ILLINOIS POLLUTION CONTROL BOARD
March 14,
1986
COMMONWEALTH EDISON COMPANY,
(Joliet Generating Station
)
Units
7
& 8),
Petitioner,
v.
)
PCB 86—39
ILLINOIS ENVIRONMENTAL
)
PROTECTION AGENCY,
)
Respondent.
OPINION AND ORDER OF THE BOARD
(by W.J. Nega):
This provisional variance request comes before the Board
upon
a March 14,
1986 Recommendation of the Illinois
Environmental Protection Agency (Agency).
The Agency recommends
that
a 30—day provisional variance be granted
to the Petitioner
from 35
Ill.
Adm.
Code 304.124
as
it pertains
to total suspended
solids
(TSS)
and
from 35
Ill. Adm. Code 304.102(a)
as
it relates
to emergency discharges from the coal pile area runoff basin
for
Units
7 and
8 at Commonwealth Edison Company’s Joliet Generating
Station.
(Rec.
1).
Commonwealth Edison Company owns and operates
a coal—fired
electrical generating station known as the Joliet Generating
Station which
is located
on the Des Plaines River
at Route
6 and
Larkin Avenue
in Joliet,
Illinois.
The Petitioner’s coal pile
area runoff basin
is served by an emergency discharge point
system.
Flows
into the coal pile area runoff basin are
from
eight primary sources which include:
(1) Unit
7
and
8 coal pile
runoff;
(2) Unit
7 and 8 drive house
floor drains;
(3) Unit
7
roof drains;
(4) Unit
7
and
8 turbine room floor drains;
(5)
the
coal cracker sumps
(both east and west);
(6)
the crusher building
sump;
(7) the demineralized water tank area runoff, and
(8) the
equipment storage building floor
and roof drains.
Intermittent
flows result, with the volume of water
being largely dependent on
the amount of rainfall during
a given time period.
(Rec.
1).
At the present time,
the coal pile area runoff treatment
system consists of two 500 gallon per minute
(gpm) pumps.
These
two pumps transfer the effluent from the coal pile area runoff
basin
to oil coalescers
for further treatment.
The water
is
subsequently discharged
to the Des Plaines River.
During heavy
rainfall, the volume
of water entering the coal pile area runoff
basin rapidly increases.
On such occasions,
the filters
in the
oil coalescers become clogged because of the high amounts of
solids
in the incoming water.
This clogging of the oil coalescer
—2—
filters decreases the
flow rate through the filters at
the
precise time when maximum flow rate is most needed.
Accordingly,
the coal pile area runoff basin overflows through the emergency
overflow line
to the Des Plaines River during periods of very
heavy rainfall.
(Rec.
1).
The Petitioner
installed
a 1,000 gallon per minute pump
to
transfer water from the runoff basin
to the ash pond for
treatment as an
interim solution
to these troublesome emergency
discharges.
However, experience has shown that
a more permanent
solution
to this problem
is needed.
Therefore,
Commonwealth Edison Company
is requesting
a 30—
day provisional variance
to allow sufficient time to install
two
4,000 gallon per minute submersible pumps on
a concrete platform
in the coal pile area runoff basin.
These
two 4,000
gprn pumps
will discharge through
a new 16 inch line to the Petitioner’s ash
pond, thereby hopefully solving
the company’s emergency discharge
problem.
(Rec.
1—2).
The Petitioner
anticipates
that approximately half of
the
coal pile area runoff basin will need
to be dewatered and cleared
of sludge
in order
to install the necessary submersible pumps
and
concrete platform.
Although the Petitioner
intends
to process as
much water
as possible through the normal treatment process
(or
transfer
such water
to the ash pond for subsequent processing)
during
the term of the requested provisional variance,
the
company has asserted that the possibility of an emergency
discharge still exists and necessitates
the requested relief.
(Rec.
2).
In regard
to
the possibility of such emergency discharges,
the Agency has indicated that
it believes that the Petitioner
will
take appropriate precautions to prevent,
or
at least
minimize, any emergency discharges during the proposed variance
period.
(Rec.
2).
However, the Agency has determined
that the
Petitioner’s provisional variance request “fulfills Standard
Condition 12(b)
(Anticipated Non—compliance)
of Petitioner’s
N~PDESpermit”
and “as such,
it
is the Agency’s opinion that
Petitioner may use
this outfall
in the case of an emergency
only.”
(Rec.
2).
Thus, the Agency has concluded
that “relief
from 35
Ill. Adm. Code 309.102(a)
is unnecessary”
in
the present
case.
The Board
finds the Agency’s reasoning persuasive
in
reference to
the aforementioned matter and will therefore follow
the Agency’s recommendation not
to grant relief from Section
309.102(a)
The Agency believes that the environmental
impact of
the
proposed provisional variance will be minimal
“due to the
precautions Petitioner will
be taking during
the variance”
and
notes that there are no
federal regulations which would preclude
the granting
of the
requested relief from 35
Ill. Adm.
304.124
as
—3—
it pertains
to total suspended solids.
(Rec.
2).
The Agency has concluded that compliance with the provisions
of
35 Ill.
Adm. Code 304.124
as
it relates
to total
suspended
solids would
impose an arbitrary or unreasonable hardship upon
the Petitioner and emphasizes that “the end result of the
provisional variance will
be the solution
to
a longstanding
problem”.
(Rec.
2).
Accordingly, the Agency has recommended
that the Board grant the Petitioner
a provisional variance
from
35
Ill. Adm. Code 304.124
as
it pertains
to total
suspended
solids,
subject
to specified conditions.
Pursuant to Section 35(b)
of the Illinois Environmental
Protection Act,
the Board hereby grants the provisional variance
as recommended.
This Opinion constitutes
the Board’s findings of fact and
conclusions of law
in this matter.
ORDER
Commonwealth Edison Company
(Joliet Generating Station Units
7
&
8)
is hereby granted
a provisional variance from 35
Ill. Adm.
Code
304.124
as
it pertains
to
total suspended solids, subject
to
the following conditions:
1.
This provisional variance shall commence on March 17,
1986,
and shall continue for
30 days
or until installation of the two
4,000 gpm submersible pumps, concrete platform, and
16 inch line
to the ash pond
is completed, whichever comes
first.
2.
The Petitioner shall,
as
indicated, take all measures
necessary
to prevent or minimize any emergency discharges from
this system during
the variance period.
3.
Any emergency discharges from this system shall
be limited
to
50 mg/l TSS.
4.
The Petitioner shall notify Mr. Dan Ray of the Agency’s
Compliance Assurance Section via telephone at
217/782—9720 when
the work described above commences and when
it
is completed.
Each such notification shall be confirmed
in writing within
5
days
to:
Illinois Environmental Protection Agency
Division of Water Pollution Control
Compliance Assurance Section
2200 Churchill Road
Springfield, Illinois 62706
Attention:
Dan Ray
5.
During
the
term of this provisional variance, the Petitioner
—4—
shall
sample each emergency discharge which occurs from this
system and analyze
it
for TSS.
The results of this analysis
along with information as
to length of time the discharge
occurred and volume discharged shall
be submitted to
Mr. Dan Ray
at the address given
above
in Item #4
for each emergency
discharge that occurs from this system.
6.
During
the provisional variance period, the Petitioner
shall
submit
to the Agency
a request
to modify its NPDES Permit
#1L0064254
to include
the emergency overflow line from the coal
pile area runoff basin serving Units
7
&
8.
7.
The Petitioner shall
complete the work described
as
expeditiously as possible.
8.
The Petitioner shall
apply for
a construction permit
for
this
project.
9.
Within 10 days of the date of this Board’s Order,
the
Petitioner
shall execute
a Certificate of Acceptance and
Agreement which
shall
be sent
to Mr. James
Frost of the Agency at
the following address:
Mr. James Frost
Illinois Environmental Protection Agency
Division of Water Pollution Control
2200 Churchill Road
Springfield, Illinois 62706
This certification shall have
the following form:
CERTIFICATION
I,
(We),
,
having
read
the Order of the Illinois Pollution Control Board
in PCB 86—39,
dated
March 14,
1986,
understand and accept
the said Order,
realizing that such acceptance renders all terms and conditions
thereto binding and enforceable.
Petitioner
By:
Authorized Agent
Title
Date
—5—
10.
The Petitioner’s request
for
relief from 35 Ill.
Adm. Code
309.102(a)
is hereby denied
as unnecessary.
IT
IS SO ORDERED.
I,
Dorothy M.
Gunn, Clerk of the Illinois Pollution Control
Board, hereby certify that the above Opinion and Order was
adopted on
the
~
day of
______________,
1986 by
a vote
of
‘7—c’
Dorothy M.
unn, Clerk
Illinois Pollution Control Board