violation of application filing county
    procedural rule section
    33.28;
    3)
    Failure
    to provided complete plans and
    specifications for building structures
    in
    violation
    of county application filing
    85—211

    procedural rule Section
    33.39.
    The rejection
    concerning this criteria stated that the
    application was unclear whether approval was
    also being sought for
    a
    recycling center and
    incineration center;
    therefore,
    the county
    required more information
    to flesh out the
    Petitioner’s Application.
    4)
    Failure
    of traffic study maps,
    road weight maps
    and building maps to match the legal
    descriptions
    of the site and surrounding areas.
    The four above—noted deficiencies are only four
    (4)
    of
    the
    seventeen
    (17) deficiencies identified by the County Board’s
    Pollution Control Site Hearing Committee
    ——
    but these do serve to
    highlight the fact that the application was incomplete when
    initially tendered on January
    22,
    1987.
    It should be noted that
    the duly enacted county ordinance states no application for site
    approval shall
    be deemed
    filed
    until
    all filing
    and data
    requirements are followed.
    The county ordinance,
    at section
    33.04,
    states
    as follows:
    “33.04.
    No application
    for site approval shall
    be
    deemed to have been filed
    or accepted for filing
    unless
    all
    of
    the requirements of this resolution
    applicable
    thereto have been met and the county
    clerk
    shall not give
    a receipt
    or other indication
    of
    filing until such time as
    it
    is determined
    that
    the application complies with the requirements
    of
    this section....”
    McLean County Revised Code,
    Section
    33.04.
    Shortly after notification
    of the deficiencies, Petitioner
    submitted further data and documentation (apparently without
    objection).
    On March
    17,
    1987,
    after Petitioner complied with
    the county ordinance by tendering
    all required information,
    the
    application was deemed
    ‘filed’
    as
    of that date.
    Upon receipt of
    a complete application package,
    the application became
    ‘filed’,
    hearings were held and
    a final decision was rendered within the
    180—day time limit established by law.
    On August
    18,
    1987 the
    full county board denied petitioner’s siting application for
    substantive reasons.
    In sum, the majority holds that because the appellate courts
    have struck down certain county boards’
    attempts
    to im~osefiling
    fees when
    the Act did not explicitly provide
    for such,
    county
    boards now lack the authority to impose any reasonable filing
    procedures and requirements when the result of such may cause
    a
    1
    It should be noted
    that the Act has subsequently been
    amended
    to allow counties
    to set filing
    fees.
    85—212

    final decision
    to be entered
    in excess
    of 180 days from the date
    that the application
    is initially tendered to the county board.
    Apparently,
    it does not matter
    that the county board’s filing
    requirements were obviously directed toward fulfilling
    the
    ultimate purpose of the act:
    A full and fair hearing on the
    merits.
    Section 39.2(a)
    of the Act establishes the criteria
    to be
    considered
    at
    a landfill siting hearing.
    Subsequently,
    it
    provides
    as follows:
    “The siting approval, procedures,
    criteria
    and appeal procedures provided for
    in this Act..,
    shall
    be the
    exclusive.., procedures and
    rules.”
    In
    1986,
    the Second District
    Appellate Court,
    narrowly interpreting this Section, held as
    follows regarding
    the imposition of
    a filing fee:
    “Section
    39.2
    does
    not
    specifically
    grant
    power
    to
    assess
    fees...
    (and)
    the
    imposition
    of
    a
    filing
    fee
    is
    not
    a
    reasonable
    and
    necessary condition in order
    to accomplish the
    purpose
    of
    Section
    39.2.”
    Concerned
    Boone
    Citizens, supra”
    While
    it may
    be true that the imposition of
    filing fees
    is
    not closely enough
    related
    to the purpose
    of the Act
    to survive
    a
    narrow interpretation, surely
    a filing requirement which seeks to
    provide the county board with
    the complete facts andrelevant
    information
    is sufficiently related.
    Without saying more,
    it
    is obvious that the intent of the
    General Assembly
    in
    directing county boards to sit
    in review of
    an application for siting
    of landfills
    is to achieve
    a full and
    fair adjudication on the merits of
    the proposal.
    This
    is why
    the
    Act establishes the criteria by which an application
    is
    to
    be
    judged,
    to wit:
    Local safety, incompatibility with nearby areas,
    impacts on local
    traffic flows...
    etc.
    The county board passed an ordinance which required
    applicants
    for
    a landfill to submit certain information with
    its
    application;
    this included data relative
    to nearby water wells,
    neighboring land uses,
    and
    road weight maps,
    in addition
    to other
    data.
    County Ordinance Procedural Rule
    Section 33.28.
    These
    data are required
    in order
    to
    fully review the application in
    accordance with
    the criteria established
    in the Act, and
    to
    establish the proposal’s safety, compatibility and impacts on the
    area.
    A county board may exercise powers which are necessarily
    implied from those powers expressly granted by the legislature.
    McDonald
    v. County Board
    of Kendall County,
    146 Ill.
    App.
    3d
    1651,
    497 N.E.2d 509
    2nd
    Dist.
    1986.
    In this case the county
    required data which would substantially aid it
    in fulfilling
    the
    obligations
    imposed by the Act.
    The county board procedural
    rules are proper, reasonable and directly related
    to the very
    purpose of the Act, which
    is
    a full and complete hearing on the
    85—213

    —4—
    merits.
    The majority apparently believes that the ultimate
    purpose
    of the Act is
    that “final action” occur.
    This,
    apparently regardless of whether this final action
    is
    a summary
    dismissal or
    a full and complete hearing.
    We disagree!
    The next issue
    is whether
    a county board can reject an
    application, where that application fails
    to comply with its
    procedural
    rules.
    The power
    to reject a purported filing for
    failure
    to comply with the regulations has been decided:
    There
    is
    a
    sound
    use,
    and
    indeed
    requirement
    of
    an
    Agency
    “rejection”
    of
    a
    party’s
    filing..,
    it
    is appropriate
    where
    the
    filing
    is
    so
    deficient
    on
    its
    face
    that
    the
    Agency
    may
    properly
    return
    it
    to
    the
    filing
    party
    without
    even awaiting
    a
    responsive
    filing
    by
    any
    other
    party...
    Both,
    when
    the
    governing
    statute
    explicitly provides
    for rejection
    and
    when
    it
    does
    not.”
    Municipal
    Light
    Boards,
    etc.,
    Mass
    v.
    FPC,
    450
    f2d
    1341,
    D.C.
    Cir.
    1971.
    In this case, although
    the county board
    is ordinarily
    a
    legislative body,
    it
    is acting pursuant
    to
    a statute which
    mandates the County Board
    to act
    as an administrative body in
    a
    quasi—adjudicatory setting.
    The analogy to administrative law
    is
    clearly appropriate.
    The county board has the authority and indeed the
    responsibility to reject Petitioner’s purported filing when that
    filing fails
    to comply with filing requirements,
    and fails
    to
    contain
    the data necessary to
    allow the county board
    to perform
    its essential function.
    The majority’s argument
    is that
    a county board may not
    reject
    a purported filing because doing so may result
    in the
    rendering of
    a decision
    in excess
    of 180 days from the date
    of
    initial tender
    to
    the Board.
    This
    is indefensible.
    The majority
    has mistakenly focused on the
    result
    ——
    not the authority to do
    the act.
    An administrative agency clearly has the authority to
    manage
    its docket by rejecting clearly insufficient purported
    filings.
    Municipal Light,
    supra.
    The majority has focused on the fact that Section 39.2
    states that
    it shall be
    the exclusive procedures and rules
    in
    local
    landfill hearings.
    Notwithstanding
    the explicit language
    of
    the Act,
    this cannot be because the Act does not contain
    provisions which would enable
    a hearing
    to occur
    or proceed.
    The
    Act fails
    to contain provisions defining or creating hearing
    officers,
    the order
    of proceedings,
    the hours and location of
    proceedings and who may or must testify.
    All of
    these are left
    to
    the county board
    ——
    notwithstanding
    the express provision of
    85—214

    the Act.
    The Act does not establish
    the amount of the filing fee
    which
    is now allowed,
    or
    the contents of the application
    package
    itself.
    Similarly the Act fails
    to describe the
    organization of the county board,
    its rules of order,
    its
    constituency, what constitutes
    a quorum,
    a valid vote, and what
    evidentiary standards will be employed.
    All
    of these
    are defined
    by other provisions
    of Illinois law or are left for
    the county
    boards
    to determine
    ——
    notwithstanding
    the express provisions of
    the Act.
    Somehow,
    the majority has no difficulty with county
    boards adopting regulations relative
    to
    the above matters
    ——
    but
    the county board may not set forth
    informational filing
    requirements
    if
    the enforcement
    of
    such might cause
    a decision
    later
    than 180 days from the date that the application was
    initially tendered.
    It should be noted
    that this Board routinely and
    unilaterally extends decision deadlines.
    For
    18 years this
    Board,
    has treated Amended Variance Petitions
    as re—starting the
    statutory time clock.
    This,
    even when the Amended Petition filed
    was
    in response
    to this Board’s notice of insufficient filing
    and
    threat
    of dismissal.
    The process works as
    follows:
    A Petition For Variance is
    filed on January
    1st.
    The Board must render
    its decision within
    120 days
    ——
    else the variance
    is deemed granted by operation of
    law.
    However,
    if the Petition is deficient
    fails
    to
    include
    necessary data required by
    35
    Ill. Adm Code 104.121
    this Board
    will require the submission
    of
    an Amended Petition containing
    the
    required data.
    If that Amended Petition
    is filed on February
    15th,
    then this Board will render
    a hearing within
    120 days of
    February 15th.
    If this Amended Petition
    is deemed insufficient,
    the
    120 time deadline will not be invoked until
    a complete
    Variance Petition
    is presented.
    The majority,
    by blindly requiring
    the county boards to
    issue
    a final decision within
    180 days
    of initial
    tender, has
    adopted
    a
    “do
    as
    I
    say
    ——
    not as
    I
    do” approach to the siting
    of
    local landfills.
    The importance of
    the above
    analogy
    is that
    it demonstrates
    the practicality and logic
    of
    reviewing an application
    for
    completeness before scheduling hearings on
    a fatally defective
    Petition.
    The logic
    is inescapable
    ——
    yet the majority refuses
    to recognize this as
    it relates
    to county board’s review of
    applications for landfills.
    Indeed
    this Board’s regulations regarding permit
    applications are almost identical to the county ordinance which
    the majority says cannot be enforced
    “An
    application
    shall
    not
    be
    deemed
    to
    be
    filed
    until
    the
    applicant
    has
    submitted
    all
    85—215

    information...
    Required...
    35
    Ill.
    Adm.
    Code Section 201.158.
    McLean County Revised Code Section 33.04
    states as
    follows:
    “No
    application..,
    shall
    be
    deemed...
    filed
    unless
    all...
    requirements...
    have
    been
    met
    and
    the county clerk
    shall
    not give
    a receipt
    or
    other
    indication
    of
    filing
    until such time
    as
    it
    is
    determined
    that
    the
    application
    complies...
    Although
    it
    is true that the Pollution Control Board may
    adopt
    its own substantive and procedural rul?s
    ——
    it
    is also true
    that
    a county board may adopt rules which are necessarily implied
    and which
    are directly related
    to
    its essential function.
    This
    Pollution Control Board adopts procedural
    rules because
    it
    is
    expressly authorized
    to do
    so.
    County boards may adopt
    rules
    because the Act is incomplete and
    a hearing could not be held
    without the adoption
    of supplemental rules.
    County authority to
    adopt proper
    rules,
    is necessarily implied.
    The majority states that actions by a county committee do
    not constitute final county action.
    Without addressing
    the issue
    of the propriety of delegating ministerial
    functions
    to
    a
    committee
    for
    instance reviewing
    an application
    to ensure that
    it complies with duly enacted county ordinances
    ——
    this case
    revolves not around the county committee,
    but on the county
    ordinance itself.
    It was the county ordinance which required
    complete information; and
    it was
    the county ordinance which held
    that
    no application was deemed filed until
    it was complete.
    Clearly,
    it was final county action adopting the procedural
    rules, which require complete applications.
    The intent of
    the General Assembly could not have been to
    force
    the county board and the Petitioner
    to engage
    in
    a
    meaningless and impotent administrative exercise, one whose
    outcome
    is predetermined by the unfortunate
    and inadvertent
    failure
    to include certain required data in the application
    package.
    But this
    is exactly what the majority requires by
    demanding
    that the county board hold
    a special meeting and public
    hearing simply
    to summarily dismiss an application.
    The purpose of
    this Board
    is the prevention of environmental
    pollution and protection of
    the public health.
    Accordingly this
    Board
    is required, by statute,
    to determine,
    define and implement
    environmental standards.
    Ill Rev Stat.
    1986
    ch.
    111 1/2 Section
    1005(a).
    The decision of the majority has preempted this
    function.
    By holding that Petitioner’s application
    is deemed granted
    by operation of law the majority has prevented this Board from
    85—216

    reviewing the merits of the proposed landfill.
    As a result of
    the majority’s decision, McLean County must now accept a landfill
    which has not been demonstrated
    to
    be safe.
    It has not been
    shown to be safe to this Board
    or
    to the duly elected
    representatives of
    the people of
    McLean County:
    The McLean
    County Board.
    The majority attempts to mollify this indignity and danger
    by noting that the Illinois Environmental Protection Agency
    (IEPA)
    is still
    required to
    review the proposal.
    But this only
    serves
    to highlight the injustice that has been done.
    The IEPA
    will do what
    it must necessarily do with every landfill proposal
    that comes before
    it:
    It will review
    the plans according
    to out-
    dated regulations
    adopted
    as
    long ago as
    1973
    to ensure
    engineering integrity congruent with those
    regulations.
    The
    Illinois Environmental Protection Agency (IEPA)
    is not charged
    with the duty
    to review the application and circumstances
    to
    ensure that
    a landfill
    is truly needed Section 39.2(a)(l).
    The
    IEPA does not review an application
    to ensure that
    a proposed
    landfill site will minimize incompatibility with the surrounding
    area Section 39.2(a)(3).
    The IEPA does not review an application
    to ensure that impact(s) upon nearby roadway uses and traffic
    patterns will
    be minimized Section 39.2(a)(6).
    It
    is the county
    board that
    is charged
    with all these duties.
    It
    is also the
    county board which
    is charged with
    the duty
    to ensure that the
    plan of operation will protect the facility and
    the surrounding
    area from fire,
    spills
    and other occupational accidents Section
    39.2(a)(5).
    The county board,
    consisting of duly elected
    representatives
    of
    the people of McLean County
    is charged with
    these and other duties pursuant
    to Ill Rev Stat.
    1986 ch.
    111 1/2
    Section 1039.2.
    Likewise this technically qualified board
    (the
    Pollution Control Board)
    is charged with the duty to review the
    county board’s decisions according to the statutory criteria and
    to ensure that these decisions are not contrary
    to the manifest
    weight of
    the evidence.
    Ill Rev Stat.
    1986 ch.
    11 1/2 Section
    1040.1.
    This statutory scheme has been preempted.
    The majority’s decision wrongly sidesteps the statutorily
    mandated scheme
    and orders that
    the permit be deemed granted by
    operation of
    law.
    The unfortunate reason
    for this unhappy result
    is the County Board Site Hearing Committee,
    in attempting
    to aid
    the Petitioner
    in tendering
    a completed package,
    and acting
    pursuant to
    a duly enacted county ordinance,
    notified Petitioner
    an
    incomplete application package was tendered.
    It was then
    fully explained
    to Petitioner
    which additional documents were
    needed.
    The majority’s decision simplisticly exalts form over
    substance.
    The very purpose
    of this board
    is
    to review the
    substance of permit applications,
    the county board decision and
    to ensure that the environment
    is protected.
    The majority’s
    decision abrogates that duty.
    85—217

    —8—
    It
    is the majority’s position that
    a special
    county board
    meeting
    is
    required to notify an applicant that
    it has failed
    to
    follow duly enacted filing
    requirements.
    This,
    notwithstanding
    the Municipal Light opinion regarding proper rejection of
    a
    proffered filing.
    For some unknown reason precious time and
    county resources must be mustered
    for
    the county board
    to engage
    in
    a meaningless exercise
    to notify an applicant that pursuant to
    an earlier enacted county ordinance it has failed
    to
    follow the
    filing procedures.
    Not only does
    the majority’s view exalt form over substance,
    but it also injects
    a needless amount of acrimony and friction
    into an already difficult situation.
    Instead of attempting to
    help an applicant by facilitating and ushering an applicant to
    a
    fair,
    final adjudication, counties are being told that they
    should refrain from helping an applicant so they can later ambush
    the application at a special county board meeting for minor
    procedural deficiencies.
    It should be noted that after July 1,
    1988,
    applicants will be prohibited from refiling for two years
    following
    a rejection.
    Not only
    is the majority’s decision
    improper but
    it
    is surely not the General Assembly’s intent.
    It
    is important
    to note that both
    sides were operating in
    good faith.
    The County Ordinance and the Petitioner were merely
    trying
    to usher
    a completed application package
    to the ultimate
    decision—maker.
    This they were successful in doing.
    Obviously,
    the legislature intended that there would be
    such a considered
    decision by an informed adjudicatory body.
    Holding that the permit should now
    issue by operation of
    law
    (for failure
    of the County Board to render
    a final decision
    within 180 days
    of January 22,
    1987)
    is incongruous with the
    conduct of
    the parties and would unfairly punish
    the county and
    the people
    of McLean County for seeking
    to aid applicants,
    and
    obtain
    a full hearing on the merits.
    It would be unreasonable
    to
    expect the county
    to prepare
    (and pay for)
    an entire hearing
    schedule upon receipt
    of
    a fatally defective application
    package.
    Surely the Act does not mandate
    a full county hearing
    process for every piece
    of paper which merely identifies itself
    as an application
    ——
    yet this
    is exactly what the majority would
    require.
    Conversely,
    it would be improper for
    a County Board
    to
    allow or encourage an applicant
    to needlessly expend resources
    when the application package
    is
    lacking important information and
    cannot be granted.
    For
    the above—noted reasons,
    we respectfully dissent.
    85—218

    —:)—
    Jacob D. Dumelle
    ~Chairman
    Ronald Flemal
    Board Member
    I,
    Dorothy M.
    Gunn,
    Clerk
    of the Illinois Pollution Control
    Board, hereby certify that the above Di senting Opinion was
    submitted on the
    ~r~-
    day of
    _____________________,
    1988.
    Dorothy M. ~3unn,Clerk
    Illinois Pollution Control Board
    Board Member
    85—219

    Back to top