ILLINOIS POLLUTION CONTROL BOARD
    October
    28,
    1971
    ENVIRONMENTAL PROTECTION AGENCY
    v.
    )
    #
    71—25
    CITY OF MARION
    CITY OF MARION
    V.
    )
    #
    71—225
    ENVIRONMENTAL PROTECTION AGENCY
    )
    Mr. William
    J. Novick,
    for the City of Marion
    Mr. Deneen
    A. Watson,
    for the Environmental Protection Agency
    Opinion of the Board
    (by Mr.
    Currie):
    The Agency~s complaint
    (#
    71-25)
    charged
    Marion with discharging
    inadequately treated sewage to a tributary of Crab Orchard Creek
    and
    with missing January and July
    1970 deadlines
    for submission of plans
    and award
    of construction contracts
    to meet
    the overflow and
    advanced—treatment requirements
    ot regulations
    SWE—I4.
    h~erej~c~ed
    a settlement proposal on the ground that
    it had not been approved
    by
    the Agency
    (#
    71-25, May
    12,
    1971),
    and
    a hearing was held
    June
    30,
    1971,
    The
    facts
    are not
    in dispute.
    The City operates
    a trickling
    filter treatment plant with chlorination, producing
    a good secondary
    effluent in dry weather
    (June 30,
    pp.
    26-27,
    31)
    ,
    when the average
    flow
    is 500,000 to 800,000 gallons per day
    (June
    30,
    p.
    25).
    In wet
    times, however,
    as much as 11,000,000
    to 13,000,000 gallons
    per day reach
    the plant
    (June
    30,
    pp.
    24,
    158).
    The hydraulic
    capacity of the plant
    is 1,300,000 gallons per day,
    and flows
    in excess
    of that quantity
    are bypassed directly to the creek
    without treatment
    (June
    30,
    pp.
    21,
    24,
    39-40).
    An Agency witness
    personally observed the bypass of objectionable materials on December
    16,
    1970,
    a date charged in the complaint
    (June
    30,
    pp.
    114-18).
    Rules and Regulations SWB-14,
    adopted by our predecessor
    the
    Sanitary Water Board
    and continued
    in force by
    the Environmental
    Protection Act,
    require the provision of additional
    (tertiary or
    advanced)
    treatment
    in Marion~s case even as to dry weather flows,
    because
    the flow of the receiving stream is
    too small
    to assimilate
    secondary effluent without harm to stream quality,
    They further
    require that “control of pollution caused by combined sewer over-
    flow
    or storm
    flow bypassing
    at sewage treatment works be provided
    at
    the
    time
    of
    improvement
    or expansion of sewage treatment works,”
    The
    date
    for
    compliance
    with
    both
    these
    requirements
    is
    July,
    1972,
    with
    plans
    to
    be
    submitted
    and
    contracts
    awarded
    substantially
    in
    advance
    in
    order
    to
    assure
    timely
    completion,

    Plans were due
    in January 1970
    for plants treating more than
    10,000 population equivalents,
    and the City’s population
    is about
    12,000
    (June 30,
    p.
    55).
    In any event, the record
    is clear, and
    the City admits
    (June
    30,
    p.
    161), that no plans were submitted
    before August of
    1971, which
    is late regardless
    of the size of the
    plant, and that contracts have not yet been awarded, which
    is also
    late in any
    case.
    In its proposed settlement agreement,
    and subsequently,
    the
    City promised to submit plans for both bypass control and tertiary
    treatment by August
    1,
    1971;
    to advertise
    for bids by November
    1;
    and to complete construction by July
    1,
    1972
    (see petition for
    variance,
    # 71-225), which would mean that the admitted delay in
    getting started would not delay the operation of the required
    facilities.
    The City’s program at that stage consisted of the
    addition of two aerated lagoons
    to capture, retain, give
    50
    treatment
    to,
    and chlorinate bypasses
    up to ten times normal dry
    weather flow, with one of the lagoons to serve
    in normal times
    as
    a tertiary facility
    (June
    30,
    pp.
    162—67).
    A few days before the proposed August
    1 date
    for plan
    submission the City received word
    (Oct.
    16,
    p.
    16) of
    the Agency’s
    just revised Technical Policy
    20-24, which among other things
    states that when waste, stabilization ponds such as those proposed
    are used “provision must be made
    to remove algae
    and other suspended
    solids to meet the intended treatment requirements and effluent
    criteria”
    (Section XII
    C).
    The theory apparently underlying
    this
    provision was suggested by an Agency witness
    (June 30~, pp.
    184-
    85)
    Presently we
    are requiring permits for lagoon type
    systems
    for ter?iary
    treatment.
    It’s been kicked
    around out in the field that lagoons sometimes
    don’t provide the treatment necessary in that
    respect.
    Sometimes they tend to grow
    algae, which
    would increase possibly the suspended solids coming out
    of it
    .
    .
    The growth of algae
    in the lagoon,
    in other words, might result
    in
    a biochemical oxygen demand
    and suspended solids
    in excess
    of the applicable limits of
    4 and
    5 ppm iespectively.
    Confronted with
    the new technical policy,
    the City filed
    its
    original plans
    according to
    its proposed schedule
    (Oct.
    16,
    p.
    18), set
    to work immediately
    on new plans to meet
    the provisions
    of the Technical Policy
    (Oct.
    16,
    pp.
    21-23),
    and filed for
    a
    variance that would extend the dates for plans, bids,
    and corr~liance
    by eight weeks
    (Oct.
    16,
    pp.
    23-24)
    because of the algae pr’~vision.
    We held
    an additional hearing October
    16
    on the variance petiLion
    (#
    71—225).

    The City’s revised plans were submitted September
    30
    (Oct.
    16,
    p.
    23)
    ,
    within the proposed eight-week extension.
    The tertiary
    lagoon will be replaced by sand filters
    that should do
    the
    job
    ~with dry-weather
    flow without creating
    any
    algae nrohlem
    (Oct.
    16,
    pp.
    16,
    26).
    Flows
    in excess of plant capacity will he retained
    in
    a single aerated lagoon and chlorinated before any discharge
    to the stream
    (Oct.
    16,
    p.
    16).
    Although the treatment plant
    together with
    the byrass retentian system will be able
    to handle
    a flow at
    the rate of no more than 8,640,000 gallons per day
    (Oct.
    16,
    p.
    43)
    (which is roughly ten to fifteen times dry weather
    -flow),
    the City will also replace
    a half mile
    of leaky interceptor
    sewer
    that
    is responsible for
    a “great amount”
    of infiltration
    (Oct.
    16,
    p.
    44).
    The
    City
    therefore
    predicts
    that
    “when
    we
    finish
    this project and eliminate some
    of
    our
    sources
    of
    pollution
    infiltration
    ,
    we will be able
    to give either complete treatment
    or primary treatment
    to all of the flow that comes to the plant
    in wet weather”
    (Oct.
    16,
    o.
    45).
    Finally,
    the City has agreed
    that
    “after the peak flows
    pass,
    we have provisions
    for draining
    the contents of the storm water pond back to the plant during
    periods of
    low flow and giving
    it complete treatment”
    (Oct.16,
    p.
    46).
    The comoletion date proposed
    for this
    improved system
    is
    September
    30,
    1972, with bids
    to he sought by December
    30,
    1971
    (Oct.
    16,
    p.
    24).
    The improvements
    in the revised program
    are considerable and
    commendable;
    the City has substantially upgraded
    its provisions
    with
    regard
    both
    to
    tertiary
    treatment
    and
    to
    stormwater.
    The
    tertiary
    standards
    will
    be
    more
    certainly
    met;
    infiltration
    re-
    ductions will
    greatly
    reduce,
    if
    not
    eliminate,
    the
    proportion
    of
    flow receiving no treatment;
    some retained stormwater will be run
    through the plant
    for full treatment.
    We
    think the
    two months’
    delay
    to
    prepare
    this
    revised
    Program
    well
    worth
    the time,
    and
    certainly
    we
    will
    not
    penalize
    the
    City
    for
    those
    two
    months.
    While
    the
    Agency
    is
    quite
    right
    in
    its suggestion
    (Oct.
    16,
    pn.
    30-37)
    that
    the
    regulation
    itself
    made
    relevant
    the
    question
    whether
    a’gae
    would
    make
    lagoons
    inadequate
    to
    meet
    the
    effluent
    standard,
    the
    record
    shows
    that.
    up
    until
    the
    issuance
    of
    the
    revised
    Technical
    Policy
    in
    July
    1971
    the
    Agency
    had
    been
    willing
    to
    grant
    permits
    for
    lagoons
    in
    similar
    circumstances
    (June
    30,
    c.
    185;
    Oct.
    16,
    p.
    34).
    The
    law
    was
    not
    changed,
    but
    the
    Agency’s
    understanding
    for
    applying
    it
    was,
    and
    no
    nenalties
    are
    in
    order
    for
    those
    ‘who
    in
    good
    faith
    did
    what
    the
    Agency
    said
    was
    sufficient.
    At
    the
    same
    time,
    we
    cannot
    find
    fault
    with
    the
    Agency
    for
    publishing
    its
    revised
    policy
    statement.
    ~Jhenever
    new
    policies
    are
    promulgated,
    someone’s
    plans
    may
    be
    affected;
    desirable
    changes
    cannot
    be
    deterred
    by
    that
    fact.
    Jima
    allowances
    have
    to
    be
    made
    in
    such
    cases,
    as
    here,
    to
    avoid
    hardsliin,
    But,
    if
    the
    Agency
    is
    right
    in
    its
    new
    algae
    nosition,
    the
    change
    has
    succeeded
    in
    arresting
    at
    the
    drawing—board
    stage
    the
    construction
    of
    an
    inadequate
    facility.
    We
    can
    only
    view
    that
    accomplishment
    as
    a
    plus.
    2
    --
    703

    The City also tells us that, with
    a reasonably dry Spring,
    it may be able
    to complete the retention lagoon by July of
    1972 despite the change of plans
    (Oct.
    16,
    pp.
    40-41).
    We shall
    require that it do
    its best
    to do
    so,
    in light
    of the importance
    of eliminating the existing raw sewage discharges.
    We need not today decide whether the Agency is iight that
    lagoons are insufficient to meet the standards without algae
    removal,
    since
    the City has committed itself to
    a more certain
    solution.
    This question,
    together with that of the degree of
    treatment
    that will ultimately be required of excess flows,
    is
    being thoroughly explored in the pending rule-making proceeding
    #R71-14.
    Nor need we decide whether the requirement that bypass
    flows be given primary treatment and chlorination means just what
    it says,
    or whether,
    as the City says itwas orally informed
    by the Agency, no more
    than ten times the normal flow must receive
    even this much treatment.
    That figure appears neither
    in the
    regulations, which govern,
    nor
    in the Technical Release.
    Since we are here considering only primary treatment,
    any flows not-
    captured will go raw to the stream;
    even
    a high degree of dilution
    (June 30,
    p.
    176)
    can hardly avoid a nuisance when the ingredients
    of raw sewage are considered.
    It
    is therefore gratifying that the
    City has committed itself to
    a program of reducing infiltration
    as well as providing retention eaoacity
    so as to enable it
    to
    give at least primary treatment and chlorination
    to all flows
    reaching the plant, and we shall require it to adhere to
    that
    program.
    Although SWB-l4
    states that
    bypass flows “shallbe given
    primary treatment,
    and chlorination
    if necessary,”
    it also requires
    “the control of pollution” resulting from bypasses,
    and at the
    time
    of required treatment plant improvements.
    The Agency interprets
    this
    (Technical Policy 20-24,
    Section VII-A)
    to require more than
    primary treatment when primary treatment
    is
    inadequate
    to prevent
    pollution.
    Because of
    the enormously heavy organic
    load
    in the
    “first flush” from
    a storm
    (see June
    30,
    p.
    32)
    ,
    that portion,
    the Agency
    says,
    should receive
    full plant treatment; whether
    primary treatment for
    the remainder suffices
    is to be determined
    on
    a case—by—case basis according
    to such factors as the
    flow
    of
    the receiving stream in order to avoid violations
    of the
    water quality standards.
    We agree that primary treatment of bypasses cannot in all
    cases be
    a complete answer under the regulations.
    In many cases
    it
    is
    feasible and reasonable
    to retain
    a large percentage
    of the
    excess
    flow
    to be run through the plant later on for complete
    treatment
    (see,
    e.g.,
    League of Women Voters
    v.
    North Shore Sanitary
    District,
    # 70-7, March
    31,
    1971).
    Whether in Marion’s case more
    is required than
    is now proposed cannot be determined from
    the
    present record.
    The Agency will make an initial determination of
    adequacy in passing on
    the permit application now pending before
    it.
    Even
    if greater retention capacity
    is ultimately required,
    the present plan seems
    a most likely intermediate step that should
    eliminate
    a
    large part
    of the present nuisance,
    and its construction
    2
    704

    ought
    not
    to
    be
    delayed.
    In sum,
    from the vantage point of today,
    we
    find the City’s
    program an appealing
    one, in terms both of time
    and of ultimate
    performance,
    with reservations only as to whether additional re-
    tention capacity may later prove necessary.
    We therefore approve
    the City’s program schedule on the conditions spelled out
    in
    the order.
    This leaves for consideration
    the question of money penalties
    for missing
    the deadline
    for submission of plans.
    There is no
    satisfactory explanation
    for this failure:
    The City knew of
    SWB—l4’s requirements
    in 1968 or 1969
    (June
    30,
    p.
    161), and
    the
    Agency’s alleged
    char’
    in policy respecting the
    size of the
    retention basin
    (June
    ,
    p.
    158)
    and the acceptability
    of
    tertiary lagoons came alter the plan deadline had already been
    missed,
    The
    importance
    of
    the
    interim
    dates
    for
    submitting
    plans
    and letting contracts
    is well illustrated by
    this case.
    Had
    plans
    been
    submitted
    when
    required,
    the adequacy of the proposed
    bypass facilities could have been fully examined,
    and any inadequacy
    corrected, without jeopardizing compliance with
    the ultimate operation
    deadline of July 1972.
    As
    it
    is, discounting the eight-week post-
    ponement
    that.
    is
    not the City’s fault,
    if
    the lagoon is too small
    there will ‘vu~’y likely be
    a further delay-before
    it can been-
    larged.
    Thus
    the seriousness of the City’s failure to file timely
    plans should not be underrated,
    On the other hand, Marion’s
    position
    is more fortunate than that of some,
    for, apart from the
    Agency’s revised effluent lagoon policy and
    the question
    of lagoon
    size, Marion was able
    to promise that it would suffer no delay
    in meeting the most important deadline, that for compliance with
    the effluent
    and treatment requirements.
    To do so
    it has shown
    a high degree of commitment and energy,
    especially
    in its prompt
    and constructive
    response to the Agency’s revised policy,
    that
    cannot go unnoticed.
    The question of
    a penalty
    in this
    case, moreover,
    is
    a part
    of a most disturbing larger picture.
    Marion
    is far from alone
    in
    missing
    its plan deadline,
    nor
    is
    it among the worst offenders.
    Without condoning past lapses, we think it appropriate
    to encourage
    those who have fallen behind to make every effort to make up
    for
    it.
    We
    shall
    therefore
    look
    with
    some
    indulgence
    upon
    local
    governments that
    file programs
    in the immediate future that will
    result in compliance within
    a short time after the ultimate deadline.
    For
    those
    whose
    violations
    will
    substantially prolong pollution
    and who even now fail to come forward with as expeditious
    a program
    as
    is
    practicable,
    the penalties may be quite severe.
    Cf.
    GAF
    Corp.
    v.
    EPA,
    #
    71-11
    (April
    19,
    1971);
    EPA
    v.
    Incinerator,
    Inc.,
    # 71-69
    (Sept.
    30,
    1971)
    ;
    Lloyd Fry Roofing
    Co.
    v,
    EPA,
    # 71-4
    (Oct.
    14,
    1971).
    We do not exclude
    the possibility
    in such cases
    of
    penalties
    cumulating
    each day ultimate compliance
    is postponed.
    2
    705

    In
    light
    of
    these
    policy
    considerations
    we
    penalize
    Marion
    the nominal sum of
    $100.
    It was not until after
    the date
    for
    submitting plans had passed that the City
    took serious steps
    to
    live up
    to the obligations of SWB-14
    (June
    30,
    p.
    156),
    and we
    cannot let
    the serious violation
    of the important interim deadline
    pass altogether.
    But Marion’s exemplary response to’the filing
    of the complaint,
    its excellent record
    for operation of its existing
    plant,
    and the critical
    fact that
    its error is not expected
    to result in continued pollution greatly mitigate the offense,
    We sincerely trust that others
    in similar circumstances will follow
    Marion’s example immediately without waiting to be prosecuted.
    Any
    substantial
    delay in
    cleanitig up our waters resulting from
    the failure of municipal
    officials
    to
    obey
    the law would be
    a
    tragedy not only
    for the environment but
    for public confidence
    in government
    as well.
    The City
    in the final hearing raised the question of financing
    (Oct.
    16,
    p.
    57).
    The
    Agency
    described
    the
    chances
    of state aid
    as
    very
    good,
    and
    the
    City
    hopes
    for federal assistance
    as well,
    As we have said before
    (see City of Mattoon
    v,
    EPA,,#
    70-8
    (Feb.
    17,
    1971)
    ;
    Sanitary District of Durand
    v.
    EPA,
    # 71-317
    (October
    18,
    1971)),
    outside help
    is
    all very well, but the obligation
    is
    that
    of
    the local government,
    and
    the unavailability or post-
    ponement or outside money cannot oe
    an exeu~e for
    poi..iutlon
    r~C
    view the City’s program
    as
    a commitment to build the necessary
    facilities, with no ifs,
    ands,
    or huts,
    If it were not such
    a
    commitment, we cbuld not .approve
    it’.
    Our otder today requires
    the City to construct those facilities
    in order
    to abate pollution
    violations.
    To comply with such an order
    the City is authorized by
    Section
    46
    of
    the Environmental Protection Act to issue general
    obligation or revenue bonds,
    if necessary, without referendum and, we have
    held, witnout regard to
    any existing merely statutory limit otnerwise
    applicable
    to bonded indebtedness,
    League of Women Voters
    v,
    North Shore
    Sanitary District,
    # 70-7
    (March
    31,
    1971).
    No specific
    order to issue bonds
    is necessary; we leave
    the question of how to
    raise money
    to the City, but the money must be raised.
    See Ruth
    v.
    Aurora Sanitary District,
    17
    Ill,
    2d 11,
    158
    N.E.
    2d 601
    (1959).
    We shall require,
    as agreed,
    ‘the submission
    of
    a plan
    for financing the necessary improvements
    (Oct.
    16,
    p.’ 74),
    A few procedural matters require brief mention.
    The City
    challenged the Board’s
    jurisdiction on the ground that no Board
    member was present at the hearing
    (June 30,
    pp.
    48-51)
    ,
    The motion
    is denied.
    The Rule referred
    to
    (Board Procedural
    Rule 204)
    applies only to rule-making proceedings
    of general applicability,
    not
    to individual adjudications.
    To require
    the attendance
    of
    a
    Board member at each of the hundreds
    of hearings held each year
    would be
    a physical impossibility,
    and both the statute and
    the
    rules
    are plain that individual cases,
    apart from rule—making,
    may be handled by hearing officers who are not Board members.
    The
    decision
    is made
    by the Board alone
    on the basis of the
    record.
    We also deny
    the motion
    (June
    30,
    pp.
    51-53)
    that the Board view
    the premises.
    Viewing
    is
    an extraordinary procedure that is
    2
    705

    authorized
    but
    not
    required
    by
    Procedural
    Rule
    322.
    To view
    in
    every case would impose an intolerable burden.
    We
    see nothing
    in the present case
    to suggest that a viewing would contribute
    materially
    to the resolution
    of any of the issues.
    The motion to
    dismiss on the ground
    that Board decisions
    are
    to be reviewed in
    the Appellate Court
    (June
    30,
    p.
    191)
    is also denied;
    the suggestion
    is premature,
    since any invalidity
    in the appeal process would
    not affect
    the Board’s ‘authority,
    and erroneous,
    since the
    governing provision
    is the ‘Environmental Protection
    Act, which
    incorporates
    only certain portions
    of the Administrative Review
    Act.
    Direct Appellate Court review
    is
    flatly authorized by the
    Illinois Constitution.
    Finally, we
    see no merit
    in the attacks
    on the admissibility
    of certain samples
    (June
    30,
    pp.
    90,
    193),
    but in any case those samples were not necessary
    to the violations
    found and played
    no part
    in our decision.
    This opinion constitutes
    the Board’s
    findings of fact
    and conclusions of
    law.
    ORDER
    1.
    The petition of the City of Marion for
    a variance extending
    the
    date
    for
    compliance
    with
    the
    treatment
    and
    effluent
    standards of SWB-l4 until September
    30,
    1972,
    is hereby granted,
    on condition that the following provisions
    of this order are
    met.
    2.
    The City of Marion shall abate its discharge of untreated
    or inadequately treated sewage and its violations
    of the
    Environmental
    Protection
    Act
    and
    of
    regulations
    there-
    under with regard to tertiary treatment and stormwater by-
    passing in accordance with it~revised program as
    submitte’d
    September
    30,
    1971,
    and with the following schedule:
    a)
    Advertisement for bids:
    December 30,
    1971;
    b)
    Completion and operation of facilities:
    September
    30,
    1972.
    3.
    The City of Marion shall make every reasonable effort to
    complete
    the facilities
    for stormwater bypasses by July
    31,
    1972.
    4.
    The City
    of Marion shall replace the interceptor
    sewer described
    at
    p.
    44
    of
    the
    October
    16
    transcript
    in
    accordance
    with
    its program as submitted September
    30,
    1971,
    and shall actively
    pursue
    a program to discover and eliminate other sources of
    infiltration subject
    to reasonable abatement.
    2
    -‘
    /07

    5.
    If the above measures prove inadequate
    to eliminate raw
    sewage
    bypasses
    by
    September
    30’;
    1972,
    the City of Marion
    shall present
    to the Agency and to the Board within thirty
    days thereafter
    a program for additional pumping and retention
    capacity.
    6.
    If the bypass control measures
    in the above program do
    not provide adequate treatment to satisfy the Agency,
    the
    City
    of
    Marion
    shall
    seek
    Board
    review
    of
    the
    Agency’s
    determination
    or shall submit
    a revised program,
    in either case within the
    time allowed by statute
    for, appeal from
    a permit denial.
    In either case, unless the present bypass program
    is wholly
    incompatible with that required
    to meet the Agency’s objections,
    the Agency shall issue
    a permit conditioned on additional
    measures to be taken in the future, and work shall
    proceed
    on
    the present program as
    a first phase of compliance
    in
    accordance with the present schedule.
    7.
    The City of Marion ~hal1 within
    35 days after receipt of
    this
    order post with
    the Agency
    a bond or other security
    in the amount
    of $100,000
    to assure compliance with
    the terms and
    conditions of this
    order,
    8.
    The City ‘of Marion shall within
    35 days after receipt of this
    order
    pay
    to the State
    Of Illinois
    the sum of $100 as
    a
    penalty
    for its failure
    to meet the requirements of SWB-14
    with respect to the submission of plans
    and
    the award of construction
    contracts~
    9.
    Within
    60
    days
    after receipt of this order,
    the City of Marion
    shall submit to the Agency and to the Board
    a plan assuring
    financing of
    the program herein approved,
    together with~
    a study
    by bond counsel discussing
    the various financing
    alternatives
    available,
    10,
    Further proceedings
    in this matter will be held
    if
    circumstances
    so require,
    and
    jurisdiction
    is retained
    for
    that purpose.
    I,
    Regina
    E,
    Ryan, Clerk
    of the Pollution Control Board,
    certify
    that the Board adopted the above Opinion this
    28
    day of
    October
    ,
    1971.

    Back to top