ILLINOIS POLLUTION CONTROL BOARD
    May 5,
    1993
    PRINCETON/BECK OIL
    )
    COMPANY,
    Petitioner,
    V.
    )
    PCB 93-8
    )
    (UST Fund)
    ILLINOIS ENVIRONMENTAL
    PROTECTION AGENCY,
    )
    )
    Respondent.
    DANIEL J. McFADDEN,
    VALLEY PETROLEUM EQUIPMENT MAINTENANCE CO.,
    APPEARED ON BEHALF OF PETITIONER, and
    TODD
    F. RETTIG APPEARED ON BEHALF OF RESPONDENT.
    OPINION AND ORDER OF THE BOARD
    (by J. Theodore Meyer):
    This matter
    is before the Board on a petition for review
    filed January
    8,
    1993 by Princeton/Beck Oil Company
    (Beck)pursuant to Section 22.18b(g)
    of the Environmental
    Protection Act
    (Act).
    (415 ILCS 5/22.18b(g)
    (1992).)
    Beck seeks
    review of a December
    4,
    1992 Illinois Environmental Protection
    Agency (Agency) decision disallowing some costs for which Beck
    sought reimbursement from the Underground Storage Tank
    (UST)
    Fund.
    A hearing was held on March 24,
    1993,
    in Princeton,
    Illinois.
    No members of the public attended.
    The only issue remaining in dispute is whether $1780
    in
    equipment and labor costs associated with compaction of backfill
    is reimbursable from the UST Fund.
    BACKGROUND
    Beck owns an auto truck plaza on Interstate 80 in Princeton,
    Illinois.
    On January 30,
    1992,
    Beck became aware of a release of
    petroleum.
    Beck notified the Emergency Services and Disaster
    Agency
    (ESDA)1 of that release on January 31,
    1992.
    (Exh.
    A.)2
    There are nine USTs at the site.
    Beck began corrective action on
    February 21,
    1992 by removing three of the tanks.
    As part of the
    ESDA is now known as the Emergency Management Agency.
    2
    Beck’s application for reimbursement,
    which was not
    included in the Agency record, will be indicated by “Exh.
    A”, the
    Agency Record,
    Technical File, will be indicated by “R. A”,
    and
    the Agency Record,
    Fiscal File,
    will be denoted by “R. B.”
    r~.
    U~4~~U

    2
    initial activity, Beck removed those three tanks,
    stockpiled
    contaminated soil, and placed backfill in the excavation hole
    next to a building to provide “needed support for the foundation”
    of the building.
    (R. A at 8.)
    Eventually,
    all nine tanks were
    removed.
    (Tr. at 27.)
    Beck submitted an application for
    reimbursement to the Agency, and on June 5,
    1992,
    the Agency
    determined that Beck was eligible to access the Fund, subject to
    a $10,000 deductible.
    (R. A at 73.)
    During the spring and summer of 1992 Beck submitted various
    billing forms to the Agency for reimbursement.
    On December 4,
    1992,
    the Agency
    issued its final reimbursement determination
    letter.
    (R. A at 145-148.)
    In its decision, the Agency made
    seven adjustments to the amount of reimbursement requested by
    Beck.
    Beck had requested reimbursement of $175,719.15, and the
    Agency allowed reimbursement of $155,755.15.
    (R. A at 145-148.)
    Beck then filed this appeal with the Board.
    ISSUE
    Beck originally contested all seven adjustments to its
    requested reimbursement.
    At hearing, Beck agreed not to contest
    $120 of the first adjustment of $657 due to a math error,
    and not
    to contest the third adjustment of $31 in manifesting costs.
    (Tr.
    at 5; Pet. Br.
    at 1-2.)
    In its brief, the Agency states
    that after considering the hearing testimony,
    it agrees not to
    contest adjustments 4,
    5,
    6, and $80.55 of
    2.
    (Agency Br.
    at 2.)
    The Agency then states that the remaining issue
    is adjustment
    7
    of $1780
    in equipment and labor costs associated with compaction
    of backfill.
    (Agency Br. at 2.)
    Initially, the Board notes that the Agency does not address,
    in its brief, the $537 remaining in adjustment
    1 or the $18
    remaining in adjustment
    2.
    In its brief, Beck states that “item
    2 should be $18.00.”
    (Pet.
    Br.
    at
    1.)
    Thus, the Board finds
    that Beck and the Agency agree that the amount of adjustment
    2
    should be $18, instead of $98.55,
    for an adjustment in handling
    charges.
    As to the remaining $537 of adjustment
    1,
    the Board
    construes the Agency’s statements in its brief to recede from
    contesting that $537.
    Thus, the Board’s review is limited to
    adjustment
    7:
    $1780 in equipment and labor costs associated with
    compaction of backfill.
    The Agency denied reimbursement of $1780
    in equipment and
    labor costs associated with compaction of backfill.
    The Agency
    found that those costs are not corrective action costs, and
    therefore are not reimbursable.
    The Agency stated that one of
    the eligibility requirements for accessing the UST Fund is that
    the costs incurred were corrective action costs which were
    incurred as a result of a release of petroleum from
    a UST.
    (R. A
    at 148.)
    The statutory definition of “corrective action” states
    in part:
    01 L~2-U038

    3
    “Corrective action” means an action to stop,
    minimize,
    eliminate,
    or clean up a release of petroleum or its
    effects as may be necessary or appropriate to protect
    human health and the environment.
    This includes, but
    is not limited to, release response investigation,
    mitigation of fire and safety hazards, tank removal,
    soil remediation, hydrogeological investigations,
    free
    product removal, groundwater reinediation and
    monitoring, exposure assessments, and the provision of
    alternate water supplies.
    (415 ILCS 5/22.18(e)
    (1)
    (C)
    (1992)
    .)
    Beck notes that the Agency adopted emergency rules in
    October 1992,
    stating that backfill and compaction costs are
    ineligible for reimbursement, but contends that it performed the
    work six months before those rules were adopted.
    Beck maintains
    that the Agency’s guidance manual includes placement of backfill
    material as an eligible cost,
    and argues that if placement of
    backfill material
    is reimbursable, then compaction of that
    material should also be reimbursable.
    Beck contends that
    compaction of backfill material is a mandatory construction
    practice for excavations as deep as the one in this case.
    Beck
    argues that failure to compact would endanger the structure next
    to the excavation,
    and would be hazardous to traffic as the
    material settled on its own.
    In response, the Agency argues that this issue can be
    decided by a straightforward application of the Board’s
    corrective action “formula.”
    The Agency notes that the Board has
    previously held that in order to determine whether a given
    activity is corrective action, the Board must determine whether
    the activity was intended to stop, minimize, eliminate,
    or clean
    up a release of petroleum,
    and whether the activity was of the
    type contemplated by the statutory definition,
    i.e. release
    investigation, mitigation of fire and safety hazards, tank
    removal,
    etc.
    The Agency contends that Beck’s compaction of
    backfill fails the first part of the formula.
    The Agency
    maintains that Beck’s compaction of backfill was for the sole
    purpose of shoring up the foundation of a building on the
    premises,
    and not to minimize,
    eliminate,
    or clean up a release
    of petroleum.
    The Agency states that compaction of the backfill
    at the facility did not affect,
    in any way, the amount of
    contamination at the facility, and thus argues that the
    compaction fails the first part of the corrective action formula.
    Therefore, the Agency contends that the costs associated with
    compaction are not reimbursable from the Fund.
    After
    a review of the record and the arguments of the
    parties, the Board concludes that the costs associated with
    compaction of backfill are not corrective action costs.
    The
    Agency correctly points out that determining whether costs were
    incurred as a result of corrective action is a two—step inquiry:
    n~
    ~_flr~t’)
    U
    ~
    ~
    L~U~.)

    4
    first, whether the costs were incurred as
    a result of action to
    stop, minimize, eliminate,
    or clean up a release of petroleum,
    and second, whether those costs are the result of activities such
    as tank removal,
    soil remediation, and free product removal. Both
    requirements must be met in order for costs to be reimbursed as
    corrective action.
    (Enterprise Leasing Co.
    v. Illinois
    Environmental Protection Agency
    (April
    9,
    1992),
    PCB 91-174, slip
    op.
    at
    5.)
    We do not believe that compaction of backfill, under the
    facts presented here,
    meets the first part of the test.
    Beck’s
    witness testified that the backfill was compacted to provide a
    solid foundation for a nearby building.
    (Tr. at 36.)
    The
    compaction is analogous to the replacement of concrete.
    These
    actions restore the facility to its original condition.
    While
    such restoration may be beneficial to the property owner and
    society,
    it does not stop, minimize, eliminate,
    or clean up a
    release of petroleum.
    As the Agency points out, the compaction
    of backfill at the facility did not affect the amount of
    contamination.
    The Board has previously held that in most cases
    the replacement of concrete is not corrective action, and is not
    reimbursable.
    (See,
    e.g.,
    Southern Food Park,
    Inc.
    v.
    Illinois
    Environmental Protection Agency
    (December 17,
    1992),
    PCB 92-88;
    Platolene 500,
    Inc.
    v. Illinois Environmental Protection Agency
    (May 7,
    1992), PCB 92—9.)
    The appellate court has upheld the
    Board’s finding that replacement of concrete is not corrective
    action.
    (Strube v. Illinois Pollution Control Board, No.
    3-92-
    0468,
    slip op.
    at 6—7
    (3d Dist. March 15,
    1993).)
    Because we
    find that compaction of backfill in this case is analogous to the
    replacement of concrete,
    since the compaction served to restore
    the property, we find that the compaction does not meet the first
    part of the corrective action test.
    Thus,
    those costs are not
    reimbursable.
    The Board is cognizant of Beck’s argument that although the
    Agency’s October 1992 emergency rules do not allow for recovery
    of compaction costs, the Agency’s guidance manual did allow
    recovery for backfill, and thus Beck contends that compaction
    costs should be allowed.
    However, this Board has previously held
    that the guidance manual
    is a rule which was not properly
    promulgated by the Agency pursuant to the Administrative
    Procedure Act, and that therefore the manual has no legal or
    regulatory effect in proceedings before the Board.
    (Platolene
    500,
    Inc.
    V.
    Illinois Environmental Protection Agency
    (May 7,
    1992), PCB 92—9,
    slip op.
    at
    5;
    Strube v. Illinois Environmental
    Protection Agency
    (May 21,
    1992),
    PCB 91—205, slip op.
    at 2-3.)
    The proper inquiry in determining whether an activity is
    corrective action is whether that activity meets both parts of
    the statutory definition.
    Because we have determined that
    compaction of backfill in this case does not meet that
    definition,
    the costs are reimbursable.
    0
    ~2-O0li~O

    5
    CONCLUSION
    In sum, the Board finds that $1780
    in equipment and labor
    costs for compaction of backfill are not corrective action, and
    thus are not reimbursable from the Fund.
    This opinion constitutes the Board’s findings of fact and
    conclusions
    of law.
    ORDER
    The Board hereby affirms the Agency’s December 4,
    1992
    determination that $1780
    in equipment and labor costs associated
    with the compaction of backfill are not corrective action costs,
    and thus are not reimbursable.
    The Agency has agreed not to
    contest adjustments 4,
    5,
    6, and $80.55 of adjustment
    2,
    and the
    Board has construed the Agency’s brief as receding from
    contesting $537 of adjustment
    1.
    Beck has agreed not to contest
    $120 of adjustment
    1,
    and not to contest adjustment
    3.
    This case is remanded to the Agency for disbursement of the
    additional
    $8015 amount, consistent with this opinion and order.
    This docket is closed.
    IT
    IS SO ORDERED.
    Section 41 of the Environmental Protection Act (415 ILCS
    5/41) provides for the appeal of final Board orders.
    The Rules
    of the Supreme Court of Illinois establish filing requirements.
    (But see also 35 Ill.Adm.Code 101.246 “Motions for
    Reconsideration” and Castenada v. Illinois Human Rights
    Commission
    (1989),
    132 Ill.2d
    304,
    547 N.E.2d 437; Strube
    V.
    Illinois Pollution Control Board,
    No.
    3—92—0468,
    slip op. at 4—5
    (3d Dist. March
    15,
    1993).)
    I,
    Dorothy M. Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby certify that the abçve opinion and order was
    adopted on the
    ~
    day of
    _______________,
    1993,
    by a vote
    of
    5~o
    .
    7/
    (1
    Dorothy M.
    çtthn,
    Clerk
    Illinois Pol~LutionControl Board
    0
    4~UOLI.
    I

    Back to top