ILLINOIS POLLUTION CONTROL BOARD
    February
    27,
    1973
    CITY OF GRANITE CITY
    PCB 72—184
    PCB 72—371
    ENVIRONMENTAL PROTECTION AGENCY
    OPINION AND ORDER OF THE BOARD
    (by Mr. Dumelle):
    This case involves two separate petitions for variance which
    have been consolidated.
    The first
    (72—184)
    requests a variance
    from Rule 405 of the Illinois Water Pollution Regulations which
    requires that no effluent shall exceed 400 fecal coliforms per
    100 ml after July 31,
    1972.
    The second
    (72—371) requests a varianc
    from Rule 404(b) (i) which requires that the effluent shall not exc~
    20 mg/l BOD and 25 mg/l suspended solids after December 31,
    1973.
    Hearing was held on January 26,
    1973.
    The Granite City sewage treatment plant
    is primary only and
    discharges indirectly to the Mississippi River.
    It serves
    a
    popula
    tion of 40,000 persons, but due to the loading from industrial
    sources,
    it has a population equivalent of around 230,000.
    The
    average daily flow is 10,039,500 gallons.
    The plant removal
    efficiency for total organic suspended solids is 60 per cent.
    The
    design capacity of the plant
    is
    20 mgd.
    The plant consists of an
    aerated grit removal tank, primary sedimentation and vacuum sludge
    filtration.
    The Agency has conducted investigations and has taken samples
    the primary effluent showing high levels of BOD, suspended solids
    and fecal coliform.
    On October
    21, 1971 there was 470 mg/l BOD,
    290 mg/l ss and 190,000,000/100 ml fecal coliform.
    On November 16,
    1971 there was 700 mg/l HOD,
    460 mg/l SS and 80,000,000/100 ml fecal
    coliform.
    On March 21, 1972 there was 410 mg/l HOD,
    270 mg/l SS and
    110,000,000/100 ml fecal coliform.
    On May
    2,
    1972 there was 9,900,0
    100 ml fecal coliform.
    On June 27, 1972 there was 690 mg/l BOD,
    350
    mg/l SS and 140,000,000/100 ml fecal coliform.
    The proposed additions to the plant include preaeration, addi-
    tional primary sedimentation,activated sludge secondary treatment,
    chlorination, sludge heat treatment and incineration, primary treat-
    ment of combined sewer overflow up to
    23 mgd and chlorination
    of
    combined overflow up to 23 mgd.
    Since January of
    1971 the City has
    7
    145

    taken certain steps
    to comply.
    An engineering consultant was retained,
    a preliminary report was prepared and final plans were drawn for the
    plant additions.
    The City’s engineer submitted a project completion
    schedule in accordance with Rule 1002
    to the Agency on August 31,
    1972.
    The engineer estimated that the earliest date for operation of
    secondary facilities with plant startup and final adjustments would
    be March
    1,
    1975.
    The City alleges that in order
    to meet the
    December 31,
    1973 deadline there would have to be an around—the-clock
    operation which would create an additional cost of $2½
    to
    $5 million
    to the project.
    Construction bids have been received but none has
    been accepted yet.
    There is some conflicting testimony regarding interim chlorination.
    The City’s engineer claims that it would not be very practical because
    most of the interim equipment would not be easily incorporated into
    the final design.
    The engineer did not, however, have any actual
    estimate of
    the costs involved for interim chlorination.
    The engineer
    did testify that the interim equipment could be located
    in a place
    so as not to interfere with the construction of the new plant.
    A representative of
    the Federal EPA also testified at the hearing.
    Be stated that
    a 180 day notice hearing had already been held before
    his Agency and that interim disinfection at Granite City was an
    immediate necessity.
    He stated that such facilities can be provided
    on a temporary basis within a two month period by utilizing the
    construction adaptability and ingenuity shown by many heavy equipment
    contractors
    in housing their stationary operating equipment.
    The
    major cost of the facility would be the operational cost of the
    chlorine itself.
    lie
    said that
    a competent equipment manufacturer and
    engineer for that company could,
    in one-half day,
    adequately locate
    the components on
    a ten by ten foot wooden frame
    slab and that this
    would be adequate for up to two years.
    An engineer for the State Agency testified that the travel time for
    the effluent in the present outfall pipe is from twelve to thirteen
    minutes and that this would be an adequate time in which to chlorinate
    the effluent within the outfall pipe itself so that no separate contact
    chamber would be necessary.
    We find that a variance from the secondary treatment deadline of
    December 31, 1973
    is warranted in this case.
    At this point we will
    only grant the variance for one year from the date of
    this opinion
    and order.
    During that time we will observe the Cityts progress and
    extend the variance at a later date if appropriate.
    We will not,
    however, grant a variance from the disinfec~on requirement.
    We
    feel
    that interim disinfection is appropriate, necessary and feasible at
    the present time and that no need for a variance exists.
    The bacterial
    count
    is much too high to be continued unabated.
    This opinion constitutes the Board’s findings of fact and
    conclusion of law.
    —2—
    7
    146

    ORDER
    1.
    A variance of one year, expiring February 27,
    1974,
    is granted
    to petitioner from Rule 404 (b) (i)
    subject to the following
    conditions:
    (a)
    Petitioner shall report monthly to the Agency.
    regarding its progress on the proposed facilities.
    (b)
    Application for extension of this variance shall be made
    at least 90 days prior to its expiration date.
    2.
    The request for variance from Rule 405 is denied.
    3.
    As stated in the interim order entered herein on February
    6,
    1973,
    petitioner is granted a variance from Section 921
    (d)
    of
    the Illinois Water Pollution Regulations which requires
    that a Project Completion Schedule be approved before a per-
    mit can be issued by the Agency.
    This does not, however,
    excuse the filing of such Schedule altogether;
    it is only
    permission
    to issue the permit prior to that time.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control Board,
    certify that the abo e Opinion and Order was adopted by the Board on
    the ~~7~day
    of
    ‘~7~’
    ,
    1973,
    by a vote of
    3
    to
    0
    —3—
    7
    147

    .
    .

    Back to top