ILLINOIS POLLUTION CONTROL BOARD
    January 23,
    1975
    CITY OF PLANO,
    Petitioner,
    vs.
    )
    PCB 75—14
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    ORDER OF THE BOARD
    (by Mr. Henss):
    Petitioner requests a variance from Open Burning
    Regulations in order to open burn landscape waste.
    On
    page
    5 of the petition the following language is included:
    “Petitioner further requests a statement
    that an air curtain destructor, properly
    installed, which presently meets require-
    nients
    for disposal of landscape waste,
    will continue to be an approved method
    For a reasonable number of years, and that
    Petitioner will be considered
    to be in
    compliance during such period of time.”
    At the present time the Regulation provides for a one
    year permit for the use of an air curtain destructor.
    Any
    extension of that time would involve the amendment to the
    Regulation.
    Petitioner does not propose to amend the Regulation
    nor would we authorize
    a regulatory proceeding to proceed in
    conjunction with
    a variance request.
    Therefore,
    the language
    which is quoted above is stricken and we authorize this petition
    to proceed as
    a request for variance from the Open Burning Regu-
    lation.
    If Petitioner
    in the future wishes to commence a
    regulatory proceeding for the purpose of authorizing long time
    usage of an air curtain destructor then the regulatory procedure
    should be followed consistent with our Procedural Rules.
    IT IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above Order was adopted this
    23rd
    day
    of January by
    a vote of 3-0.
    15—345