ILLINOIS POLLUTION CONTROL
BOARD
December 18,
1975
ELMHURST COUNTRY CLUB,
)
Petitioner,
v.
)
PCB 75—76
ENVIRONMENTAL PROTECTION AGENCY,
)
)
Respondent.
MR. LAWRENCE X. PUSATERI, appeared on behalf of the Petitioner;
MR. JOHN T. BERNBOM, appeared on behalf of the Respondent.
OPINION AND ORDER OF THE BOARD
(by Mr.
Dumelle):
On February
T,
1975, Petitioner Elmhurst Country Club filed
with the Illinois Pollution Control Board
(Board)
a “Motion To
Re-Open” PCB 74-354.
That previous Opinion and Order of the
Board denied Petitioner’s September
30, 1974 petition for variance.
The Board, while denying Petitioner’s motion to re-open,
construed
that motion as a new petition for variance.
The Illinois Environ-
mental Protection Agency
(Agency)
filed its recommendation on
March 10,
1975.
A hearing was held on April
2,
1975.
More than seven months elapsed between the hearing date in April
and the time Petitioner delivered copies of the transcript to the
Board on November
12,
1975.
Petitioner had filed a waiver of the right
to a decision within 90-day
(that right had already been waived by
operation of Rule 410 of the Board’s Procedural Rules).
Petitioner
has not explained this extraordinary delay in presenting copies
of the transcript to the Board.
Such delay causes the Board
to seriously question the presence of good faith on the part of
Petitioner.
The net effect of the extraordinary delay has been to
prevent this Board from rendering its decision until almost the
time that Petitioner has stated as the latest possible date of
compliance, and four months after the anticipated compliance
date.
The Board is thus asked to render a decision on Petitioner’s
variance request more than eight months after the hearing.
The
Board is asked to grant this variance without any information
whatsoever as to the progress of’Petitioner’s alleged efforts
to control its discharges into Salt Creek, and its alleged
efforts
to construct a sewer connection to the Addison Sewage
19
-
474
—2—
Treatment Plant.
Petitioner was to have completed these projects
by mid—summer of 1975.
It is now winter.
The Board has received
no information on these projects since the testimony given on
April 2,
1975.
The Board’s Procedural Rule 410 clearly states
it is Petitioner’s
responsibility to furnish the Board with transcripts within 15 days
of the hearings.
Given the unexplained
7 month delay, Petiti~ner
should have at the very least submitted an explanation of
both the delay and its progress towards compliance.
The Board finds that, due to Petitioner’s unreasonable delay,
it is faced with a situation analagous to mootness.
The Board
has no way of knowing whether Petitioner has been acting in
good faith in its compliance program for these past eight months.
Normally, if such a variance were granted the Board would impose
conditions on Petitioner regarding the operation of its waste
treatment system and a timetable for the completion of various
stages of construction and modification.
Here the Board has no
way to determine whether or not such conditions would be moot.
The unreasonable seven month delay, being unexplained by
Petitioner, places upon Petitioner the additional burden of
setting forth the details of its alleged compliance efforts. for
the period of the delay.
Therefore, the Board finds that Petitioner
has failed to present facts sufficient to support its petition
for variance.
This Opinion constitutes the Board’s findings of fact and
conclusions of law.
Mr.
Young abstains.
ORDER
The Board hereby denies the Petition for Variance.
IT IS SO ORDERED.
I, Christan L.
Moffett, Clerk of the Illinois Pollution Control
Board,
hereby certify the above Opinion and Order were adopted on the
~
day of December,
1975 by a vote of
.3-~
Illinois Pollution
trol Board
19
-
475