ILLINOIS
    POLLUTION
    CONTROL BOARD
    October 9, 1975
    UNARCO INDUSTRIES,
    INC.
    Petitioner,
    v.
    PCB 75—289
    ENVIRONMENTAL PROTECTION AGENCY,
    )
    )
    Respondent.
    INTERIM
    OPINION
    AND
    ORDER
    OF
    THE
    BOARD
    (by
    Mr.
    Dumelle):
    Unarco Industries
    (Petitioner),
    filed a variance petition
    on July 25, 1975 seeking relief from Rule 203(a) of the Board’s
    Air Pollution Control Regulations, Chapter 2
    (Air Rules) until
    May 15,
    1976.
    The Illinois Environmental Protection Agency (Agency)
    filed its Recommendation proposing a variance grant, on
    September 8, 1975.
    No hearing was held.
    Petitioner engages in the manufacture of porcelain steel
    sinks and their porcelain component parts.
    Its facility is
    located approximately one—half mile west of the City of
    Paris, in Edgar County.
    New
    residential housing is located
    approximately 1/8 mile east of Petitioner’s facility.
    Petitioner’s basic sink operation consists of the
    stamping of carbon
    and
    coil steel into sink basins, welding
    the basins together in pairs, welding in necessary auxiliary
    components, spray coating the units with porcelain frits, and
    firing the porcelain to achieve a finished surface.
    It is
    the porcelain spraying operation which fails to conform to
    Rule 203(a) of the Air Rules.
    During this operation, particulate
    discharge resulting front overspraying escapes the spray
    booth
    baffles and vestibule and enters the atmosphere via the
    booth’s
    stack, 32 feet above ground level.
    19—57

    —2—
    Petitioner states that the disch~rgefrom the spray booth
    unit occurs at
    a rate of 2.1 pounds per hour.
    The Agency notes
    in its Recommendation that as three units are normally
    in operation,
    the actual emission rate is 6.3 pounds per hour.
    The standard
    under Rule 203(a),
    is
    .53 pounds per hour.
    rfhe
    contaminant from Petitioner’s stack
    is
    a finely
    milled porcelain enamel particulate.
    Petitioner contends
    that the particulate
    is quite heavy, with a specific gravity
    of
    2.5, and therefore mostly remains near the point of
    emission in the center of the facility’s roof.
    The Agency,
    however,
    states that a micron analysis reveals that 67
    of the
    particulate is comprised of particles under
    40 microns in
    size.
    The Agency indicates that particles of this size tend
    to remain airborne for longer periods of time and for
    greater distances than larger particles and hence will not
    remain very near the emission point.
    The Agency further
    notes that during an August
    1,
    1975 inspection,
    an Agency
    engineer observed porcelain enamel particulate emissions
    drifting from two booth stacks across and beyond the plant
    roof.
    Petitioner states that it provides emission control on
    porcelain emissions by the use of the baffles and vestibule arrange-
    ment incorporated into the booth assemblies.
    Petitioner proposes
    to reduce its emissions to comply with the Rule 203(a)
    standard by installing a filtration system capable of capturing
    96
    to 99
    of the particulate matter.
    Petitioner proposes to
    use either a multicyclone or baghouse collector.
    The program
    would clean approximately 90,000 standard cubic feet per
    minute, which would then be returned to the in-plant atmosphere.
    The Agency Recommendation indicates that both of the alternative
    filtration systems proposed by Petitioner are capable of producing
    compliance with Rule 203(c) assuming little or no porcelain
    frit fracture upon induction to the filters.
    Petitioner has also supplied regional ambient air quality
    data for 1974, which indicates that
    the
    grant of a variance would not
    pose a hazard to either primary or secondary particulate standards.
    The Agency Recommendation notes that this data comes
    from sampling sites at Bloomington and Champaign and is not
    conclusive as to the ambient air quality near Petitioner’s
    plant
    in
    Paris.
    However,
    the Agency also states that given
    the small size of Petitioner’s emissions and the general
    nature of the area,
    it agrees with Petitioner’s assessment
    that a variance would not affect the air quality standards
    in
    the area around Petitioner’s facility.
    19
    58

    —3—
    Both Petitioner and the Agency state that there have
    been no citizen complaints regarding Petitioner’s emissions.
    Petitioner alleges that a denial of a variance would make it such to
    an arbitrary and unreasonable hardship.
    Petitioner alleges
    that if required to comply immediately with Rule 203(a)
    it
    would be forced to cease
    its porcelain application and consequently
    close
    its facility until control equipment will be installed.
    Petitioner alleges this would result in a layoff,
    a loss
    of approximately $1,000,000
    in income, and a possible decision
    not to reopen the plant.
    However,
    as the Agency notes
    in its
    Recommendation,
    Petitioner has not substantiated these allegations
    with any data.
    Furthermore,
    the Board has consistently held,
    that
    denial of a variance does not constitute
    a shutdown.
    The Petitioner
    can still operate although subjecting itself to possible
    enforcement action
    (ABC Great States
    v.EPA,
    PCB 72—39;
    Flintkote
    C~y~EP~,
    PCB 71—68; Commonwealth Edison v.
    EPA,
    PCB 72—91,
    72—150)
    The Agency states
    in its Recommendation that there is
    no reason why
    Petitioner could not have achieved compliance earlier.
    Petitioner now has all of its required permits other than those
    pertaining
    to the porcelain sink manufacturing process.
    However,
    Petitioner
    did not begin
    to submit any of its permit applications
    until two years after the applicable compliance date for the
    facility.
    It appears then, that any hardship to the Petitioner
    at
    this point is self—imposed.
    Petitioner also failed to advance any arguments as to
    unavailability of controls or financial inability to install
    such controls prior
    to the mandated compliance date.
    The
    Board has held that a hardship imposed by denying
    a variance
    is
    “not unreasonable and arbitrary”,
    if it was
    earlier
    within the power of the Respondent to remedy,
    and is
    thus
    self-imposed
    (City
    of Danville
    v.
    EPA,
    PCB 72-335;
    GAF Corporation
    v,
    EPA, PCB 71-Il.
    Title
    9,
    Section
    35, of the Act provides that the Board
    may grant
    a
    variance whenever
    it
    is found,
    “.,.upon presentation
    of adequate
    proof...”, that compliance will impose an arbitrary
    or
    unreasonable hardship.
    The Board could
    find, based upon this record,
    that Petitioner
    has failed
    to establish beyond a mere assertion that the denial
    of
    a variance would impose such an arbitrary and unreasonable
    hardship and that
    it has not justified its failure to bring its
    facility into timely compliance.
    The Petitioner shall be granted 60 days within which to submit
    additional materials,
    if any, bearing upon the hardship question
    and the apparent self-imposed delay.
    A waiver of the 90—day
    aeci~on
    period
    set by
    statt.~te
    shall
    ha executed and filed with
    the
    Board
    on or before Octoier
    22,
    1975.
    Failure to timely file
    the
    waiver
    shall result in
    the dismissal of
    this case and the
    denial of the variance because of the grounds already stated.
    19
    59

    —4—
    The Board notes
    in conclusion, that the Agency has
    stated in its Recommendation that it informed Petitioner on
    August
    8,
    1975 that Petitioner need not wait until the Board
    decision in the variance to begin its compliance program.
    The Agency indicates that based on the Agency modification of
    Petitioner’s proposed compliance schedule, allowing adequate
    time for determination of supplier and costs, delivery,
    installation, and testing, Petitioner can be
    in compliance
    with Rule 203(a) by March 15,
    1976.
    ORDER
    1.
    Petitioner shall have a
    60-day period from the date
    of this Order to file additional material with the Board and
    Agency bearing upon the hardship and delay questions discussed
    in this Interim Opinion.
    2.
    Petitioner shall on or before October 22,
    1975 file
    with
    the Board a waiver of the 90-day decision period for an
    additional
    90 days.
    Failure
    to timely file the waiver shall
    result in the denial of the variance for the reasons stated.
    IT
    IS SO ORDERED.
    I, Christan L.
    Moffett, Clerk of the Illinois Pollution Control
    Board, hereby certify the above Interim Opinion and Order were adopted
    on the
    44~
    day of October, 1975 by
    a vote of
    4-a
    Illinois
    Board
    19—
    60

    Back to top