ILLINOIS POLLUTION CONTROL BOARD
September
18,
1975
CITY OF MARION,
Petitioner,
v.
)
PCB 75—220
ENVIRONMENTAL PROTECTION AGENCY,
Respondent.
OPINION AND ORDER OF THE BOARD
(by Mr. Dumelie):
The City of Marion
(Petitioner)
filed a variance petition
on May 23,
1975,
seeking relief from Rule
203(c)
of Chapter
3:
Water Pollution Regulations,
as applied
to phosphorus.
On July 18,
1975,
pursuant to a Board Order, Petitioner
submitted additional information concerning algae blooms
in Crab Orchard Lake and their effect upon the dissolved
oxygen
in benthic organisms of the Lake.
The Environmental
Protection Agency
(Aaency)
filed its Recommendation
to
~rant
the varianc3,
on August 19,
1975.
No hearing was held.
Petitioner
is a municipal corporation and operates
four independent treatment plants:
a 1.3 MGD trickling
filter plant, a single cell lagoon,
and two 3—cell lagoon
systems with chlorination.
Petitioner
is currently under
a Board Order to upgrade its trickling filter plant, and has
failed
to comply with this Order.
The Agency has sought
enforcement in Circuit Court.
Petitioner has accepted a grant by the Agency for the
replacement of its existing facilities with a new tertiary
treatment plant.
The proposed plant will remove phosphorus
through a liquid alum chemical process.
Petitioner states
that its new plant will meet all of the Chapter
3 effluent
standards.
However,
the proposed facility will discharge to
Crab Orchard Creek,
a tributary
to Crab Orchard Lake.
The
phosphorus concentration in Crab Orchard Creek as it enters
Crab Orchard Lake periodically exceeds 0.05 mg/i.
In addition,
Petitioner’s plant effluent will constitute the principal
flow in Crab Orchard Creek below its confluence with West End
Creek during 7-day,
l~1_yearlow flow conditions.
Rule 402
18
—
561
—2—
of Chapter
3 requires that no effluent shall, alone or in
combination with ‘ther sources, cause a violation of any
applicable water quality standards.
Where
a violation exists,
the Agency may require the discharger
to meet whatever effluent
limits are necessary to insure compliance with the water
quality standards.
Since Petitioner’s proposed discharge
will be tributary to Crab Orchard Creek,
a tributary to
Crab Orchard Lake,
Rule 402
is applicable.
Petitioner’s
effluent must not contribute to a violation of the Rule 203(c)
water quality standa:d for phosphorus.
Petitioner’s effluent
is limited
to the Rule
203(c)
standard of 0.05 mg/i phosphorus
and it is from this standard that Petitioner
seeks a variance.
Petitioner s?eks
a
limitation of 1.5 mg/i on its phosphorus
effluent.
Petitioner claims
it
is not technically feasible to
consistently meet the 0.05 mg/i standard with existing removal
technology.
Petitioner
also states that as an alternative, diversion
4.5 miles
to another watershed with a higher allowable standard
would cost $1,050,000 and thus be prohibitively expensive
compared to chemical removal methods.
Petitioner has not considered land application as an
alternative.
The Agency indicates
in its Recommendation
that since the Petitioner is under a Board Order,
“to install
and operate upgraded improved sewage treatment facilities
..
.“,
and since Petitioner accepted an Agency grant offer which
was based upon
a ‘leterminatiori by the Agency of the most
cost—effective means of treatment,
that it would be
inappropriate to consider land application at this time.
The Board does not agree that it is for the Agency to make
any final “cost-effective” determinations binding upon the
Board.
Petitioner states that its chemical removal system will
cost approximately $19,700
a year to remove phosphorus to
a level of 1.5 mg/i.
Petitioner contends that to remove
phosphorus
to the 0.05 mg/l level would cost an additional
$29,222 for a tot~1yearly removal cost of $48,922.
Petitioner
alleges that this additional cost would be prohibitive.
Petitioner fails
to present data beyond
a mere assertion,
that this cost increase would be a financial hardship.
Petitioner presents no data as
to the cost of reaching
a removal
level of
).
mg/l phosphorus.
The Agency states
in its Recommendation that while it
does not believe it is chemically feasible to remove phosphorus
consistently to a level of 0.05 mg/l,
that Petitioner can
reach a level of
1 mg/i simply by adding additional chemicals.
The Agency states that the proper dosage with the proposed
equipment can best be determined after the facility commences
operation.
The Ag~ncyadmits that the purchase of alum
and polymers
is a major cost in phosphorus removal.
18— 562
—3--
The Agency Recommendation notes that given the 2.5 MGD
average design flow of Petitioner’s proposed facility, with
an approximate phosphorus concentration of
1 mg/l, the
Petitioner would discharge about 7,619 pounds of phosphorus
per year.
The concentration of phosphorus found in Crab
Orchard Creek, approximately 1-1/2 miles south of Marion,
below West End Creek which carries Petitioner’s trickling
filter plant effluent,
averaged 1.71 mg/i in 1974 and 1975.
The Agency states in its Recommendation that the
U.S.
Environmental Protection Agency
(U.S.
EPA)
estimates
that Petitioner currently contributes 35,450 pounds per year
of phosphorus
to Crab Orchard Lake,
or 22
of the annual
influx.
The U.S. EPA also indicates that Crab Orchard Lake may
be nitrogen, rather than phosphorus,
limited since the
nitrogen:phosphorus ratio is
4.79:1.
The Agency notes that two eutrophication studies have
been made of Crab Lake.
Both found algae in various numbers
in the Lake.
Although there is evidence that blooms
do occur about twice
a year, neither study clearly demonstrates
the presence of algae blooms.
Nor do the studies reveal
oxygen depletion arising from algae die-off.
No hypolimnion study has been
conducted on Crab Lake.
The Agency
indicates that an adequate study, would not be
justified in this proceeding as it could not be accomplished
within the
30 days which the Agency has to answer
a variance
petition, and would be an unreasonable financial hardship
upon the Petititoner.
The Agency st~atesif Petitioner
is allowed a variance at
1 mg/i of phospho~-us, the anticipated environmental imapct in
Crab Orchard Lake will be minimal,
as the Lake appears
to be
limited by nitrogen rather than phosphorus
at the present.
The Board finds that based on Petitioner’s existing
obligation
as to upgrade its sewage treatment facilities,
the
inclusion in the proposed treatment facility of a phosphorus
removal system,
the economic and administrative constraints
which preclude alternative removal methods and the projected
minimal
impact of Pet;tioner’s discharge upon Crab Orchard
Lake at a level of
1 mg/i, Petitioner would suffer an arbitrary
and unreasonable financial hardship
if compelled to meet
Rule
203(c)
at the present time.
However, Petitioner has
failed to clearly demonstrate economic hardship as to cost
increments
in achieving compliance below a level of 1.5 mg/i.
In addition,
the Agency
indicates
a level of
1 rng/l phosphorus
can be reached by
a higher chemical dosage.
In light of
this information and Petitioner’s position as a major contributor
of phosphorus to Crab Orchard Lake,
the Board finds that
a
18
—
563
—4—
limit of
1 mg/i phcsphorus maybe justified.
Petitioner will
be required to install equipment capable of achieving
1 mg/i.
Since Crab Lake may be nitrogen-limited, operation at 1.5
tfIg/l
phosphorus
in the effluent will be permitted.
In future
variance or regulatory proceedings, the needed research
can be presented ior further determinations.
Because of the interrelationship
in the protection of
water quality between the relief sought
——
a variance
from the phosphorus standard
--
and other pollutants
such
as BOD and suspended solids, we will condition the grant
of this variance with the operation of Petitioner’s sewage
treatment plant so as to afford the best practicable
treatment in accordance with the prior Board Order in
PCB 71—25.
Because Petitioner
is required to obtain an NPDES permit,
the Board may gra~ita variance for up to a five year period.
The Board has determined that Petitioner should be granted a
variance until July
1,
1977.
This Opinion constitutes the Board’s findings of fact
and conclusions of
law.
ORDER
The Pollution Centrol Board hereby grants the City of
Marion a variance from Rule 203(c)
of Chapter
3 until
July
1,
1977 subject to the following conditions:
1.
Petitioner’s proposed waste treatment facility
effluent shall be limited in its phosphorus discharge to
1.5mg/i but shall be capable of achieving 1.0 rng/l
if necessary.
2.
Petitioner
shall adhere to the project schedule set
forth on the first page of its original petition for
variance,
submitted to the Board on May 27,
1975.
3.
Petitioner
shall maintain its present sewer treatment
facility so as to
E’fford the best practicable treatment and
in accordance with the dictates of the prior Board Order
(PCB 71-25)
to wit:
a.
The City of Marion shall operate its existing
waste treatment facilities
in such manner that
no effluent shall exceed
25 mg/i BOD or 25 mg/l
suspended solids except that wet weather flows in
excess of 1.3 MGI’ shall not be subject to this
requirement.
Chlorine residual in the treated
effluent shall be maintained between
0.5 mg/i and
1.0 mg/i during this interim period.
18
—
564
—5—
b.
The City of Marion shall provide suitable
sampling taps for all effluent and bypass lines
in
accordanc’~ewith the provisions of Rule
502
of the Watei Pollution Control Regulations
within
30 days of receipt of this Order.
c.
The City of Marion shall submit monthly
progress reports to the Environmental Protection
Agency.
Said piogress reports shall commence on
September
23, 1975 and shall provide details of
Petitioner’s progress toward completion
of the
new waste treatment facilities.
4.
Within
35 days after the date of the Board Order herein,
the City of Maricn shall execute and submit to the Manager,
Variance Section, Division of Water Pollution Control, Illinois
Environmental Protection Agency,
2200 Churchill Road, Springfield,
Illinois,
62706, a Certification of Acceptance and agreement to
be bound
to all terms and conditions of the variance.
The form
of said certification shall be
as follows:
CERTIFICATION
I
(We),
_______________________
having read and fully
understanding the Order of the Illinois Pollution Control Board
in PCB 75-220 here3y accept said Order and agree to be bound
by all terms and ~-‘onditionsthereof.
Signed
_______________________
Title _________________________
Date ____________________________
I,
Christan L. Moffett, Clerk of the Illinois Pollution
Control
Board,
hei’eJ~zr certify the above Opinion and Order were
adopted on the
/J’
day of September,
1975 by a vote of
1-0
Christan
L.
offet
rk
Illinois Pollution
ontrol Board
18
—
565