ILLINOIS POLLUTION CONTROL BOARD
July 31, 1973
ENVIRONMENTAL PROTECTION AGENCY,
Complainant,
vs.
)
PCB 72—391
GENERAL FIRE EXTINGUISHER CORP.,
)
Respondent.
GENERAL
FIRE
EXTINGUISHER CORP.,
Petitioner,
vs.
PCB 73—199
ENVIRONMENTAL PROTECTION AGENCY,
)
Respondent.
Douglas T. Moring, Attorney for the EPA
Irving Friedman, Attorney for General Fire Extinguisher Corporation
OPINION AND ORDER OF THE BOARD
(by Mr.
Heriss)
General Fire Extinguisher Corporation manufactures fire
extinguishers in Northbrook, Illinois.
The EPA filed an enforcement
action alleging that the company had discharged contaminants into
the air in violation of Rule 3-3.111 of the Rules and Regulations
Governing the Control of Air Pollution and Section 9(a) Environ-
mental Protection Act.
The violations allegedly occurred between
July 15, 1971 and September 29,
1972.
The Agency also claimed that in June 1972
the Company installed
air pollution control equipment without first obtaining a permit
from
the
EPA.
General Fire Extinguisher filed
a petition in which they request
variance
from
Rule 3-3.111 until October 15,
1973r
the anticipated
completion date for installation of
a new emission control process.
The Agency has recommended that the variance be denied.
B
667
—2—
The enforcement and variance cases will be considered together
in this Opinion.
General Fire Extinguisher states that the manufacture of fire
extinguishers includes a charging of the casing with dry powder
and that during this process some powder ordinarily escapes to
the atmosphere.
The Company alleges that in 1968 it began experi-
menting with methods of preventing
this
loss of powder.
Control
at that time included a cyclone and some dust collectors.
The
Company determined that better results would be obtained by
enclosing this material completely within a pneumatic conveying
system rather than the use of a conventional dust collecting
system.
This approach, which the Company calls
~revolutionary”
required custom designing
(over 4000 hours of engineering time)
and involved a greater delay in bringing the system to completion.
Death of the Company Chairman in 1971 and changes in personnel
resulted in further delay.
New management apparently had problems
in funding the one-half million dollar cost of the project.
Part of the system for handling bulk quantities
of bicarbonate
of soda became operational in August 1972.
The system, when
completed,
will use six bag houses.
It is expected that the
entire system will be operational by October
15, 1973.
On June
6,
1972 the plant was inspected by an EPA surveillance
engineer.
Company officials informed the investigator that the
annual consumption of sodium bicarbonate was 2,500
tons and that
2
of its production was lost.
From this it was determined that
24.5 lbs.
per hour was lost during processing.
Of this amount
approximately
16 lbs. per hour was being collected by control
equipment or was settling to the ground.
The Agency calculated
that the plant was
then emitting 8.50 lbs.
per hour of sodium
bicarbonate to the atmosphere.
Under Rule 203(a) of Chapter
2,
Part II of the Regulation the allowable emission rate for Respondents
operation is 2.95 lbs. per hour.
The Company also presented
a process weight calculation of its
particulate emissions.
The Company calculated that it was emitting
1.5
lbs. per hour to the ambiant air and was not in violation of
the Regulation.
The defense witness who made these calculations
had used an emission factor applicable
to a plant manufacturing
sodium bicarbonate.
General Fire Extinguisher does not manufacture
sodium bicarbonate.
We believe that the Agency calculation based
upon information gained from officials of General Fire Extinguisher
i
more accurate.
We find that Respondent General Fire Extinguisher Corporation
did violate the provisions
of Rule 3-3.111 during its operation
8— 668
—3—
between July
15,
1971 and September
29,
1972.
No members of
the public appeared.
There ~s no testimony in the record
regarding the impact of these emissions upon the community.
For
past violations we will assess
a monetary penalty
in the amount
of
$1,000.
There was no proof of the alleged permit violation.
Therefore,
that portion of the Complaint which charged Respondent with in-
stalling equipment without
a permit shall be dismissed.
We see nothing to be gained by denying the variance petition.
The Agency has stated that the system which will be completed
by October
15, 1973 will effectively reduce Petitioner’s particulate
emissions to the Standard set forth in the Rule.
Under this method
control is achieved by using a vacuum system for the transport of
the powder.
From the tank cars the powder is taken by air pressure
through a pneumatic hose into
a silo.
The tankers are unloaded at
a rate of 20,000
lbs. per hour using 520 cubic feet per minute of
air.
The air is then discharged to the atmosphere through a bag
house,
This control equipment is said to have
a 99.6
efficiency.
The Agency agrees that this system will bring the Company into
compliance, however,
the Agency is also of the opinion that the
method is not revolutionary and that the Company took too much
time in putting
it into operation.
Also the Agency states that this control system does not yet
reduce emissions coming from the filling stations.
Emissions
still occur when the fire extinguishers are filled with powder
by gravity from hoppers.
These emissions are principally sodium
bicarbonate.
Some mono ammonium
phosphate and potassium bicarbonate
are
also emitted.
However,
these filling stations will be hooded
and closed with emissions going to a bag house.
When the system
Is
completed,
emissions will he about 0.24
lbs. per hour.
Total
cost will
be $400,000
to $500,000.
The Agency recommends denial of
the variance because of its
belief that the Company delayed unnecessarily in installing the
control equipment.
That is one of the factors which we consider
in imposing a $1,000 monetary penalty.
However, with both an
enforcement and variance ca~sebefore us, we see no reason to
leave open the possibility of further prosecution for emissions
of this type during this construction period.
The Agency has
had
its opportunity to present a full
case and the Company is
now
entitled to assurance that there will not be a second
prosecution
during
this
construction
period
for
emissions
which
are
ci
the
same
caliber.
Therefore,
the
variance
will
be
granted
until
October
15,
1973.
8
—
669
—4—
ORDER
It
is ordered that:
1.
Respondent General Fire Extinguisher Corporation
shall pay to the State of Illinois by September 15,
1973 the sum of $1,000 as a penalty for its past
violations of Rule 3-3.111 as found in this proceeding.
Penalty payment by certified check or money order
payable to the State of Illinois shall be made to:
Fiscal Services Division, Illinois EPA,
2200
Churchill Road,
Springfield, Illinois 62706.
2.
General Fire Extinguisher Corporation is granted
a variance from the provisions of Rule 3-3.111 of
the Rules and Regulations Governing the Control
of Air Pollution until October 15, 1973.
3.
General Fire Extinguisher Corporation shall cease
and desist from its violations of Rule 3-3.111 of
the Rules and Regulations Governing the Control of
Air Pollution on October 15, 1973.
4.
General Fire Extinguisher Corporation
is adjudged
not guilty on the charge that it installed equipment
without a permit in violation of Section
9(b)
of
the Environmental Protection Act.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Board, hereby certify the above Opinion and Order was adopted
this
J1~
day of July,
1973 by
a vote of
~/
to
C~
8
—
670