ILLINOIS POLLUTION CONTROL
BOAPJJ
March
26,
1975
EARLY AND DANIEL COMPANY,
Petitioner,
v.
)
PCB 74—368
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
Mr.
Robert
W.
Thomson,
attorney
for
Petitioner.
Mr~William A.
Erdman,
attorney
for Respondent.
OPINION AND ORDER OF THE BOARD
(by Dr.
Odell)
On May 9,
1974,
in Environmental
Protection Agency v.
E~1
md Daniel
Compan1
PCB
73-454,
12 PCB
237
(May
9,
1974),
the Illinois Pollution Control Board
(Board)
ruled that Early
and Daniel Company
had violated Section
9(a)
of the Illinois
Environmental Protection Act
(Act).
In that Order, the Board
gave Early and Daniel until October
1,
1974,
to install equip-
ment to control emissions from its truck dump and railroad load—
out area at its grain elevator in Sheldon, Illinois.
On
September
30,
1974, Petitioner sought a variance from the October
1,
1974,
Board deadline
for
installation
of control equipment for
the truck dump and railroad load-out areaas
set out in Orders
:3(a)
and 3(b)
of the May
9,
1974, Opinion and Order.
On October
10, the Illinois
Environmental Protection Agency
(Agency)
filed
a Motion To Dismiss because the Petition for Variance lacked
necessary information.
The Board, on October
17, ordered
Petitioner
to supply additional information on its variance re-
quest.
On October
18,
1974,
the Board received from Petitioner
a Motion to Modify Order and supporting information which
re-
quested that the dates in subparagraphs 3(a)
and 3(b)
of our
May 9,
1974, Order in PCB 73-454 be changed from “October
1,
1974”
to “December 1,
1974,
or such other dates as the Board shall deem
appropriate.”
We considered this to be an amended petition for
variance.
Citizen complaints mandated the Board on December 5,
1974, to order that
a hearing be held.
Petitioner’s motions to
dispose of the Petition for Variance without hearing were denied
on January
3,
1975.
The hearing was held on January 29, 1975,
in Watseka,
Illinois.
Final Board action was later waived until April 15,
1975.
The testimony established that delays in installing the
equipment to control emissions from the truck dump and load—out
area were beyond the control of Petitioner
(R.82)
.
Supplier’s
delivery of improperly fabricated equipment delayed installation
(R.90).
The control equipment was completely installed by
December 15, 1974
(R.
39,
63,
82,
104).
Three citizen witnesses
16 —195
—2—
testified and stated that although they were still bothered by
emissions,
the situation had improved from what it was a year
ago
(R.
18 to 31).
To show good faith, Petitioner established
that equipment required to be installed by October
1,
1975, was
installed by December 15,
1974
(R.
83).
Good housekeeping
practices are being observed at the facility
(R.
57).
The Agency filed an Agency Summation on March
11,
1975,
and recommended that the variance be granted from October
1 to
December 15,
1974.
We grant the variance.
Petitioner has made good faith
efforts to achieve compliance and the delay in the installation
of control equipment was not self—imposed.
Based on the facts
of this case,
to deny the variance would impose an unreasonable
hardship on
the Petitioner.
ORDER
A Variance is hereby granted
to the Early and Daniel
Company for the period of October
1,
1974,
until December 15,
1974,
from the provisions’ of subparagraphs 3 (a)
and
3 (b)
of the Board
Order of May 9,
1974,
in PCB 73-454.
IT IS SO ORDERED.
I, Christan
L. Moffett, Clerk of
the Illinois Pollution Control
Board, hereby certify that the above Opinion and Order was adopted
on the
~t~\day
of
______________,
1975, by
a vote of
-~
to
c.~.
ãhiistan
L. M~ffett
16
—
196