ILLINOIS POLLUTION CONTROL BOARD
    July
    31,
    1981
    SADDLE HILL ESTATES, an Illinois Partnership, and
    )
    THE FOGELSON COMPANIES,
    INC.,
    an Illinois Corpo-
    )
    ration,
    Petitioners,
    v.
    )
    PCB 81—66
    ILLINOIS ENVIRONMENTAL PROTECTION AGENCY, and
    )
    COUNTY
    OF
    LAKE,
    )
    Respondents.
    OPINION
    AND
    ORDER
    OF
    THE
    BOARD
    (by
    J.
    D.
    Dumelle):
    On
    April
    24,
    1981 Saddle Hill Estates
    (Saddle Hill)
    and The
    Fogelson
    Companies,
    Inc.
    (Fogelson)
    filed
    a
    petition
    for
    variance
    front Rule
    962(a)
    of
    Chapter
    3:
    Water
    Pollution,
    to
    allow
    ten
    ad-
    ditional single-family homes in the Saddle Hill Farms Subdivision
    to discharge to the Terre Fair Sewage Treatment Plant
    (STP)
    on
    a
    temporary basis.
    Hearing was waived.
    In response to the Board~s
    May 1, 1981 Order, on May 13,
    1981 the County of Lake was joined
    as a respondent.
    On May 28,
    1981 an objection to the variance was
    filed and in response a hearing was scheduled for July 21,
    1981.
    However, only the parties and the objector appeared, and pursuant
    to an agreement between all present, the objector withdrew his
    objection and no hearing was actually held.
    Although the Board
    is reluctant to allow the cancellation of hearings for which notice
    has gone to the public through the Environmental Register,
    in this
    case since the objector agreed and no one else appeared,
    there
    appears to have been no prejudice to anyone.
    Therefore,
    the Board
    can properly reach a decision on the pleadings and the Illinois
    Environmental Protection Agency’s
    (Agency’s)
    amended recommendation
    which was filed on July 22,
    1981,
    recommending that variance be
    granted subject to certain conditions.
    Saddle Hill Farms
    is a subdivision located in the Village of
    Green Oaks, Lake County,
    Illinois.
    An Intergovernmental Agreement
    provides for the treatment of sewage from Green Oaks by Lake County
    at the Libertyville Sewage Treatment Plant.
    Saddle Hill Estates
    has exercised its option to purchase the ninety—six lots
    in the
    subdivision and has presently paid for sixty.
    It has constructed
    or is constructing homes on forty—one lots and has delivered or
    will deliver thirty-nine of them to buyers.
    It has contracts for
    four additional homes, but cannot start construction since Green
    Oaks will not issue building permits.
    The reason is that only
    forty units are approved for treatment at the STP.
    43—13 1

    —2—
    Fogelson previously developed
    a ninety-unit subdivision
    across the road from Saddle Hill Estates in an unincorporated
    portion of Lake County.
    It constructed the STP at its own cost
    to treat sewage from its development.
    It was understood that
    upon completion of the Libertyville interceptor sewer,
    the STP
    would be dismantled and the sewage would flow directly into that
    interceptor.
    The County agreed to operate the STP until the
    interceptor became available.
    However,
    there have been continual
    delays in its construction, and the County
    is unable to predict
    a completion date.
    However,
    it does not object to Saddle Hill
    expanding the STP at its own expense to handle the flow from ten
    additional homes.
    On March 25,
    1981 the Agency denied Saddle Hill’s application
    to increase the number of units discharging to the STP from forty
    to fifty.
    The reason was that the Agency determined that the in-
    crease would result in a hydraulic loading of 110.
    However, Fogel-
    son has initiated all necessary action to increase the capacity
    of the STP to serve all ninety-six Saddle Hill homes, and the County
    has agreed to continue operation.
    The planned expansion is esti-
    mated to be completed in 165 days.
    A minimum of 120 days is needed
    to build and connect homes to the system.
    Although Saddle Hill
    hopes to complete all
    96 homes, this variance only requests that
    ten be allowed connection.
    Apparently,
    further connections will
    not be requested until after expansion of the STP or completion of
    the interceptor.
    During 1980 Discharge Monitoring Reports disclose only two
    violations of NPDES permit conditions at the STP for BODç and SS.
    The Agency alleges that the planned expansion should enable the
    STP to continue to meet NPDES requirements.
    However,
    the Agency
    further alleges that surcharging has occurred from an eight—inch
    line serving Fogelson’s subdivision.
    Although this
    is not the same
    line which serves Saddle Hill,
    both are tributary to the same lift
    station.
    Therefore, any variance granted must
    be
    conditioned on
    resolving the problems which result in such surcharging.
    Saddle Hill and Fogelson have advised the Agency that they
    are proceeding with steps to eliminate the surcharging. They have
    also expressed a willingness to take other actions recommended by
    the Agency to assure that the surcharging will not be repeated.
    During a recent two and a half inch rainfall the Agency observed
    no surcharging.
    The Board finds that any adverse environmental impact should
    be minimal.
    The time period of overloading at the STP should be
    of short duration since the earliest projected date for new con-
    nections is only forty-five days prior to the estimated date for
    completion of expansion of the STP.
    Further, the efforts to solve
    the surcharging problem,
    the abandonment of the STP upon completion
    43—132

    —3—
    of
    the
    interceptor,
    and
    the
    interim
    expansion
    of
    the
    STP
    should
    all
    serve
    to
    minimize
    any adverse impact.
    Given
    the
    lack
    of
    serious
    harm,
    the
    Board
    further
    finds
    that
    denial
    of
    the
    variance
    would
    impose
    an
    arbitrary
    and
    unreasonable
    hardship.
    Saddle Hill has apparently committed itself
    to delivery
    of
    some
    of
    the
    homes
    and
    has
    completed
    plans
    for
    the
    remainder.
    It
    is
    carrying
    interest
    charges
    of
    over
    $254,000/year
    and
    other
    costs
    of
    approximately
    $200,00/year.
    Further,
    at
    least
    thirty
    construction jobs would be lost in Lake County, and marketing
    and promotion momentum generated over the last two years will be
    dissipated.
    This Opinion constitutes the Board’s findings of fact and
    conclusions of law in this matter.
    ORDER
    1.
    It is hereby ordered that Saddle Hill Estates and the
    Fogelson Companies,
    Inc.
    (Petitioner)
    be granted a variance from
    Rule 962(a)
    of Chapter
    3:
    Water Pollution, subject to the fol-
    lowing conditions:
    a.
    This variance shall only apply to allow extension of
    tributary sewer lines to serve 10 additional single family
    dwellings.
    b
    Occupancy and use of the additional dwellings, or any
    of them,
    shall be prohibited prior to Petitioner’s installation
    of backup blower equipment at the Terre Fair STP as set forth
    in the Agency’s recommendation in PCB 81-69.
    c.
    Whenever
    the interceptor sewer becomes available,
    Petitioners shall connect to
    it and abandon the Terre Fair STP
    as soon as practicable;
    d.
    Petitioners shall obtain all necessary permits for the
    sewer
    system
    extension
    sought
    by
    them.
    e.
    Petitioners’ expanded STP shall be on line and opera-
    tional as soon as practicable, but in no event later than 90
    days after the Agency approves Petitioners’ permit application
    for the expansion of the Terre Fair Treatment Plant;
    Peti-
    tioners shall submit a complete permit application
    (including
    plans
    and
    specifications)
    within
    forty—five
    (45)
    days
    of
    the
    grant of this variance.
    f.
    Petitioners
    shall assure that all lines tributary to
    the Terre Fair STP shall at all times be properly installed
    so as to prevent surcharging.
    This shall include, but need
    not be limited to, the following:
    1.
    Proper
    installation
    and grading of manholes
    43—133

    —4—
    to prevent storm water inflows to the sanitary sewer
    lines.
    ii.
    Installation of proper equipment at tributary
    lift stations;
    iii.
    Location and removal of blockages within
    sewer lines as necessary.
    g.
    Respondent Lake County Department of Public Works
    will assure proper operation and maintenance of the plant
    in accordance with Paragraph
    1. of an agreement entered
    into between the County and Petitioners on August 12, 1975
    and attached as “Exhibit
    D” to the Petition.
    2.
    The Agency is hereby authorized to issue
    a Permit to
    Construct and Operate a sewer system extension consistent with the
    Board’s Order herein and including the requirement that Petitioners’
    sewer lines,
    as extended,
    shall be constructed and maintained so as
    to prevent backups and surcharging.
    3.
    Within 45 days after the date of this Order the
    Petitioners
    shall
    execute
    and
    forward
    to
    the
    Illinois
    Environ-
    mental Protection Agency,
    Water Pollution Control Division,
    2200 Churchill Road, Springfield, Illinois 62706 and to the
    Pollution Control Board
    a Certification of Acceptance and Agreement
    to be bound to all terms and conditions of the variance.
    This
    45 day period shall be held in abeyance for any period during which
    this matter is appealed.
    The form of said Certification shall be
    as follows:
    CERTIFICATION
    Saddle Hill Estates and the Fogelson Companies,
    Inc., Petitioners
    herein, having read and fully understanding the Order of the Illinois
    Pollution Control Board in PCB 81-66 hereby accept said Order and
    agree to be bound by all terms and conditions thereof.
    SADDLE HILL ESTATES
    THE FOGELSON COMPANIES,
    INC.
    _______________________________
    By_______
    Name(s)
    Title
    Date
    By
    Name(s)
    Title or Capacity in which
    Signing
    Date
    43—134

    IT
    IS SO ORDERED
    I,
    Christan. L~Moffett, Clerk of
    t.he. Ii
    linois Po1lut~on
    Control BoRrd,
    hereby certify that the above
    Order was adopted
    onthe3/’~’da~
    1981 byavoteof
    Illinois
    ~oard
    43
    135

    Back to top