ILLINOIS POLLUTION CONTROL BOARD
October
3,
1972
ENVIRONMENTAL PROTECTION AGENCY
V.
)
#71—338
CPC INTERNATIONAL,
INC.
Mr.
Prescott E. Bloom,
Special Assistant Attorney General for
Environmentai Protection Agency;
Mr. James W. Gladden, Jr.,
for
CPC International,
Inc.
Opinion of the Board
(by Mr. Currie)
The Agency’s complaint charges CPC with various violations
of regulations and statutes
in regard to emissions of air
contaminants from its corn processing plant in Pekin.
We find,
among other things, that during 1971 CPC by its own testimony
violated applicable standards governing the emission of particulate
matter from its boiler C and enter a remedial order,
as more
fully described below.
The complaint was in two counts:
violation of particulate
emission standards by coal—fired boilers and statutory air
pollution
(which consists of interference with the comfort,
health,
or property of other persons)
(Environmental Protection Act,
p9(a)) ,as a result of emissions from the boilers, from wastewater
treatment facilities, and from the corn milling processes them-
selves.
CPC denied any violations and raised several legal de-
fenses, which we reject.
The standard arguments are made that the air pollution
standard is vague and that the Board cannot
constitutionally be
given power to impose money penalties; we have rejected these
before.
EPA v. Granite City Steel Co.,
#70-34
(March 17,
1971);
EPA v.
Modern Plating Corp., #71-38 (April 14,
1971).
CPC argues
that because it was following an approved Air Contaminant Emission
Program
(ACERP)
it cannot be held in violation of ~he law under
Rule 2-2.41 of the Air Pollution Control Board rules, but the
principal violation we find is not the violation the program was
seeking to correct.
We agree that an approved ACER? was the equivalent
of
a variance excusing the emissions covered by the program while
the company goes about correcting
them,
see EPA v. Commonwealth
5
—
541
—2—
Edison Co.,
#70-4
(Feb.
17,
1971).
But the existence of an ACERP
cannot excuse excessive emissions
from equipment that was claimed
to be in
compliance in 1967 and for that reason excluded from the program.
It is urged that compliance with the numerical standard for corn
wet milling dusts
is
a complete defense against an air pollution
complaint concerning
them.
As we held in the Granite City Steel
case,
supra,
the statute makes compliance with numerical standards
only a prima facie defense, not a complete one;
the regulations
cannot repeal the statute by authorizing the creation of an
active nuisance.
See also our opinion in In
the
Matter of
Emission
Standards,
#R7l-23
(April 13,
1972)
.
The suggestion that
more stringent standards where required by more severe adverse
effects violate the equal protection clause refutes itself;
see,
in addition to the opinion in #R71-23, supra, that in In the
Matter of Effluent Standards,
#R 70-8
(Jan.
6,
1972).
We find no
fault with the complaint itself;
it adequately informs CPC of the
charges it must defend, and it has done so with vigor.
As we held
in EPA v.
Iowa—Illinois Gas
& Electric Co.,
#72—216
(July 25L
1972)
,
the statute of limitation in Ill.
Rev.
Stat.
ch.
83,
~ 15
is inapplicable to complaints by government agencies.
As for
the 18-month limitation of
ch.
38,
§
3-5, that is a part of the
Criminal Code applicable only to criminal prosecutions;
it has
been held inapplicable,
in the only analogous case we have found,
to a debt action for a penalty for violation of a municipal ordin-
ance.
City of Chicago
v.
Enright,
27
Ill. App.
589
(1889).
The
present proceeding
is administrative,
not criminal.
In any case,
the principal violation we find took place during the year 1971,
all of which was within 18 months prior to the filing of this
complaint.
The record contains no evidence as
to the alleged problem
with the wastewater treatment facilities.
When the Agency attempted
to elicit testimony as
to odors in the vicinity of CPC’s plant,
the company’s objection was sustained on the ground that the
Agency had said nothing about odors in answering interrogatories
seeking information
as to what the Agency would seek to prove
(R.
30—32).
We sustain the hearing officer’s ruling; CPC was
entitled to adequate notice as to what it had to defend against.
Cf. EPA v. Commonwealth Edison Co., supra.
The only evidence as
to air pollution from corn milling equipment concerned isolated
incidents,
conceded by CPC,
in which extraordinary conditions caused
nuisance deposits of corn material (gluten)
on neighboring property.
(R. 66—69,
154,
200,
360—61).
That these incidents constituted
air pollution we have no doubt,
as there was uncontradicted evidence
they interfered with the neighbors’
comfort.
See EPA v. General
Iron Industries, Inc.,
#71—297
(March
7,
1972).
We think it
sufficient, given the sporadic and apparently accidental nature of
these events and the rather minor harm they caused, to require the
company to exercise all reasonable care to prevent such incidents
in the future.
5
—
542
—3—
The important question in this case concerns boiler
emissions.
CPC has three boilers; the evidence is clear that
boilers A and B have been brought into compliance in conformance
with the company’s ACER? and that there is no cause for imposing
any penalties on their account
(R. 126—27,
214—15; CPC Exs.
10,
12).
It is Boiler C that isin serious dispute.
Boiler
C
is and has been since the 1950’s equipped with
mechanical particulate collection devices of the multiclone
variety
(R.
313).
The company submitted emission estimates in
connection with its compliance program indicating that it believed
Boiler
C already met the applicable standard of 0.6 pounds of
particulates for each million btu of heat input
(CPC Exs.
6,
8,
10)
.
The Agency questioned the company’s assumption that the cyclones
removed 90.8
of the particulate matter
(CPC Ex.
15); CPC res-
ponded by determining the particle size distribution of the
boiler emissions and referring to a manufacturer’s graph that
predicted collection efficiencies of 92.5
with the size
distribution it had measured
(CPC Ex.
16).
Computing probable
emissions on the
basis of the ash content and heating value of
the coal used at the time and using the 90.8
collection figure,
CPC concluded that Boiler C’s emissions were just about what the
standard required
(0.6056 lb/mbtu) and therefore that it need not
take further action to achieve compliance with the boiler
(CPC
Ex.
10).
EPA’s case is based upon citizen evidence that CPC’s
boilers are or have been causing annoying dust or soot de-
posits on neighboring property
(R.
29,
72-73, 88-90, 154—56,
166-68,
177),
which we find to be the case,
and upon the Agency’s
own estimates of Boiler C’s emissions.
The Agency rejects the
92,5
estimate of efficiency on the basis of standard publications
and long-standing EPA guidelines suggesting an upper limit in
installations such as this one of
83
(R.
111,
122—25)
.
Using
a 75
efficiency factor,
EPA calculated estimated emissions of
2.08 lb/mbtu when burning coal such as was consumed in 1971
(CPC Exs.
2,
3)
.
Since on EPA’s assumption
as to efficiency 25
of the particulate is uncollected and on CPC’s only 7.5,
the
reason for the great discrepancy in estimates is apparent.
As we have held from the beginning,
estimates of emissions
based upon standard emission and efficiency factors determined
from experience with similar facilities are accept.able,
in the
absence of more specific information,
to prove compliance or
violation.
EPA v. Lindgren Foundry Co.,
#70-1
(Sept.
25, 1970).
We have also made clear that such estimates are subject to re-
buttal on the basis of more specific information.
EPA v. Norfolk
&
Western Ry., #70-41
(May
26, 1971).
In the present case EPA’s
generalized efficiency estimate, drawn from recognized authorities,
was sought to be rebutted by
a particle size test and its application
to a performance chart supplied by the equipment manufacturer
(CPC Exs.
16,
39;
R.
293—97).
There
is
nothing in the record
5
—
543
—4—
to substantiate the manufacturer’s chart; what it is based upon
~cedo not know.
If this were the only rebuttal information in
the record, we should be hesitant to find it adequate.
Cf.
ommonwealth Edison Co.
v.
EPA,
#72-150
(Aug.
8,
1972).
We should
be inclined
to ask for proof that the chart represented actual
experience rather than mere expectations or manufacturer’s claims.
The best evidence as to actual emissions
is an actual stack
test,
and one was taken very recently, showing emissions of
2.53 lb/mbtu under present operating conditions
(R,
277-89).
Working backward from the test result and from the ash and heat-
ing values of the coal used in the test
(see CPC Ex.
40.
R.
292-93)
~e conclude that the test tends to confirm a cyclone efficiency,
now,
in the range of 90.
More importantly,
since the Agency did not
significantly shake the accuracy of the test on cross-examination,
the test establishes to our satisfaction that Boiler C was in
compliance with the emission standard on the date of the test.
:?c
acknowledged that possible turbulence at the point where the
samele was taken could distort the sample and testified that
standard precautions were taken, by increasing the number of samples
taken,
to compensate by obtaining
a complete cross section
(R.
31—22,
337)
That Boiler C complied as of the date of the test does not
excuse any past violations that may have occurred.
CPC acknow-
edges that in the fall of 1971 it inspected the cyclones, found
holes
in several of them,
and repaired them
(R.
353-54; CPC Ex.
44).
~:oevidence is given to enable us to determine that nothing could
have been done earlier to correct this condition.
It is thus clear
from CPC’s own evidence that during at least part of 1971 the
collector was not operating at the efficiency concededly necessary
to assure compliance, which the test and CPC’s original estimates
both show was barely acheived at optimal efficiency.
We must there-
fore direct CPC to take every precaution
in the future to inspect
the cyclones and to maintain them atamaximurn efficiency.
We do
tot rely on the deterioration of the cyclones in assessing penalties,
because the evidence as to fault in this regard
is unclear, and
because there
is another and much more unmistakable reason for
tenalties which we deem sufficient
in itself.
CPC’s original conclusion that Boiler
C was in compliance
xas based upon the use of coal with an ash content of 8.3
(as
fired) (CPC Exs.
6,
7,
8,
10)
.
Well knowing from its own
calculations that continued compliance depended upon using coal
of
a relatively low ash content, CPC in “early 1971”
(R.
355) by
~ts own evidence purchased and burned in Boiler C coal containing
~
ash
(as fired) (CPC Ex.
2), almost 20
more than that on
whIch hare compliance depended.
According to standard equations
accerted by both parties
(EPA Ex.
20;
R.
114),
the amountof
5
—
544
--5—
particulate matter to be collected is, other factors being equal,
closely proportional to the ash content of the coal.
By increasing
the ash content, CPC increased its emissions correspondingly;
and
even CPC’s own calculations, based on 92.5
efficiency, which is
better than the later test showed, reveal emissions
in 1971
(0.626 lb/mbtu
(CPC Ex.
41)
in excess of the standard.
Belatedly recognizing the problem about November,
1971, CPC
has switched to low—ash coal
(6.6
as fired) (R.
355; CPC Exs.
40,
45-46), and the stack test indicates that Boiler
C will comply
so
long as it
is properly maintained and low-ash coal
is used.
We
shall
so order.
We must also impose money penalties
for the
company’s serious neglect of
its recognized responsibilities.
It
is not enough to equip a boiler with adequate collection equip-
ment;
the boiler must also be operated so as to assure compliance.
It was CPC’s duty
to burn coal sufficiently low in ash to fulfill
the promise of its estimates.
There can be no plea of lack of
knowledge,
since CPC’s own ACER? revealed it knew compliance
could be achieved only by burning low-ash coal.
The harm done by this violation cannot be accurately assessed.
CPC’s boilers have interfered with the neighbors, but we cannot
say how much this was due to Boiler C when it was out of com-
pliance, how much due to Boilers A and B before they were con-
trolled
(see
R.
224)
,
and how much due to emissions permitted by the
old regulations under which this case was brought.
For the future
we think it adequate to warn CPC that more stringent emission
standards must be met in the next couple of years under our new
regulations, and that the date for filing a control program is not
far off.
See PCB Regs,
Ch.
2.
But the penalty question must be
determined largely in terms of the degree of fault displayed by
the company and in terms of the significant amounts of money
CPC saved by burning inferior coal to the detriment of its neighbors.
We think the complete inattention to this question,
in light of
the
clear warning in CPC’s own ACERP documents,
is serious indeed.
We note that CPC testified that low—ash coal such as is now being
used
is costing it an extra $12,000 per month above its former
fuel costs
(R.
356).
Given that the violation and consequent saving
extended over many months of 1971, we could easily justify a penalty
of $50,000 or more
to assure that the company did not profit by
overlooking its obligations to the public.
But because this
is
a first offense, because there is no suggestion it was deliberate,
because no catastrophic pollution resulted, and because of the
commendable attitude of CPC in correcting the problem once it
recognized what was happening, we limit the penalty to $15,000.1
This opinion constitutes
the Board’s findings of fact and
conclusion of law.
1.
After the hearing the Agency moved to amend its complaint by adding a
charge that CPC improperly suppressed
information as to the actual efficiency
of the Boiler C cyclone.
CPC objected on grounds of lack of opportunity to
defend.
Since we find the later stack test the best evidence of actual per-
formance and impose penalties for the admitted use of high-ash coal,
we think
nothing significant
is added by the proposed amendment and deny the motion to
amend, without prejudice to the filing~ such future complaints as EPA may
choose to file.
5
—
545
—6—
ORDER
1.
CPC
shall
take
all
reasonable
precautions
to
prevent
further
incidents
involving
the
deposit
of
gluten
material
on
neighboring
property.
2.
CPC
shall
maintain
in
satisfactory
operating
condition
the
cyclone
collection
devices
on
Boiler
C,
shall
burn
in
Boiler
C
coal
of
sufficiently
low
ash
content
and
high
heating
value as to assure compliance with applicable regulations, and
shall cease
and
desist from emissions fran Boiler C in excess of
0.6 lb/mbtu.
3.
Within 35 days after receipt of this order,
CPC
shall
pay
to the
State
of Illinois, in penalty for the violations
found in the Board’s opinion, the sum of $15,000.
Payment
shall be by check payable to Fiscal Services Division,
Environmental Protection Agency,
2200
Churchill
Road, Springfield,
Illinois 62706.
I, Christen Moffett, Clerk of the Pollution Control Board, certify
that
the
Board
adopted
the
abo!e
Opinion
this
~‘
day of
September,
1972
by
a
vote
of
~
(-‘A,c’~.C:’-’
~‘4hcjrt’
5— 546