ILLINOIS POLLUTION CONTROL BOARD
    May 23,
    1991
    VILLAGE
    OF
    GARDNER,
    )
    Petitioner,
    )
    V.
    )
    PCB 91—21
    (Variance)
    ILLINOIS
    ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    )
    Respondent.
    OPINION
    AND
    ORDER OF THE BOARD
    (by J.
    C. Marlin):
    This matter comes before the Board on the February
    1,
    1991
    filing by the Village of Gardner
    (“Gardner”)
    of a Petition for
    Variance (“Pet.”).
    Gardner seeks relief from 35 Ill.
    Adm. Code
    602.105(a),
    “Standards for Issuance”,
    and 602.106(b),
    “Restricted
    Status”, to the extent those rules relate to violation by
    Gardner’s public water supply of the
    5 picocuries per liter
    (“pCi/i”) combined radjum-226 and radium-228 standard and the 15
    pCi/i gross alpha particle activity standard of 35
    Iii.
    Adm. Code
    Subtitle F.1
    Variance is requested for three years.
    The Illinois Environmental Protection Agency (“Agency”)
    filed its Variance Recommendation (“Rec.”)
    on March 8,
    1991.2
    The Agency recommends that variance be granted, subject to
    conditions.
    Hearing was waived and none has been held.
    Based on the record before it, the Board finds that Gardner
    has presented adequate proof that immediate compliance with the
    Board regulations at issue would impose an arbitrary or
    unreasonable hardship.
    Accordingly, the variance will be
    granted,
    subject to conditions consistent with this Opinion and
    as set forth in the attached Order.
    1
    The standard for combined radium was formerly found at 35
    Ill.
    Adm. Code 604.301(a); effective September 20,
    1990 it was
    recodified to 35
    Ill. Adm. Code 611.330(a).
    The standard for
    gross alpha particle activity was formerly found at 35 Ill. Adm.
    Code 604.301(b); effective September 20,
    1990
    it was recodified
    to 35 Ill. Adm. Code 611.330(b).
    (See,
    Illinois Register, Volume
    14,
    Issue 40, October 5,
    1990).
    2
    The Agency’s filings were accompanied by motions to file
    instanter.
    The motions were granted on March 14,
    1991.
    122—255

    —2—
    BACKGROUND
    Gardner is a municipality located in Grundy County.
    Among
    other services, Gardner provides potable water supply and
    distribution to a population of approximately 1322 residents and
    33 industries and businesses
    (Pet. ¶6).
    Gardner’ water supply
    system is a well system drawn from four wells,
    two deep and two
    shallow, plus pumps and distribution facilities (~. ¶8).
    The
    deepest well is the main source of the elevated combined radium
    and gross alpha concentrations (~. ¶12).
    The most recent analyses of Gardner’s water supply reported
    a combined radium concentration of 15.5 pCi/i
    (Rec.
    ¶11)
    and a
    gross alpha particle concentration of 21.1 pCi/i
    (a.).
    That
    analyses was dated July 17,
    1990.
    REGULATORY FRAMEWORK
    In recognition of a variety of possible health effects
    occasioned by exposure to radioactivity, the United States
    Environmental Protection Agency
    (“USEPA”) has promulgated
    a
    maximum concentration limit for drinking water of
    5 pCi/l
    of
    combined radium-226 and radium-228 and 15 pCi/l of gross alpha
    particle activity.
    Illinois subsequently adopted these same
    limits as the maximum allowable concentrations under Illinois
    law.
    Pursuant to. Section 17.6 of the Illinois Environmental
    Protection Act
    (Ill. Rev.
    Stat.
    1989,
    ch.
    111
    ½,
    par. 1017.6),
    any revision of the
    5 pCi/i standard by the USEPA will
    automatically become the standard in Illinois.
    The action that Gardner requests here is ~
    variance from
    the maximum allowable concentrations for either radium or gross
    alpha particle activity.
    Regardless of the action taken by the
    Board
    in the instant matter,
    these standards will remain
    applicable to Gardner.
    Rather, the action Gardner requests
    is
    the temporary lifting of prohibitions imposed pursuant to 35 Ill.
    Adm. Code 602.105 and 602.106.
    In pertinent part these Sections
    read:
    Section 602.105
    Standards for Issuance
    a)
    The Agency shall not grant any construction or
    operating. permit required by this Part unless
    the
    applicant submits adequate proof that the public water
    supply will be constructed, modified or operated so as
    not to cause a violation of the Environmental
    Protection Act
    (Ill. Rev. Stat.
    1989,
    ch.
    ill
    ¼, pars.
    1001 et seq.)
    (Act), or of this Chapter.
    Section 602.106
    Restricted Status
    b)
    The Agency shall publish and make available to the
    public,
    at intervals of not more than six months,
    a
    122—256

    —3—
    comprehensive and up—to—date list of supplies subject
    to restrictive status and the reasons why.
    Illinois regulations thus provide that communities are
    prohibited from extending water service, by virtue of not being
    able to obtain the requisite permits,
    if their water fails to
    meet any of the several standards for finished water supplies.
    This provision is a feature of Illinois regulations not found in
    federal law.
    It is this prohibition which Gardner requests be
    lifted.
    Moreover, grant of the requested variance would not
    absolve Gardner from compliance with the combined radium or gross
    alpha particle activity standards,
    nor insulate Gardner from
    possible enforcement action brought for violation of those
    standards.
    In consideration of any variance, the Board determines
    whether
    a petitioner has presented adequate proof that immediate
    compliance with the Board regulations at issue would impose an
    arbitrary or unreasonable hardship
    (Ill. Rev.
    Stat.
    1989,
    ch.
    111
    ¼,
    par.
    1035(a)).
    Furthermore, the burden is upon the petitioner
    to show that its claimed hardship outweighs the public interest
    in attaining compliance with regulations designed to protect the
    public (Willowbrook Motel v. Pollution Control Board
    (1977),
    135
    Ill.App.3d,
    481 N.E.2d, 1032).
    Only with such showing can the
    claimed hardship rise to the level
    of arbitrary or unreasonable
    hardship.
    Lastly,
    a variance by its nature is a temporary reprieve
    from compliance with the Board’s regulations
    (Monsanto Co.
    v.
    IPCB
    (1977),
    67 Ill.2d 276,
    367 N.E.2d 684), and compliance is to
    be sought regardless of the hardship which the task of eventual
    compliance presents an individual polluter
    (u.).
    Accordingly,
    except in certain special circumstances,
    a variance petitioner is
    required,
    as a condition to grant of variance, to commit to a
    plan which is reasonably calculated to achieve compliance within
    the term of the variance.
    PREVIOUS VARIANCE AND COMPLIANCE PROGRAM
    Gardner originally filed for a variance on April 2,
    1985
    (PCB 85-42) but this petition was withdrawn on June 27,
    1985.
    Following withdrawal of the petition, on September 30,
    1987,
    Gardner entered into a Letter of Commitment with the Agency.
    In the Letter of Commitment Gardner obligated itself to achieve
    full compliance on or before July 10,
    1991
    (Pet.
    ¶13).
    Gardner
    will be unable to achieve compliance on that date for the reasons
    specified below.
    Gardner has complied with the Letter of Commitment to the
    extent that it has hired a professional engineer, filed an
    Interim Compliance Report and a Detailed Compliance Report,
    enacted an ordinance and sealed off certain drains
    (Pet.
    ¶24).
    Gardner has not complied with the deadlines contained in the
    122—257

    —4—
    Letter of Commitment because the analyses of the prospective
    methods of compliance has taken longer than expected
    (Rec.
    ¶18).
    Gardner has considered several alternatives, and the costs of
    those alternatives,
    for achieving compliance.
    Those alternatives
    include cooperative water systems (at least $1.1 million), deep
    well blending
    (at least $150,000 per well),
    ion exchange
    treatment (at least $1.2 million), reverse osmosis treatment
    (at
    least $1.8 million), and shallow well blending (at least $1.8
    million)
    (Pet. ¶15 and ¶24).
    At this time, Gardner has not
    determined which alternative will be implemented but prefers the
    deep well blending option as the most cost efficient solution.
    Gardner has hired outside consultants for review and evaluation
    of the alternatives and for preparation of recommendations
    (Pet.
    ¶17).
    During the term of the proposed variance, Gardner proposes
    to continue the quarterly sampling program and to, when feasible,
    blend water using the new deep well(s).
    In addition, Gardner
    plans on a schedule which will begin construction no later than
    one year from the grant of the variance and complete construction
    no later than two years from grant of the variance (Pet.
    ¶26).
    Before construction begins Gardner proposes to 1)
    immediately
    hire professional assistance to complete investigation of
    compliance options,
    2) complete the investigation within three
    months of the grant of the variance,
    3)
    apply for all necessary
    construction permits within six month from the grant of the
    variance,
    and
    4)
    advertise for bids within three months after the
    issuance of each construction permit
    (Pet.
    ¶26).
    HARDSHIP
    Gardner contends that denial of variance would constitute an
    arbitrary or unreasonable hardship.
    It notes, among other
    matters, that:
    Failure to obtain a variance means that all
    construction within the petitioner’s service area
    requiring the extension of the water supply system,
    could not resume.
    This hurts prospective home
    purchasers as well as business developers and
    Petitioner’s tax base.
    (Pet.
    ¶28).
    The Petitioner could be forced to proceed with the
    design and construction of treatment facilities at its
    well site which will probably be duplicitous or
    unnecessary when blended water from its new well or
    wells becomes available.
    (Pet.
    ¶29).
    The Agency also contends that denial of variance would
    constitute an arbitrary or unreasonable hardship
    (Rec.
    ¶20).
    12 2—258

    —5—
    PUBLIC INTEREST
    Although Gardner has not undertaken a formal assessment of
    the environmental effect of its requested variance, it contends
    that there will be
    little., or no adverse impact caused by the
    granting of variance
    (Pet.
    ¶ 23).
    The Agency contends likewise
    (Rec.
    ¶16).
    In support of its contention,
    the Agency references
    testimony presented by Richard E.
    Toohey,
    Ph.D. of Argonne
    National Laboratory at the hearings held on July 30 and August 2,
    1985 in R85-14, Proposed Amendments to Public Water Supply
    Regulations,
    35 Ill. Adm. Code at 602.105 and 602.106 and to
    updated testimony presented by Dr. Toohey in the Board’s hearing
    on the Braidwood variance, PCB 89-212.
    (Rec.
    ¶15).
    The Agency believes that while radiation at any level
    creates some risk,
    the risk associated with Gardner’s water
    is
    very low
    (Rec.
    ¶14).
    In summary, the Agency states:
    The Agency believes that the hardship resulting
    from denial of the recommended variance from the effect
    of being on Restricted Status would outweigh the injury
    of the public from grant of that variance.
    In light of
    the cost to the Petitioner of treatment of its current
    water supply, the likelihood of no significant injury
    to the public from continuation of the present level of
    the contaminants in question in the Petitioner’s water
    for the limited time period of the variance, and the
    possibility of compliance with a new MCL standard by
    less expensive means if the standard is revised upward,
    the Agency concludes that denial of a variance from the
    effects of Restricted Status would impose an arbitrary
    or unreasonable hardship upon Petitioner.
    The Agency observes that this grant of variance from
    restricted status should affect only those users who
    consume water drawn from any newly extended water
    lines.
    This variance should not affect the status of
    the rest of Petitioner’s population drawing water from
    existing water lines,
    except insofar as the variance by
    its conditions may hasten compliance.
    In so saying,
    the Agency emphasizes that it continues to place
    a high
    priority on compliance with the standards.
    (Rec.
    ¶29 and ¶30)
    CONCLUSION
    The Board finds that,
    in light of all the facts and
    circumstances in this case, denial of variance would impose an
    arbitrary or unreasonable hardship upon Gardner.
    The Board also
    agrees with the parties that no significant health risk will be
    incurred by persons who are served by any new water main
    extensions, assuming that compliance is timely forthcoming.
    122—259

    —6—
    The Board notes that timely compliance by Gardner may be
    affected by pending USEPA action to promulgate new standards for
    radionuclides in drinking water.
    USEPA recently proposed to
    publish its Notice of Proposed Rulemaking
    (“NPRN”)
    in June 1991,
    and expects to issue final action on new radionuclide standards
    in April,
    1993
    (56 Fed. Reg. 18014, April 22,
    1991).
    New
    radionuclide standards from USEPA could significantly alter
    Gardner’s need for a variance or Gardner’s alternatives for
    achieving compliance.
    In recognition of this situation, the
    Board’s variance will contain suitable tiinefraines to account for
    the effects of.any USEPA alteration
    (or notice of refusal to
    alter)
    of the radium or gross alpha standards.
    Aside from these
    changes in the schedule, the dates and conditions of this
    variance follow the proposal of the Agency contained in its
    Recommendation (Rec.
    ¶31).
    Gardner is to bear in mind that today’s action is solely a
    grant of variance from standards of issuance and restricted
    status.
    Gardner is not being granted variance from compliance
    with either the radium or gross alpha particle standard, nor does
    today’s action insulate Gardner in any manner against enforcement
    for violation of these standards.
    The variance is granted, with conditions,
    for a period of
    four years from the grant of variance or for two years after
    USEPA action or until compliance is shown, whichever is earliest.
    This Opinion constitutes the Board’s findings of fact and
    conclusions of law in this matter.
    ORDER
    Petitioner, Village of Gardner,
    is hereby granted variance
    for its water system from 35 Ill. Adm. Code 602.105(a), Standards
    of Issuance, and 602.106(b), Restricted Status,
    as they relate to
    the standards for radium and gross alpha particle activity in
    drinking water of 35
    Ill. Adm. Code.Subtitle F,
    subject to the
    following conditions:
    (A)
    For the purposes of this Order,
    the date of USEPA
    action shall consist of the earlier of the:
    1)
    Effective date on any regulation promulgated by
    the U.S. Environmental Protection Agency (“USEPA”)
    which amends the maximum concentration level for
    combined radium, either of the isotopes of radium,
    or the method by which compliance with a radium
    maximum concentration level is demonstrated;
    or
    2)
    Date of publication of notice by the USEPA that no
    amendments to the
    5 pCi/l combined radium standard
    122—260

    —7—
    or the method for demonstrating compliance with
    the
    5 pCi/i standard will be promulgated.
    (B)
    Variance shall terminate on the earliest of the
    following dates:
    (1)
    When analysis pursuant to 35 Ill. Adm. Code
    611.720(d), or any compliance demonstration method
    then in effect,
    shows compliance with standards
    for radium and gross alpha particle activity in
    drinking water then in effect; or
    (2)
    May 23,
    1995, or
    (3)
    Two
    years following the date of USEPA action.
    (C)
    Compliance shall be achieved with any standards for
    radium and gross alpha particle activity then in effect
    no later than the date on which this variance
    terminates.
    (D)
    In consultation with the Illinois Environmental
    Protection Agency (“Agency”), Petitioner shall continue
    its sampling program to determine as accurately as
    possible the level of radioactivity in its wells and
    finished water.
    Until this variance terminates,
    Petitioner shall collect quarterly samples of water
    from its distribution system at locations approved by
    the Agency.
    Petitioner shall composite the quarterly
    samples for each location separately and shall have
    them analyzed annually by a laboratory certified by the
    State of Illinois for radiological analysis so as to
    determine the concentration of radium-226, radium-228,
    and gross alpha particle activity.
    At the option of
    Petitioner the quarterly samples may be analyzed when
    collected.
    The results of the analyses shall be
    reported within 30 days of receipt of the most recent
    result to:
    Illinois Environmental Protection Agency
    Compliance Assurance Section
    Division of Public Water Supplies
    P.O. Box 19276
    2200 Churchill Road
    Springfield, Illinois 62794—9276
    (E)
    Within three months of USEPA action or 24 months after
    this grant of variance, whichever is sooner, Petitioner
    shall apply to the Agency at the address below for all
    permits necessary for construction of installations,
    changes or additions to the Petitioners’s public water
    supply needed for achieving compliance with the maximum
    allowable concentration for combined radium and gross
    122—261

    —8—
    alpha particle activity,
    or with any standards for
    radium in drinking water then in effect:
    Illinois Environmental Protection Agency
    Division of Public Water Supply
    Permit Section
    2200 Churchill Road
    Springfield,
    Illinois 62794—9276.
    (F)
    Within
    3 months after each ‘construction permit is
    issued by the Agency, Petitioner shall advertise for
    bids,
    to be submitted within 60 days,
    from contractors
    to do the necessary work described in the construction
    permit.
    The Petitioner shall accept appropriate bids
    within
    a reasonable time.
    Petitioner shall notify the
    Agency, at the address in condition (E), within 30 days
    of each of the following actions:
    1)
    advertisement for
    bids,
    2)
    names of successful bidders, and 3) whether
    Petitioner accepted the bids.
    (G)
    Construction allowed on said construction permits shall
    begin within a reasonable time of bids being accepted.
    In any case, construction of all installations, changes
    or additions necessary to achieve compliance with the
    maximum allowable concentration of combined radium and
    gross alpha particle activity, or with any standards
    for radium and gross alpha particle activity in
    drinking water then in effect,
    shall begin no later
    than
    6 months after USEPA action.
    Petitioner shall
    complete construction no later than three years from
    the grant of variance.
    (H)
    Pursuant to 35 Ill. Adm. Code 611.851(b),
    in its first
    set of water bills or within three months after the
    date of this Order, whichever occurs first, and every
    three months thereafter,
    Petitioner shall send to each
    user of its public water supply a written notice to the
    effect that Petitioner has been granted by the
    Pollution Control Board a variance from 35
    Ill.
    Adm.
    Code 602.105(a)
    Standards of Issuance and 35 Ill. Adm.
    Code 602.106(b)
    Restricted Status,
    as they relate to
    the radium and gross alpha particle activity standards.
    (I)
    Pursuant to 35
    Ill. Adm. Code 611.851(b),
    in its first
    set of water bills or within three months after the
    date of this Order, whichever occurs first, and every
    three months thereafter,
    Petitioner shall send to each
    user of its public water supply a written notice to the
    effect that Petitioner is not in compliance with the
    standards for radium and gross alpha particle activity.
    The notice shall state the average content of radium
    and gross alpha particle activity in samples taken
    122—262

    —9--
    since the last notice period during which samples were
    taken.
    (J)
    Until full compliance is achieved, Petitioner shall
    take all reasonable measures with its existing
    equipment to minimize the level of combined radium-226
    and radium-228, ‘and gross alpha particle activity in
    its finished drinking water.
    (K)
    Petitioner shall provide written progress reports to
    the Agency at the address below every six months
    concerning steps taken to comply with the paragraphs of
    this Order.
    Progress reports shall quote each of said
    paragraphs and immediately below each paragraph state
    what steps have been taken to comply with each
    paragraph.
    Illinois Environmental Protection Agency
    Division of Public Water Supply
    Field Operations Section
    2200 Churchill Road
    Springfield, Illinois 62794—9276.
    Within 45 days of the date of this Order, Petitioner shall
    execute and forward to Stephen C.
    Ewart,
    Division of Legal
    Counsel, Illinois Environmental Protection Agency,
    2200 Churchill
    Road, Post Office Box 19276, Springfield, Illinois 62794—9276,
    a
    Certification of Acceptance and Agreement to be bound to all
    terms and conditions of this variance.
    The 45-day period shall
    be held in abeyance during any period that this matter is being
    appealed.
    Failure to execute and forward the Certificate within
    45 days renders this variance void and of no force and effect as
    a shield against enforcement of rules from which variance was
    granted.
    The form of said Certification shall be as follows:
    CERTIFICATION
    I
    (We),
    hereby accept and agree to be bound by all terms and conditions
    of the Order of the Pollution Control Board in PCB 91-21 May
    —,
    1991.
    Petitioner
    Authorized Agent
    Title
    122—263

    —10—
    Date
    Section 41 of the Environmental Protection Act,
    Ill.
    Rev.
    Stat. 1989 ch.
    111
    ½
    par.
    1041, provides for appeal of final
    Orders of the Board within 35 days.
    The Rules of the Supreme
    Court of Illinois establish filing requirements.
    IT IS SO ORDERED.
    Board Member B. Forcade dissented.
    I, Dorothy N. Gunn, Clerk of the Illinois Pollution Control
    Board, hereby certify that the above Opinion and Order was
    adopted on the
    ~-~“
    day of
    ___________________,
    1991, by
    a vote of
    _____________
    Dorothy N. 9~nn,Clerk
    Illinois Po~/LutionControl Board
    122—264