    ORDER OF THE BOARD:
    By order of April 13,
    1995, pursuant to P.A. 88-690, the
    Board granted Meyer Steel Drum,
    Inc.
    (Meyer)
    an extension of time
    through July 10,
    1995 in which to file an appeal of a March
    7,
    1995 Agency permit determination.
    On July 10,
    1995, Meyer filed
    a petition for permit review regarding its facility, located at
    3201 West Millard,
    Chicago, Cook County,
    Illinois.
    This matter
    is accepted for hearing.
    The hearing must be scheduled and completed in a timely
    manner, consistent with Board practices and the applicable
    statutory decision deadline,
    or the decision deadline as extended
    by a waiver (petitioner may file a waiver of the statutory
    decision deadline pursuant to 35 Ill.
    Adiu. Code 101.105).
    The
    Board will assign a hearing officer to conduct hearings
    consistent with this order, and the Clerk of the Board shall
    promptly issue appropriate directions to that assigned hearing
    officer.
    The assigned hearing officer shall inform the Clerk of the
    Board of the time and location of the hearing at least 40 days in
    advance of hearing so that public notice of hearing may be
    published.
    After hearing, the hearing officer shall submit an
    exhibit list,
    a statement regarding credibility of witnesses and
    all actual exhibits to the Board within five days of the hearing.
    Any briefing schedule shall provide for final filings as
    expeditiously as possible and,
    in time—limited cases, no later
    than 30 days prior to the decision due date, which is the final
    regularly scheduled Board meeting date on or before the statutory
    or deferred decision deadline.
    Absent any future waivers of the
    decision deadline, the statutory decision deadline is now
    November 7,
    1995
    (120 days from July 10,
    1995); the Board meeting
    immediately preceding the due date is scheduled for November 2,
    1995.
    If after appropriate consultation with the parties, the
    parties fail to provide an acceptable hearing date or
    if after an
    attempt the hearing officer is unable to consult with the

    2
    parties,
    the hearing officer shall unilaterally set a hearing
    date in conformance with the schedule above.
    The hearing officer
    and the parties are encouraged to expedite this proceeding as
    much as possible.
    The Board notes that Board rules
    (35 Ill. Adm.
    Code 105.102) reauire the Agency to file the entire Agency record
    of the permit application within 14 days of notice of the
    petition.
    This order will not appear in the Board’s opinion volumes.
    IT IS SO ORDERED.
    I, Dorothy M. Gunn,
    Clerk of the Illinois Pollution Control
    Board, hereby ce tify that the above order was adopted on the
    ____
    day of
    __________________
    ,
    1995, by a vote of
    _________
    Control Board

    Back to top