ILLINOIS POLLUTION CONTROL
BOARD
September 7,
 1978
IN THE
MATTER
OF:
 )
)
PROPOSED DETERMINATION OF
 )
NO SIGNIFICANT ECOLOGICAL
 )
 PCB 78-61
DAMAGE FOR THE QUAD CITIES
 )
GENERATING STATION.
 COMMONWEALTH
 )
EDISON
COMPANY.
INTERIM
ORDER
OF THE
 BOARD
 (by Mr. Dumelie):
On
 March 8,
 1978, Commonwealth Edison Company
 (Edison)
 filed
this Petition for a determination, as required by Rule 203(i) (5)
of the Board’s Water Regulati~ons,that thermal discharges from
Edison’s Quad Cities Generating Station have not caused and cannot
be reasonably expected to cause significant ecological damage to
the receiving waters of the Mississippi River.
 A hearing in this
matter was held on July 19, 1978.
The Board finds that Edison’s Petition is insufficient, because
it fails to meet the requirements of Rule 602(c) (2)
 and
 (3)
 of
the Board’s Procedural Rules.
 The Rule provides,
 in pertinent
parts:
“The following information, where applicable,
 shall be filed:
(c)
 Plume Studies
2.
 Theoretical plume studies for all four seasons for
 typical and worst case conditions.
Worst case
conditions shall be identified as worst conditions
of plant load factor, precipitation, ambient water
temperature, air temperature;
 such studies~shall
consider the frequency of occurrence and their
joint probabilities of occurrence;
 and,
3.
 Theoretical plume studies which identify isotherms
at
30
Fahrenheit intervals down to ambient temper-
ature indicating three dimensional effects.”
31—371
—2—
Since
 a
 hearing
 in
 this
 matter
 has
 already
 been
 held,
 the
Board
 remands
 the
 Petition
 to
 Edison
 with
 instructions
 to
 supply
the
required
 information
 in
 an
 Amended
 Petition.
IT
 IS
 SO
 ORDERED.
I,
 Christan
 L.
 Moffett,
 Clerk
 of
 the
 Illinois
 Pollution
 Control
Board, hereby certify
 the
 above
 Order
 was
 adopted
 on
 the
 7~
day of ~~-j~~i
 ,
 1978
 by
 a
 vote
 of
 ~/.c
~
Christan
 L. Moffett )Clerk
Illinois Pollution~&ontrolBoard