ILLINOIS POLLUTION CONTROL BOARD
    January 30, 1973
    ENVIRONMENTAL PROTECTION AGENCY
    #72—163
    v.
    VILLAGE OF BEECHER
    HERMAN
    R.
    TAVINS, ASSISTANT ATTORNEY GENERAL, APPEARED ON BEHALF
    OF ENVIRONMENTAL PROTECTION AGENCY
    GEORGE M. BUTTELL, APPEARED ON BEHALF OF VILLAGE OF BEECHER
    OPINION AND ORDER OF THE BOARD
    (BY SAMUEL T.
    LAWTON,
    JR.):
    Complaint was filed against the Village of Beecher alleging
    violations of Section
    18 of the Environmental Protection Act and
    Rule 3.13
    of the Public Water Supply Systems Rules and Regulations,
    in the conduct of the Village’s public water supply facilities.
    Specifically, the Village was charged with failure to provide clean
    water in adequate quantities and of satisfactory mineral character,
    and has failed to provide adequate treatment for.excessive iron
    content contained in the water.
    The Village has stipulated that
    the iron content exceeds the applicable limit of
    .3 ppm.
    Hearing was held on the complaint on September 21, 1972 and
    continued to December 14,
    1972,. in order
    to enable Respondent
    to
    make engineering studies to correct the deficiencies noted.
    At
    the December 14,
    1972 hearing,
    a report from the engineering firm
    of
    R.
    W. Robinson
    &
    Associates was submitted into evidence
    (Respon—
    dent’s Exhibit
    2)
    setting forth four alternative methods for reducing
    the
    iron content of the water.
    The Village represented that it would
    determine which alternative method would be adopted by the Village.
    The case presents no issue of fact nor are we advised at this
    point
    which method proposed has been accepted by the Village.
    Respondent’s Exhibit
    2 sets
    forth that the present water supply and
    storage facilities of
    the Village consist of two wells and
    pumps
    rated at approximately 375 gallons per minute each and a 100,000
    gallon elevated tank.
    Water consumption is based on a population
    of 1,800, which on the basis of maximum daily use of 150 gallons
    per person per day would equal 270,000 gallons.
    The pumping equipment
    is adequate to provide well in excess of this estimate.
    The report continues as follows:
    6—641

    “To bring the iron content of the water to the permissible
    standard as established by the E.
    P.
    A. we recommend the in-
    stallation of
    iron removal equipment at the water source,
    the
    wells.
    If it
    is decided to install iron removal equipment,
    then
    one of the following projects should be undertaken.
    A.
    Treatment of one of the wells using the existing
    well room
    to house the equipment.
    B.
    Treatment of both wells using the existing well
    room and part of the fire department building to
    house the equipment.
    C.
    Treatment of one or both wells
    and.
    housing the
    equipment in a new building.
    D.
    Drilling a new well and constructing a new treat-
    ment plant at the site.
    The following are our comments and approximate construc-
    tion cost estimates,
    including engineering fees,
    for the
    projects outlined above.
    Project
    “A” would involve the installation of four
    (4)
    6’-6” diameter iron removal filters in the existing well
    room of the municipal building including necessary piping
    revisions,
    new reinforced concrete floor and electrical work.
    The estimated cost for this project
    is $82,500.00.
    Project
    “B” would involve approximately twice the con-
    struction plus additional piping as outlined in
    “A” and is
    estimated to cost approximately $170,000.00.
    However, the
    entire truck bay adjacent to the well room would have to be
    utilized.
    Project “C” would require the purchase of property
    near the wells and the construction of
    a building to house
    the equipment.
    Depending on whether one or both wells are to
    be treated the cost estimate is between $110,000.00 and
    $230,000.00 which does not include the cost of property.
    Project
    “D” involves the drilling of a new well
    (800
    to 1,000 gallon per minute capacity)
    and construction of a
    treatment plant.
    This project would cost approximately
    $300,000.00 plus
    the cost of purchasing property.
    You will note the least expensive project would be to
    treat the water from one well and house the equipment in the
    existing well room.
    B
    642

    This project would treat approximately twice the
    maximum days use as we outlined earlier in this report.
    The other well would be utilized if the demand on the
    system required it but the water would by-pass the
    filters.”
    On the present State of the record, we do not believe it
    incumbent
    upon the Board
    to direct which alternative the Village
    should pursue.
    We are only concerned with compliance with the
    relevant regulations and, accordingly, order the Village to take
    immediate steps to bring their water facility into compliance.
    We
    will direct that the Village select which program it intends to
    pursue and obtain the requisite permits from the Agency by May 1,
    1973, and further direct that the Village he in conpiiance with all
    statutory and regulatory provisions with respect to the operation
    of a public water facility by Novertiber
    1,
    1973.
    On the state of
    the record,
    the imposition of a penalty does not appear warranted.
    This opinion constitutes
    the findings
    of fact and conclusions
    of law of the Board.
    IT IS
    THE
    ORDER of the Pollution Control Board the the Village
    of Beecher shall apply for and obtain the requisite permits from the
    Environmental Protection Agency for construction of its public water
    supply facility by May
    1,
    1973,
    and shall be in full compliance with
    all statute and regulatory provisions with respect to the conduct
    and operation of a public water supply facility by November
    1,
    1973.
    Reports on the progress of its compliance program shall be made monthly
    to the Environmental Protection Agency,
    the first to be filed no later
    than June
    1,
    1973.
    I, Christan Moffett,
    Clerk of the Illinois Pollution Control Board,
    certify that the above Opinion and Order was adopted on the dc~’4’~
    day of January,
    1973,
    by
    a vote of
    ~3
    to
    ~
    —3—
    6
    643

    Back to top