ILLINOIS POLLUTION CONTROL BOARD
    April
    8,
    1976
    UNARCO INDUSTRIES,
    INC.
    Petitioner,
    v.
    )
    PCB 75—289
    ENVIRONMENTAL PROTECTION AGENCY,
    Respondent.
    OPINION AND ORDER OF THE BOARD
    (by Mr. Duinelle):
    On July
    25,
    1975 Unarco Industries,
    Inc.
    (Unarco)
    filed
    a petition for variance from Rule 203(a)
    of the Air Pollution
    Control Regulations.
    On September
    8,
    1975 the Environmental
    Protection Agency
    (Agency)
    filed its Recommendation.
    The
    Board issued an Interim Order on October
    9,
    1975 requiring
    tinarco
    to submit additional information.
    On October
    30,
    Unarco waived,
    for 90 days,
    the 90-day decision requirement.
    tJnarco filed
    its Supplemental Petition before this Board on
    December
    18,
    1975,
    and further waived the decisional date
    on January
    9,
    1976.
    On January
    28, 1976 the Agency filed
    an Amended Recommendation
    in which the Agency recommended
    that a variance be granted.
    The facility
    in question
    is a porcelain-on-steel
    manufacturing plant located west of Paris, Illinois,
    in
    Edgar County.
    The plant employs 35-hourly and five salaried
    personnel,
    manufacturing procelain—on-steel
    sinks for the
    housing industry and certain porcelain component parts.
    The
    specific portion of this process that occasioned the instant
    petition is the spray application of finely milled porcelain
    enamel onto steel.
    During the spraying operation some of
    these particles are emitted from the spray booths into the
    atmosphere, via stacks 32 feet high,
    in violation of the
    particulate limits of Rule 203(a).
    21—45

    —2—
    Unarco
    is presently
    in the process of installing a system
    designed to collect,
    at
    a 99.9
    efficiency, particles above
    1/2 micron in size.
    (Page
    4 of Exhibit II)
    The projected cost
    is $178,091.00.
    As Unarco states that the emitted dust consists
    only of particles of 3.75 microns and above
    (page
    3 of Petition),
    there can be no doubt that the completed system would bring
    Unarco into compliance with particulate regulations.
    In fact,
    the processed air is
    to be recirculated back into the plant
    (Page
    1, Exhibit
    1).
    Unarco shows that its emissions are not causing or contributing
    to a violation of Ambient Air Quality Standards
    in Bloomington
    or Champaign,
    Illinois
    (Page
    5 of Petition).
    While these data
    are not conclusive as to the air quality near Unarco’s plant,
    the small amount of the emissions
    (2.1 lbs/hr.
    from each of
    3
    spray booth assemblies)
    and the absence of any citizen complaints
    indicate no reason to suspect any significant adverse impact on
    ambient air quality according to the Agency
    (See page
    5 of
    Recommendation)
    The remaining issue is whether Unarco’s delay in compliance
    (the regulation was effective as of December 31,
    1973)
    has been
    self—imposed so as to negate Unarco’s claim of unreasonable or
    arbitrary hardship.
    On page
    8 of its Supplemental Petition
    Unarco comments:
    “This has not been
    a situation of a manufacturer
    claiming a necessity to choose between either increased
    corporate profits or the spending of extra profits on
    pollution control devices.
    Instead,
    it is
    a manufacturer
    struggling
    to get an operation off the ground, while
    at the same time attempting to meet the various environmental
    requirements.”
    Unarco has asserted facts which would tend to support this
    generous language.
    Indeed, Unarco speaks of several crisis
    situations,
    since it obtained the plant
    in February 1973, which
    required serious evaluation and justification for keeping the
    plant open.
    In early summer of 1974 Unarco became aware that
    it
    would lose its prime customer.
    During May,
    1975, Unarco
    was ordered by its home office to evaluate the effects of
    a
    natural gas cutback.
    However,
    from the period of February, 1973
    to early summer
    of 1974 Unarco states that its failure to act on the problem
    in question was due
    to the allocation of its financial and
    manpower resources to three other environmental projects which
    were of greater consequence.
    Knowing that it was
    in violation
    of Rule 203(a), Unarco decided to:
    1) not remedy the problem,
    and
    2)
    not apply for
    a variance.
    Unarco has certainly not
    demonstrated that it could not have afforded the cost of
    21
    —~46

    —3—
    preparing and filing
    a petition for variance.
    The evidence submitted,
    voluminous
    as
    it
    is, does not satisfactorily explain Unarco’s
    failure to petition for a variance until July of 1975.
    However,
    Unarco appears to have been otherwise earnest in its attempts
    to comply with the Board’s regulations.
    It
    is arguable that,
    given the lack of funds to accomplish compliance,
    the delay
    did not cause substantial additional environmental damage.
    Further, the loss of Unarco’s prime customer and decisions
    on
    the economic viability of this recently purchased plant do explain
    substantial parts of the lengthy delay.
    On balance,
    the Board finds that compliance with Rule 203(a)
    would have caused an unreasonable hardship for Unarco,
    and
    that Unarco’s delay was substantially explained.
    However,
    it
    is not the loss of a customer or the allocation of funds
    to other
    projects which the Board views
    in mitigation of Unarco’s failure
    to take steps necessary
    to obtain compliance with Rule 203(a).
    The mitigating factor
    is the economic hardship which was caused
    by these occurrences,
    These other hardships combine
    to make
    compliance with Rule 203 a sufficiently arbitrary and unreasonable
    hardship to outweigh even Unarco’s lengthy delays.
    Yet even
    that finding could have been outweighed
    in this case had Unarco’s
    emissions constituted a more significant threat to the environment.
    The Board finds that
    a variance until May 15, 1976 should
    allow Unarco adequate time
    to diligently complete the construction
    of its frit particulate collection system.
    Due to the nearness
    of Unarco’s completion date for the collection system,
    no
    performance bond will be required.
    This Opinion constitutes
    the Board’s findings of fact
    and conclusions of
    law.
    ORDER
    1.
    Petitioner Unarco Industries,
    Inc.,
    is hereby granted
    variance from Rule 203(a)
    of the Air Pollution Control Regulations
    from July
    25,
    1975 until May 15,
    1976.
    2.
    Petitioner Unarco Industries,
    Inc.,
    shall, as a condition
    of
    this variance,
    submit monthly reports to the Agency detailing
    its progress towards completion of its compliance program.
    These
    progress reports shall begin on the first day of the month
    following the Board Order and shall be submitted on the first
    day of each month thereafter until the project
    is completed.
    The
    21-—47

    —4—
    progress reports will be submitted to:
    Environmental Protection Agency
    Division of Air Pollution Control
    Control Program Coordinator
    2200 Churchill Road
    Springfield,
    Illinois
    62706
    IT
    IS SO ORDERED.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Boa~d,hereby certify the above Opinion a d Order were adopted on the
    ~‘__day
    of April 1976 by a vote of
    -
    Christan L.
    Moffett,
    k
    Illinois Pollution C
    ol Board
    21—48

    Back to top