ORDER OF THE BOARD (by C.A. Manning):
This order vacates the December 7, 2000 order, which granted an extension of time to
file a permit appeal to January 25, 2001. On December 28, 2000, IBP, Inc. (IBP) filed a
motion for clarification of the December 7, 2000 order.
The parties agreed to extend the normal 35-day appeal period for a period of 90 days to
and including March 1, 2001, which is the 125th day following the Illinois Environmental
Protection Agency’s (Agency) permit issuance on October 27, 2000.
On December 7, 2000, the Board issued its order granting an extension of the time to
file a permit appeal to January 25, 2001, which is a total of 90 days following the Agency’s
permit action.
In this case, IBP and the Agency agreed to an extension for 90 days to and including
the 125th day following the Agency’s permit action, that is, March 1, 2001. Given that
agreement, the Board vacates its December 7, 2000 order and grants an extension of the time
to file a permit appeal to March 1, 2001.
The Board will dismiss this matter and close the docket if petitioner fails to file an
appeal on or before that date.
IT IS SO ORDERED.
2
I, Dorothy M. Gunn, Clerk of the Illinois Pollution Control Board, hereby certify that
the above order was adopted on the 18th day of January 2001 by a vote of 7-0.