ILLINOIS POLLUTION CONTROL BOARD
    December 19,
    1974
    A.?. GREEN REFRACTORIES
    CO.
    PETITIONER
    )
    )
    PCB
    74—163
    ENVIRONMENTAL
    PROTECTION AGENCY
    )
    RESPONDENT
    )
    MR.
    JAMES
    PEACOCK,
    ATTORNEY,
    in
    behalf
    of
    A.?.
    GREEN
    REFRACTORIES
    MESSRS.
    JOHN
    PALINSCAR
    and
    WILLIAM
    A.
    ERDMAN,
    ATTORNEYS,
    in
    behalf
    of
    the
    ENVIRONMENTAL
    PROTECTION
    AGENCY
    OPINION
    AND
    ORDER
    OF
    THE
    BOARD
    (by
    Mr.
    Marder)
    This
    action
    involves
    a
    request
    for
    variance
    filed
    on
    April
    26,
    1974.
    The
    Board
    on
    May
    2,
    1974,
    ordered
    more
    information
    so
    as
    to
    allow a more reasoned decision.
    Petitioner on June 10, 1974, sup-
    plied such additional information which fulfilled the Board’s re-
    quirements.
    Relief was requested from Rules
    202
    (b),
    203
    (b)
    ,
    203
    (f),
    and 204
    (f) (1) (A)
    of the Board’s Air Pollution Regulations, as
    they apply to Petitioner’s facility.
    Petitioner owns and operates in Morris, Illinois, a facility for
    the mining of raw clay as well as associated unit operations such as
    crushing,
    grinding,
    drying,
    and mixing.
    Materials produced are used
    basically in the steel and foundry industry.
    It is alleged that the
    nearest alternate source for such material is located in Southern
    Ohio and Missouri.
    The facility engages in strip mining on site to
    supply approximately 81.2
    of its raw material.
    Mining is carried
    out by the use of dozers, drag crane, and scraping equipment.
    It is
    alleged that water sprays are utilized to minimize fugitive dust.
    Mined material is then passed through a roll crusher to reduce its
    size to less than 2”
    in
    diameter..
    Material so crushed is then trans-
    ported via conveyor belts
    to the central grinding department.
    Mater-
    ial is then passed through pan grinders to reduce the particle size.
    This
    is then bucket
    conveyed
    to
    a
    screening
    and
    rotary
    drying
    opera-
    tion.
    A selected portion of the screened material is sent to the drier
    for admixing with undried material or to be used to generate a separate
    end product.
    Approximately 21.6
    (15,561 tons) of total grinding
    throughput was dried.
    Transference from the screening operations
    to
    either bulk loads
    or other production areas in the plant takes place.
    These transfer points are allegedly controlled by means of a fabric
    filter baghouse.
    A percentage of the material from the grinding department
    is con—
    ‘4—693

    —2—
    veyed
    to
    the
    “Castable”
    department.
    Material
    is
    then
    passed
    through
    two
    rotary
    dryers
    as
    needed.
    Material
    is
    then
    mixed
    and
    transported
    for
    shipment.
    Other
    materials
    from
    the
    grinding
    operation
    are
    diverted
    to
    the
    “Hendryx”
    Building,
    which
    is
    essentially
    a
    material
    handling
    facility.
    The
    final
    portion
    of
    ground
    material
    is
    diverted
    to
    either
    the
    sleeve
    press
    or
    fireplace
    brick
    facilities.
    Both
    of
    these
    opera-
    tions entail drying and firing operations
    (via a kiln).
    A detailed
    flow sheet for the above operations has been submitted verbally in
    “Appendix A”
    to the Petition and schematically in Drawing #ll6F-7 ap-
    pended
    to
    the
    Petition.
    Emissions
    are
    generated
    at
    various
    points
    along
    the
    process.
    Trans-
    ference and packaging operations give rise to fugitive dust problems,
    while dryers generate particulates.
    The kilns, due to the high oper-
    ating temperature and composition of feed,
    emit SO2 as a product of com-
    bustion.
    The main emission sources at the facility are as follows:
    Source
    Type Emiss-
    App. Rule
    Allow.
    Estimated
    Emiss ions
    ions
    Crush. Dept.
    Dryer
    800-890#/hr.
    Particulate
    203
    (a)
    l2.5#/hr.
    Castable Dept.
    Dryers
    600-700#/hr.
    Particulate
    203
    (a)
    4.144t/hr.
    Crush.
    Dept.
    Dryer
    SO2
    4960 ppm
    204(f) (1) (A)
    2000 ppm
    An initial hearing was held, on August 13, 1974,
    at which time a ten-
    tative stipulation was entered into between the parties.
    This situa-
    tion was,
    at a later date (10/30/74), followed with two joint stipula-
    tions which are at the heart of this matter,
    and will be discussed lat-
    er in this Opinion.
    At the August 13, 1974, hearing, Mr. Noell
    (plant manager) discussed
    the location and staffing of the plant.
    The facility has approximately
    88
    employees
    (R.
    16)
    and
    is
    located
    on a 900-acre site which is rela-
    tively
    isolated
    from
    residential
    structures.
    Mr.
    R. Besalke
    (mgr. en-
    vironmental control) appeared to briefly discuss Petitioner’s attempts
    at compliance.
    One major point raised at this hearing is that by stip-
    ulation the variance request for Rule 203
    (f) was withdrawn,
    as no evi-
    dence of fugitive dust violations were found or anticipated.
    The Aug-
    ust 13 hearing was then adjourned to allow time for submittal of a new
    stipulation.
    The
    second
    hearing
    was
    held
    on
    October
    30,
    1974,
    at
    which
    time
    new
    stipulations
    were
    presented.
    The
    highlights
    of
    said
    stipulations
    are
    as
    follows:
    14
    694

    —3—
    1.
    Continuing investigation of methods to control emiss-
    ions
    has resulted in
    a new compliance plan.
    2.
    The new compliance plan would,
    in the opinion of the
    parties, abate the particulate and SO2 emissions.
    3.
    The present drying operation in the grinding depart-
    ment will be discontinued.
    4.
    A 100 ft. by 140
    ft. structure shall be installed to
    eliminate the artificial drying method at a cost of
    $95,000.
    The parties agree that the above plan: will eliminate all slurry and
    water
    problems
    (which
    would
    be
    generated
    should
    a
    scrubber
    be
    used);
    will
    eliminate
    all
    SO2 emissions; will conserve fuel for said dryer;
    and
    be
    technically superior.
    The parties suggest compliance will be accomplished by April
    1,
    1975.
    This
    plan
    also,
    calls
    for
    the
    installation
    of
    a
    fabric
    collector
    to
    control
    emissions
    for
    the
    two
    rotary
    dryers
    in
    the
    castable
    building
    according
    to
    the
    following schedule:
    Purchase and order of equipment
    11/15/74
    Erection contract
    12/31/74
    Delivery
    4/15/75
    Completion of installation
    5/15/75
    Compliance testing
    5/30/75
    Operational
    5/30/75
    A second stipulation cites conditions which would be acceptable
    should the Board grant variance.
    To determine whether the Board should accept the above stipulation
    as the basis
    for a variance, we must explore environmental impact and
    hardship to Petitioner.
    Environmental impact:
    As mentioned above, Petitioner’s facility is loc-
    ated in a sparsely-populated area.
    The
    closest resident is 3/4 mile from
    the source,
    and the next closest resident is
    1 1/2 miles from the source
    (R.
    22).
    A major alleged source of particulate emission was shut down
    on April 11, 1974, when
    the
    Grundy facility ceased operation.
    Although
    there is no evidence as to actual emissions that emanated from this
    (Grundy) plant, Mr. Noell testified that by visual observation emissions
    were large
    CR.
    20).
    Mr. Noells further testified that to
    his
    knowledge
    he knew of no citizen complaints regarding the facility
    (R.
    20).
    It is
    the Board’s feeling that the environmental impact of Petitioner’s emiss-
    ions would be minimal.
    Hardship:
    Petitioner alleges that failure to receive a variance would
    result in a
    shutdown of
    Petitioner’s
    facilities.
    The Board again reiter-
    ates
    its
    opinion
    that
    failure
    to
    grant
    variance
    is
    not
    a
    shutdown
    order,
    but
    rather
    a
    shield
    from
    prosecution.
    The
    hardship
    then
    is
    exposure
    to
    a threat of prosecution.
    Should Petitioner’s facility be shut down, Pet-
    itioner alleges a potential loss of 88 jobs and loss of $572,000
    in
    corn—
    14
    695

    —4—
    munity income.
    Although the hardship case is minimal, in light of the
    minor environmental damage and a viable compliance plan, the Board will
    grant variance.
    The
    Board’s
    variance
    will
    be
    specifically
    limited
    to
    those
    operations
    which
    are
    covered
    by
    compliance
    plans.
    We
    have
    no
    way
    of
    knowing
    wheth-
    er a variance is required for Petitioner’s kilns, nor were we presented
    with a compliance plan should such variance be needed.
    This Opinion constitutes the findings of fact and conclusions of
    law of the Board.
    ORDER
    IT IS THE ORDER of the Pollution Control Board that:
    1.
    Variance is granted from Rules 204(f) (1) (A),
    202(b),
    and
    203(a)
    as it applies to Petitioner’s crushing house and
    grinding department until April
    1, 1975.
    2.
    Variance is granted from Rule 202(b)
    and 203(a)
    as it ap-
    plies to Petitioner’s castable building until May 30,
    1975.
    The above variances are conditioned on the following:
    1.
    Within
    50
    days from the date of this Order, Petitioner shall
    post a performance bond with the Agency at 2200 Churchill
    Road, Springfield,
    Illinois,
    62706,
    in the amount of $10,000.
    Said bond shall guarantee installation of equipment
    as de-
    tailed in the November 30,
    1974,
    Stipulation as agreed by
    both parties.
    2.
    Petitioner shall submit bi-monthly progress reports to the
    Agency at the above address.
    Such reports shall contain as
    a minimum a summary of progress made towards installation of
    the six-bay storage shed and fabric filter collector,
    as well
    as copies of all documents, purchase orders, or agreements
    pertaining to this compliance plan.
    3.
    In the event of unavoidable delay, Petitioner shall notify the
    Agency as soon as possible.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board,
    certify that the above Opinion and Order was adopted by the
    Board on the
    19th
    day of
    December
    ,
    1974, by a vote of
    4
    to
    p
    .
    .
    14
    696

    Back to top