ILLINOIS POLLUTION CONTROL BOARD
October
 28,
 1971
FREEMAN
 COAL
COMPANY
#71—78
V.
ENVIRONMENTAL
 PROTECTION
 AGENCY
MR.
 RICHARD
 ELLEDGE,
 ATTORNEY
 FOR
 PETITIONER,
 FREEMAN
 COAL
 COMPANY
MR.
 JOHN
 EcCREERY,
 ATTORNEY
 FOR
 ENVIRONMENTAL
 PROTECTION
 AGENCY
OPINION
 OF
 THE
 BOARD
 (BY
 MR.
 DUMELLE)
Petitioner, Freeman Coal Company
 (“Freeman”)
,
 seeks ~ variance
to
 continue
 operating
 a
 coal
 processing
 plant
 at
 its
 Orient
 #3
 Mine
near
 Waltonville,
 Illinois,
 in
 violation
 of
 Rule
 3—3.111
 of
 the
Rules
 and
 Reculations
 Governino
 the
 Control
 of
 Air
 Pollution.
 This
~ine
 r:coduces
 3
 million
 tons
 of
 low
 sulphur
 coal
 annually
 (20
 of
 the
Illinois
 total)
 emplcp~s 630
 rersons
 and
 has
 an
 annual
 payroll
 in
of
 $5,000,000.00.
Each
 of
 four
 air
 cleaning
 tables
 in
 the
 mine
 s
 processing
 plant
oorts
 an
 estimated
 110
 pounds
 of
 particulate
 matter
 per
 hour
 (R,287)
The
 allowable
 limit
 is
 46,3
 pounds
 per
 hour
 from
 each
 table.
 In
 April
of
 1971, Freeman
 shut
 down
 three
 air
 tables
 and
 a
 heat
 drier
 which
 had
beer.
 emission
 sources
 of
 an
 estimated
 420
 pounds
 of
 particulate
 per
The processing olant separates
 12,000
 tons
 of
 raw
 coal
 daily
 into
~:m~nus
 7/16””
 (“fine coal”)
 and
 “plus
 7/16””
.
 60
 of the
 coal is~
se~
orated
 and
 is
 cleaned of
 impurities
 by
 using
 wet
 methods
 which
 pose
00
 emission
 ~rohlan.
 40
 of
 the coal
 (“fine
 coal”)
 is
 separated
 and
ciean~d
by
 confine
 it
 across
 fluidized air
 beds
 which
 are the subject
at
 this variance oroceecing.
 Freeman proposes
 to
 replace thas methon
cicaniric
 the “f~aecoal”
 witir
 a new facility emoioyinp
 a
 wet
 crocess,
which will include flotation
 and
 heavy
 media cyclones,
 and
 a
 new
 drier
controlled
 by
 a
 hich
 enerov
 wet
 scrubber
 (R.242—246)
,
 and which will
briny
 the
 olant
 into
 comoliance
 with
 the Regulations.
 Freeman states
that
 at:
 will
 require
 18
 to
 20
 months
 for
 installation
 of
 this plant.
Tar
 the
 follc-einc reasons and subject
 to several conditions,
 we
crane
 a
 variance
 to
 operate the
 four air cleaning tables for one year.
The
 Environmental
 Protection
 Agency
 (Agency
 Recommendation
asks
 that
 we
 deny
 the
 variance,
 or,
 in
 the
 alternative,
 that
 we grant
it with
 the requirement that Freeman pay
 a penalty and begin immediate
installation of facilities and equipment necessary for compliance~
The Agency further attempted
 to show that Freeman could feasibly cur-
sue several interim steps designed to reduce the emissions from the
processing plant pending completion of the new facility.
With
 the exception of the penalty, we
 find no merit in the
Recommendation.
 The Agency failed to establish that construction of
the new facility could be done more quickly than 18 to
 20 months.
Petitioner satisfactorily rejected each of several suggestions
 for
interim control measures.
 Free~iancannot sell
 the
 minus
 7/16” coal
in
 an
 uncleaned
 state;
 the
 raw
 coal
 has
 too
 high
 an ash content and
no market for it exists
 (R.9,
 15 and
 17)
.
 The company cannot stock-
pile 40
 of
 its production to be cleaned when
 the new facility
has been
 completed
 because
 space
 is unavailable and
 because
 stock-
piling
 in any event poses
 a fire hazard
 (R.32-35,
 73)
.
 Nor
 can
Freeman ship coal from Orient
 #3 Mine to
 a recently completed pro-
cessing plant at Orient
 #6 Mine,
 several miles
 away,
 in order for
such coal to be cleaned there pending completion
 of the new plant at
Orient
 #3
 Mine.
 Facilities
 do not exist
 for shipping coal
 in such
amounts or
 for receiving
 and processing
 it at Orient
 #6
 (P.90-91)
Finally,
 the Agency has failed to lend substance to its Recommen-
dation that we
 deny
 the variance petition.
 Freeman has established
on
 the
 one
 hand
 that
 it
 will
 need
 considerable
 time
 for
 construction
of
 the
 new
 plant
 and
 that
 to
 deny
 the
 variance
 would
 pose
 a
 severe
economic hardship for63O e:aployees who would have
 to be
 laid
 off
for
 eighteen
 to
 twenty
 months,
 and
 would
 deprive
 Freembn
 customers
of
 much needed low sulphur coal.
On
 the
 other
 hand,
 Freeman
 has
 demonstrated
 that
 there
 is
 only
 a
slight
 public
 nuisance
 from
 the
 plant~s
 emissions
 at
 present
 (oer~
haps reduced by as
 much
 as
 54
 by
 the
 recent
 shut-down
 of
 three
air tables
 (P.193,
 194,
 232,
 235)
.
 Air cjualitv data compiled
by
Freeman shows air
 in
 the vicinity of the niant
 to be in concliance
with
 National
 Primary
 and
 Secondary
 Ambient
 Air
 Quality
 Staniards
(P.334)
.
 The
 Agency
 failed
 to
 produce
 any
 local
 complainant,
 and
no
 public
 testimony
 in
 protest
 of
 granting
 the
 variance
 was
 heard
(the
 possibility
 that,
 as
 one
 witness
 testified,
 the
 emissions
 from
the
 plant
 may
 be
 inadvertently
 recirculated
 by
 draft
 fans
 into
 the
mine,
 thus
 affecting
 mine
 air
 quality,is
 a
 consideration
 of
 industria
hygiene
 beyond
 our
 jurisdiction
 absent
 a
 shnwing
 that
 “in-~c1ant”
 air
contaminates
 the
 amth ant
 air)
In
 light
 of
 the
 company~s
 voluntary
 54
 reduction
 in
 processing
operations,
 the
 absence
 of
 any
 significant
 showing
 of public
 harm
and the economic burden
 imposed upon many workers by
 a
 plant
 lay—oil
are adequate reasons
 for
 granting
 this
 variance.
But Freeman failed
 to submit
 an Air Contaminant Emission
Reduction Program
 (Acerp)
 as required by law in 1968.
 The timely
submission
 of an Acerp could have
 led to closer scrutiny of Free—
manes efforts
 to control
 its emission problem, would have put
Freeman
 under
 a specific compliance deadline
 (which not unreason-
ably could have been considerably sooner)
,
 and conceivably
 could
nave resulted in an outright denial of
 a request for more time
 (as
what
 the company wants
 to do today was technically and economically
feasible
 in
 1968.)
 (R,44,
 109) ,Freeman contends
 that there were
significant technical reasons requiring Orient
 #6 processing plant
to be built before the Orient
 #3 olant
 (R.45)
;
 that
 the company
wanted to avoid spending
 funds
 simultaneously
 on
 the
 two
 plants
(R,7l)
;
 and that an adequate supply
 of mining engineers was un-
available
 to supervise simultaneous construction
 (R,268)
.
 No
sionificant
 technical
 reason
 is
 shown requiring Orient #6
 plant
to
 be
 built
 orior to Orient
 #3
 plant.
 The plants are basically
similar and while
 some problems have been encountered in the opera-
tion of Orient
 #6
 plant,
 this plant
 is not
 a prototype
 to the
mining
 industry
 (R,l2,
 45)
.
 In
 addition,
 Freeman~s parent
 corpora-
tion,
 General
 Dynamics, made
 a profit of $57,000,000.00
 in
 1967
and $38,000,000.00
 in 1968
 (R.l09)
.
 While
 the supply of mining
engineers may have been inadequate to permit simultaneous construc-
tion of the
 two plants,
 it is just such questions
 as these and
other considerations
 raised
 by scrutinizing
 a
 concrete control
 program
which
 the Acerp hearing was designed to answer.
In
 its
 Letter
 of Intent submitted
 in
 1967, Petitioner stated
that
 it would, unan completion
 of
 a new processing plant at Orient
#6
 Mine,
 close
 down Orient
 #3 Mine while rebuilding its processing
olant,
 Freeman
 s
 need
 aooarently
 was
 to
 permit
 Orient
 #6
 Mine
 to
 be
finished
 in
 ardor
 to
 use
 it
 for
 meeting
 buyer
 demands
 for
 low
 ash
coal
 from
 Orient
 #3
 Mine.
 Now
 Freeman
 states
 that
 it
 wishes
 to
 continue
oceratino
 Orient
 #3
 Mine.
 even
 though
 Orient
 #6
 Mine
 is
 prepared
 to
omerate,
 endan
 the
 cociriction
 of
 the
 new
 processing
 plant
 at
 Orient
 #3
Mine,
 (Variance
 Petition
 and
 .R,292)
 .
 Thus,
 it
 appears
 that
 while
the
 carrot
 of
 lower
 cnliut~on
 levels
 was
 offered
 in
 a
 statement
 of
good
 intentions,
 ahe
 comPany’s
 vague
 plan
 has
 changed,
 resulting
 in
more
 emissions
 than
 would
 have
 otherwise
 been
 the
 case.
 This
 has
occurred
 without
 an
 initial
 opportunity
 for
 pollution
 contrdl
 author-
i-ties
 to
 analyze,
 to
 aacroae,
 or
 to
 disapprove
 a
 concrete
 abatement
crooosat.
In
 any
 event,
 the
 Regulations
 are
 designed
 to
 produce
 a
 clean
environment
 as
 roicke
 ac
 possible
 in
 accordance
 with
 technological
reasabil~ty
 ana
 economic
 reasonabaeness.
 If
 tney
 are
 to
 have
 meaning,
they
 must
 be
 enforced.
 The
 fact
 that
 the
 Company’s
 pollution
 impact(as
duced)
 may
 be
 nal
 nrnimal,
 is
 merely
 a
 mitigating
 consideration,
To
 carry
 not
 the
 roroose
 of
 compliance
 with
 the
 Regulations,
 we
imrrse
 a
 token
 eena~t
 of
 $5,000.00,
 Malibu
 Village
 Land
 Trust
 v.
Environmental
 Pratectaon
 Agency,
 #PCE7O-45.
2
 711
Finally, pursuant to Pollution Control Board Rule No. 107,
Petitioner has moved for non—disclosure of pages
 50 through 61
of the transcript.
 In support of this motion, Petitioner states
that disclosure of the price of the new processing plant, which
is discussed in these pages, would harm the company’s relation-
ship with contractors and would impair Freeman’s competitive
position in the coal industry because part of the cost basis
 for
coal sold from Orient #3 Nine would thereby be revealed to other
mining companies.
Neither argument is impressive.
 Reason may exist for non-
disclosure of a bid prior to its acceptance by a company, but
Freeman, subsequent to the hearing, awarded a contract to one
of
the
several bidders.
 Nor has petititioner submitted evidence
that public knowledge of the cost of its new processing plant
would injure Freeman’s competitive position.
 Such an inference
is not obvious
 and we will not block public access to our records
 on the basis of a mere assertion of the need for secrecy.
Mr. Lawton took no part in these proceedings.
This Opinion constitutes
the
findings of fact and conclusions
of law of the Board.
IT IS HEREBY ORDERED THAT:
1,
 Variance is granted Petitioner until October 27,
1972 to operate the four air cleaning
tables
which are
the subject of this hearing, in violation of Section
3-3.111 of the Rules and Regulations Governing the
Control of Air Pollution,
 subject to the following
conditions:
2.
 Petitioner shall, within 90 days of receipt of this
Order,
 submit to the Agency
 a schedule outlining
the interim stages
 of construction and installation
of
 the new processing plant at Orient #3 Nine,
 and
specifying the date by which it is anticipated each
stage will be completed.
3.
 Petitioner shall petition this Board 90 days
 in
advance of said expiration date for an extension of
this variance, demonstrating that
it has diligently
pursued the goal of total installation by April
 30,
1973 of its new coal preparation plant and that it
has complied with the interim stages of said installa-
tion as required in Paragraph
 2 of this Order.
 -
4.
 Petitioner shall, within 35 days of receipt of this
Order, post with
 the Agency
 a bond or other security
in the amount of $125,000.00 in
 a form satisfactory
to the Agency which
 sum
 shall be forfeited
 to the
State
 of
 Illinois
 in
 the
 event
 that
 the
 conditions
of this Order are not met or the air tables in question
are operated in violation of the Rules and Regulations
Governing the Control of Air Pollution after October
 27,
1972 without
 a variance.
5.
 Petitioner shall pay
 a money penalty in the amount
of $5,000.00 for failing to submit an Air Contaminant
Emission Reduction Program as required by Section
2-2.41 of the Rules
 and Regulations Governing the
Control of Air Pollution.
6.
 Petitioner’s motion for non-disclosure of paaes
 50
to 61 of the transcript herein is denied.
I, Regina E.
 Ryan, Clerk of
 the Illinois Pollution Control Board,
certify
 that
 the
 above
 Opinion
 and
 Order
 was
 adopted
 by
 the
 Board
on the
 28
 day of October,
 1971.
2
—
 713