ILLINOIS POLLUTION CONTROL BOARD
April
8,
1976
UNARCO INDUSTRIES,
INC.
Petitioner,
v.
)
PCB 75—289
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
OPINION AND ORDER OF THE BOARD
(by Mr. Duinelle):
On July
25,
1975 Unarco Industries,
Inc.
(Unarco)
filed
a petition for variance from Rule 203(a)
of the Air Pollution
Control Regulations.
On September
8,
1975 the Environmental
Protection Agency
(Agency)
filed its Recommendation.
The
Board issued an Interim Order on October
9,
1975 requiring
tinarco
to submit additional information.
On October
30,
Unarco waived,
for 90 days,
the 90-day decision requirement.
tJnarco filed
its Supplemental Petition before this Board on
December
18,
1975,
and further waived the decisional date
on January
9,
1976.
On January
28, 1976 the Agency filed
an Amended Recommendation
in which the Agency recommended
that a variance be granted.
The facility
in question
is a porcelain-on-steel
manufacturing plant located west of Paris, Illinois,
in
Edgar County.
The plant employs 35-hourly and five salaried
personnel,
manufacturing procelain—on-steel
sinks for the
housing industry and certain porcelain component parts.
The
specific portion of this process that occasioned the instant
petition is the spray application of finely milled porcelain
enamel onto steel.
During the spraying operation some of
these particles are emitted from the spray booths into the
atmosphere, via stacks 32 feet high,
in violation of the
particulate limits of Rule 203(a).
21—45
—2—
Unarco
is presently
in the process of installing a system
designed to collect,
at
a 99.9
efficiency, particles above
1/2 micron in size.
(Page
4 of Exhibit II)
The projected cost
is $178,091.00.
As Unarco states that the emitted dust consists
only of particles of 3.75 microns and above
(page
3 of Petition),
there can be no doubt that the completed system would bring
Unarco into compliance with particulate regulations.
In fact,
the processed air is
to be recirculated back into the plant
(Page
1, Exhibit
1).
Unarco shows that its emissions are not causing or contributing
to a violation of Ambient Air Quality Standards
in Bloomington
or Champaign,
Illinois
(Page
5 of Petition).
While these data
are not conclusive as to the air quality near Unarco’s plant,
the small amount of the emissions
(2.1 lbs/hr.
from each of
3
spray booth assemblies)
and the absence of any citizen complaints
indicate no reason to suspect any significant adverse impact on
ambient air quality according to the Agency
(See page
5 of
Recommendation)
The remaining issue is whether Unarco’s delay in compliance
(the regulation was effective as of December 31,
1973)
has been
self—imposed so as to negate Unarco’s claim of unreasonable or
arbitrary hardship.
On page
8 of its Supplemental Petition
Unarco comments:
“This has not been
a situation of a manufacturer
claiming a necessity to choose between either increased
corporate profits or the spending of extra profits on
pollution control devices.
Instead,
it is
a manufacturer
struggling
to get an operation off the ground, while
at the same time attempting to meet the various environmental
requirements.”
Unarco has asserted facts which would tend to support this
generous language.
Indeed, Unarco speaks of several crisis
situations,
since it obtained the plant
in February 1973, which
required serious evaluation and justification for keeping the
plant open.
In early summer of 1974 Unarco became aware that
it
would lose its prime customer.
During May,
1975, Unarco
was ordered by its home office to evaluate the effects of
a
natural gas cutback.
However,
from the period of February, 1973
to early summer
of 1974 Unarco states that its failure to act on the problem
in question was due
to the allocation of its financial and
manpower resources to three other environmental projects which
were of greater consequence.
Knowing that it was
in violation
of Rule 203(a), Unarco decided to:
1) not remedy the problem,
and
2)
not apply for
a variance.
Unarco has certainly not
demonstrated that it could not have afforded the cost of
21
—~46
—3—
preparing and filing
a petition for variance.
The evidence submitted,
voluminous
as
it
is, does not satisfactorily explain Unarco’s
failure to petition for a variance until July of 1975.
However,
Unarco appears to have been otherwise earnest in its attempts
to comply with the Board’s regulations.
It
is arguable that,
given the lack of funds to accomplish compliance,
the delay
did not cause substantial additional environmental damage.
Further, the loss of Unarco’s prime customer and decisions
on
the economic viability of this recently purchased plant do explain
substantial parts of the lengthy delay.
On balance,
the Board finds that compliance with Rule 203(a)
would have caused an unreasonable hardship for Unarco,
and
that Unarco’s delay was substantially explained.
However,
it
is not the loss of a customer or the allocation of funds
to other
projects which the Board views
in mitigation of Unarco’s failure
to take steps necessary
to obtain compliance with Rule 203(a).
The mitigating factor
is the economic hardship which was caused
by these occurrences,
These other hardships combine
to make
compliance with Rule 203 a sufficiently arbitrary and unreasonable
hardship to outweigh even Unarco’s lengthy delays.
Yet even
that finding could have been outweighed
in this case had Unarco’s
emissions constituted a more significant threat to the environment.
The Board finds that
a variance until May 15, 1976 should
allow Unarco adequate time
to diligently complete the construction
of its frit particulate collection system.
Due to the nearness
of Unarco’s completion date for the collection system,
no
performance bond will be required.
This Opinion constitutes
the Board’s findings of fact
and conclusions of
law.
ORDER
1.
Petitioner Unarco Industries,
Inc.,
is hereby granted
variance from Rule 203(a)
of the Air Pollution Control Regulations
from July
25,
1975 until May 15,
1976.
2.
Petitioner Unarco Industries,
Inc.,
shall, as a condition
of
this variance,
submit monthly reports to the Agency detailing
its progress towards completion of its compliance program.
These
progress reports shall begin on the first day of the month
following the Board Order and shall be submitted on the first
day of each month thereafter until the project
is completed.
The
21-—47
—4—
progress reports will be submitted to:
Environmental Protection Agency
Division of Air Pollution Control
Control Program Coordinator
2200 Churchill Road
Springfield,
Illinois
62706
IT
IS SO ORDERED.
I, Christan L. Moffett, Clerk of the Illinois Pollution Control
Boa~d,hereby certify the above Opinion a d Order were adopted on the
~‘__day
of April 1976 by a vote of
-
Christan L.
Moffett,
k
Illinois Pollution C
ol Board
21—48