ILLINOIS POLLUTION CONTROL BOARD
    June 20,
    1974
    CAMEO
    DEVELOPMENT
    INC.
    PETITIONER
    )
    v.
    )
    PCB
    74—109
    ENVIRONMENTAL PROTECTION AGENCY
    RESPONDENT
    ~4R.
    JOSEPH
    WRIGHT,
    JR.,
    ATTORNEY,
    in behalf of CAMEO DEVELOPMENT,
    INC.
    ~1R,
    JOHN H.
    REIN,
    MR. HENRY HANDZEL, ATTORNEYS,
    in
    behalf of the
    ENVIRONMENTAL PROTECTION AGENCY
    ~)PINION
    ~ND
    ORDER OF THE EOARD
    (by Mr. Marder)
    This action involves a request for variance filed March
    25,
    1974,
    by
    Cameo Development, Inc., requesting relief from an Agency-imposed
    sewer ban
    (pursuant to Rule 921
    al
    of
    Chapter
    3).
    Additional inform-
    ation regarding this matter was filed on April 4th and April
    11th.
    The Agency filed its recommendation which suggested that the request-
    relief be denied.
    Hearing was held on May 21,
    1974,
    at
    the
    Effing—
    ham City Hall,
    ?etiticner~,Cameo Development,
    inc.,.owns
    5.78 acres of
    land.
    in
    the
    city
    of
    Effingham.
    It
    is the intent
    of
    Petitioner to utilize
    this
    land
    for
    the
    construction
    of
    a 122-unit Days Inn Motel, a 100-seat
    Tast:?
    4orld
    restaurant,
    and
    a
    three-pump
    gas
    station
    (R.
    22)
    .
    Although
    men-
    :ion
    of
    a
    gas
    station was not included
    in
    the petition for
    variances
    ~t
    was
    brought
    out
    on
    hearing.
    The
    hearing
    officer
    elected
    to
    allow
    testimony in that
    no
    undue
    surprise
    was
    evident,
    and
    the
    station
    was
    not
    a major
    factcr
    in the waste load flow.
    We
    concur
    in
    this f±ndtn~,
    Petitioner
    now
    finds that
    due
    to
    an
    Agency-imposed
    sewer
    ban,
    it
    can
    not obtain
    the
    required sewer extension permit and thus cannot
    ~oInmence
    construction.
    Petitioner further alleges that the curtailment
    of
    ~on~
    structa~onwould lead to an arbitrary and unreasonable hardship in
    that
    it
    ~hardship)
    was not self-imposed.
    The Agency counters that
    the
    hard-
    ship
    was
    indeed
    self-imposed,
    and
    that
    the
    variance
    request
    should
    he
    denied.
    The
    Board
    in
    deciding
    a
    case
    of
    this
    nature
    must
    go
    to
    the
    facts
    re-
    ;arding
    hardship,
    environmental
    impact,
    and
    alternates
    in
    order
    to
    reach
    a
    reasoned
    decision.
    A history
    of
    the
    facts
    surrounding
    thL:~
    case
    is
    thus
    in
    order.
    ~4r.,
    Richard
    H. Cocdy
    (president, Cameo Development
    Corp.)
    test
    i~i
    as
    to
    ~:he history
    of
    this
    project.
    The
    land.
    was
    purchased
    in
    Nv~~o~

    —2—
    1973
    (R.
    27), and before this time an attempt was made to verify the
    existence and availability of utilities
    in the area.
    Mr. Coody en-
    gaged Crossroads Realty of Effingham as their agent in this search.
    Mr. Coody received a letter (Exhibit A)
    dated November 16, 1973,
    signed by a Mr. Lowell Wines, Superintendent of the Street
    and
    Sewer
    Department of Effingham, stating in pertinent part:
    “This letter is to inform you that the city sewer facil-
    ities
    are within
    70
    feet of the property on the West Fayette
    Avenue, that the facilities are adequate for installation
    that you are planning to do.
    It will be necessary for you
    to obtain a permit from the Illinois State Highway Depart-
    ment for easement on their right of way.
    The city tap fee
    is
    fifteen dollars
    ($15)
    per tap.”
    In addition the letter bore the handwritten notation,
    “We need an
    Environmental Protection Agency permit.”
    Mr. Coody then checked with
    the city of Effingham as to the problems which would or would not be
    concerned in obtaining an Environmental Protection Agency permit
    (R.
    41).
    He was informed that permits for sewer extensions were being
    reviewed, and received no indication that there would be any problem
    in obtaining a permit
    (R.
    42).
    Mr. Coody then purchased the above-
    mentioned land and proceeded with engineering.
    A loan for construct-
    ion was obtained in December,
    1973.
    A permit was filed with the En-
    vironmental Protection Agency in March, 1973
    (Exhibit 5,
    R.
    31).
    Upon hearing that the Environmental Protection Agency had stopped is-
    suing permits Mr. Coody filed the instant variance petition.
    The
    Agency sewer ban went into effect in February of 1974.
    The rationale for this ban
    along with interim steps being taken
    by the city of Effingham weigh heavily in .~thiscase.
    The city of
    Effingham owns
    and
    operates a secondary treatment plant consisting of
    primary settling,
    anaerobic digestion, trickling filters, and final
    settling with recirculating pumps and chlorination.
    The plant was con-
    structed in 1957 at a rated capacity of 1.27 mgpd.
    Since 1970 the city
    has undertaken to improve the capacity of the plant by cleaning the di-
    gestor, rebuilding internal piping, increasing the size of the recirc-
    ulating pump,
    and going to alternate sludge disposal
    (R.
    47).
    The city
    has also taken steps to remove
    a large portion of storm water from the
    combined system,
    and this storm water now discharges into the stream
    (R.
    50)
    (done March 1974).
    The city is presently
    (under Agency permit
    R.
    51)
    adding prechiorination and converting the trickling filter from
    a single stage to a recirculating system.
    Chemical settling agents
    will also be added to reduce suspended solids.
    This work is being con-
    ducted in an attempt to obtain
    a 20/25 BOD/SS effluent
    (R.
    53).
    This
    project is due for completion in July 1974.
    Under cross—examination the subject of increased capacity due to the
    above improvements was questioned.
    It is clear that the improvements
    do not guarantee additional capacity; however, there is a substantial
    chance for success.
    Discussions as to whether or not the Effingham
    plant can
    ‘fleet the required 20 BOD/25 SS requirement were long and in-
    volved.
    Again, there is no way to determine whether or not the plant
    will indeed meet this criteria.
    However, this question is of central
    importance
    in the instant case, in that it swings the balance of other
    12—578

    —3—
    testimony.
    One must then explore the Agency’s seeming intent in grant-
    ing a permit for these improvements, and try and ascertain what the
    Agency’s belief was prior to granting said permit.
    The Agency recommendation,
    P.
    6, states as follows:
    “However, Agency engineers strongly believe that even
    after the improvements are completed,
    the plant will not
    be able to meet the twenty mg/l BODç and twenty-five mg/i
    suspended solids standard of Rul.e 4~4-Bof Chapter 3.”
    Mr. Broms
    (Environmental Protection Agency Permit Section)
    ,
    when
    asked about this quotation, said,
    “Well, the strongly believes,
    I won’t say I’m negative
    on it,
    I have my doubts,
    I won’t say emphatically it will,
    I won’t say emphatically it won’t.”
    (R.
    81)
    Mr. BromS further testified that due to the design differing from
    normal practices one could not predict with certainty the outcome of
    the project.
    (R.
    82)
    He further testified that the permit was issued
    to see if the facility would meet the’standards and then couldbe per-
    haps rerated to 1.75 mgpd
    (R.
    84).
    Mayor Clyde Martin
    (city of Effingham)
    testified as to the reasons
    for the city entering into the abovementioned improvements.
    Mayor
    Martin testified that he was led to believe
    (by the Environmental Pro-
    tection Agency) that the improvements would allow the city to meet the
    applicable regulations
    and
    thus continue to grow.
    He referred to a
    call he placed to the Environmental Protection Agency from which he
    learned that the city had “no problem”
    (R.
    109).
    Mayor Martin further testified as to a meeting held in the Environ-
    mental Protection Agency offices in Springfield at which time the
    Environmental Protection Agency stated that the improvements would help
    the city get off restrictions
    however, no guarantee was made
    (R. 116).
    Mayor Martin stressed that the city committed to expend $40,000 on the
    basis that they were led to believe that this would “get by”
    (R.
    117).
    Mr. Lowell Wines, Superintendent of Streets and Services,
    city of Eff-
    ingham, was also present at the above meeting.
    Mr. Wines
    also testi-
    fied that at no time did the Agency express
    a firm opinion as to whethex
    the improvements would or would not meet the applicable criteria
    (R.
    125)
    Agency Exhibit #1 is a letter from the Illinois Environmental Pro-
    tection Agency notifying the city of Effingham that it is being put
    on critical review (dated February 10, 1972).
    Critical Review is a
    process whereby the Agency informs the city that its plant
    is approach-
    ing design capacity and that the Agency will be closely scrutinizing
    any new permit applications
    (R.
    92).
    This letter (Exhibit
    1) relates
    the following design and actual loading:
    Design Hydraulic Flow
    1.20 mgd
    Design Pop. Equivalent
    10,500
    12—579

    —4—
    Design
    BOD
    Load
    1785
    #/day
    Average
    Flows
    5
    Month
    1.42
    mgd
    1971
    Average
    Pop.
    Equiv.
    6890
    From
    the
    above
    the
    Agency
    concludes
    that:
    “The
    Effingham
    sewage
    treatment
    facilities
    are
    hydraul-
    ically
    overloaded even during periods of no precipitation
    while
    some
    reserve
    organic
    capacity
    remains.”
    The
    Agency
    further
    speculates
    that
    a
    large
    discharge
    of
    relative-
    ly
    contaminant-free
    water
    is
    entering
    the
    system.
    Petitioner’s
    Exhibit
    I
    is
    a
    letter
    from
    the
    state
    Environmental
    Protection Agency dated February
    4,
    1974.
    This
    letter
    informed
    the
    city
    of
    Effingham
    that
    it
    was
    to
    be
    put
    on
    restricted
    status.
    Re-
    stricted
    Status
    means
    that
    the
    Agency
    will
    no
    longer
    issue
    permits
    for
    the
    subject
    system.
    The
    following
    data
    details
    the
    rationale
    for
    this
    decision.
    (Note
    the
    change
    in
    design
    load
    -
    no
    reason
    given.)
    Design Hydraulic
    Flow
    1,27
    mgd
    Design
    Pop.
    Equiv.
    11,500
    Average
    Flows
    (low
    flows)
    1.676
    mgd
    Average Flows
    (high
    flows)
    2,073
    mgd
    Average Organic Loading
    10.275
    PE
    ftc
    letter
    also
    details
    very
    high
    SOD/and
    suspended solids of
    85
    mg/i
    and
    86
    mg/i
    respectively.
    This
    letter
    also indicated that per-
    mits
    granting
    a
    population
    equivalent
    of
    2,221.3
    and
    flow
    of
    202,130
    ~pd
    were
    in
    the
    works,
    which
    would
    further
    complicate
    matters.
    Mr.
    Fitzpatrick
    (city
    engineer)
    stated
    (R.
    71)
    that
    a
    number
    of
    the
    above
    permits
    will
    not
    be
    exercised
    for
    quite
    some
    time
    if
    at
    all,
    and
    his
    orcjection
    would
    be
    an
    addition
    of
    830
    PE.
    If
    this were the case,
    the
    total
    organic
    load
    would
    then
    be
    11,105
    vs.
    a design of
    11,500.
    :t
    this
    time,
    then,
    it
    would
    seem
    that
    the
    organic
    loading
    is
    close
    to
    capacity,
    and.
    the
    hydraulic
    load
    is
    somewhat
    above
    capacity.
    This
    analysis
    places
    heavy
    weight
    on
    the
    abcvementioned testimony
    that
    a
    substantial
    portion
    of
    the
    storm
    water
    was
    removed
    from
    the
    system
    in
    ~4arch
    1974.
    ~Ir.
    G.
    Schwager
    testified
    as
    to
    how
    samples
    are
    handled
    at
    the
    Envir
    onmental
    Protection
    Agency
    laboratory,
    and
    as
    to
    the
    results
    of
    samples
    run
    at
    that
    laboratory~
    There
    was
    much controversy over the validity
    of
    the
    samples;
    however,
    this
    oint
    was
    somewhat
    moot.
    The
    Agency
    rec~
    ommendat.ion
    (Pg.
    5)
    details
    tesuits
    of
    samples
    run
    on
    the
    city
    of
    ~
    ingham~seffluent.
    These
    results
    ~ncw
    brie
    city
    ho
    be
    clearly in viol-
    ation of the ap~1icab1e
    standatho.
    It
    is
    important
    tc
    note
    that
    these
    samples
    were
    taken
    before
    the
    city
    oor~pleted
    the
    abovementioned
    imprcv
    ments
    ~some
    .improvemen~s
    are
    st:~.~onderway
    ,
    and
    reflect
    Only
    that
    th
    Acencv~as
    correct
    in
    issuing
    a
    ~ewer
    can.
    These
    analyses
    gave
    no
    !a
    cation
    f
    what
    the
    effl
    cent
    will
    ~:a. a that
    improvements
    are
    completed.

    —5—
    All of the above may be summarized to state that although the
    Agency properly imposed a sewer ban, the city of Effingharn has been
    diligently pursuing a plan which has the potential of cringing its
    plant into compliance.
    This means
    that should a variance be allowed
    Cameo Developers, the impact of this added effluent
    (1864 gpd at 300
    mg/i BOD5
    )
    should have much less effect on the receiving stream than
    it would in a case where no improvement is underway.
    The question
    then must go to the hardship involved.
    Mr. Coody related the economics involved in the project.
    He stated
    that a price of $32,900 per acre was paid for the land, which was sig-
    nificantly greater than its value for residential property.
    He ex-
    plained that the $32,900 per acre was reasonable
    in that his project
    was a high density area
    (R.
    16)
    .
    Mr. Coody anticipates that the land
    would be worth $5,000
    an acre should he not be able to build
    (R. 17).
    Mr. Coody also related that if he were to lose his loan and then have
    to reie~otiateat
    a later date, he would potentially incur a loss
    of up
    to $200,000
    (FL
    19).
    Mr. Coody further related engineering costs of
    $30,000.
    Various other commitments were mentioned, totaling approxi-
    mately $380,000.
    Although Mr. Coody conceded that some of the above
    commitments could be cancelled, he had no
    way
    of knowing what his loss
    would be
    (R.
    27).
    The Agency contends
    (see Agency Brief Pg.
    9-10)
    that the financial
    hardship is vague and at best defers the enjoyment of the subject
    property rather than terminates its use
    (Brief Pg.
    13).
    The Board
    must agree that this is true; however, the hardship, although vague,
    is, by facts
    elicited, substantial.
    While it is true that some of
    the losses can be recouped in time, no one can guess how long this
    time will be.
    The city of Effingham enjoys priority
    4146
    (FL
    75), and
    Mr. Fitzpatrick (engineer for Effingham) predicted that federal money
    should be available during 1974—1975.
    The city has completed its in-
    flow—infiltration analysis and could st&rt construction during late
    1974.
    This, however,
    is an estimate and not a firm date.
    The Board
    feels that delay in utilization of said property could be substantial
    indeed.
    The Board, then, must weigh the potential hardship against the en-
    vironmental harm which would ensue should the variance be granted.
    This Board has faced similar situations many times in the past.
    In
    instances such as Viking Investment
    Co.
    v. Environmental Protection
    As~ency,PCB 73-236, and Meridian Community School District
    ~t1v. En-
    vironmental Protection Agency, PCB 73-349,
    this Board has granted
    variance due to conditions which combined with other factors showed
    substantial hardship.
    In many other cases, such as Monyek v. Environ-
    mental Protection Agency, PCB 71-80, the Board has refused to grant
    variance.
    In the instant áase the Board takes
    note
    that
    there
    is
    a
    reasonable
    chance that the receiving plant will comply with applicable regulations
    shortly.
    Agency witnesses testified that such is the case.
    The Board
    finds that this factor involves a condition which
    is unique in sewer
    ban cases,
    and must be given serious consideration.
    In light of this
    fact, and with cognizance that a substantial hardship will occur, this
    Board will grant variance.
    12—581

    6_
    We emphasize that the unique factors surrounding this case have
    led to this decision.
    In future cases the Board will ask for proof
    of operation of the Effinghain plant before granting variances.
    The
    improvements
    are scheduled for July,
    1974,
    and data of this nature
    should be shortly forthcoming.
    We would again confirm our position
    in Feige
    V.
    Environmental Protection Agency, PCB 72-192, wherein the
    Board noted that completion of construction or substantial steps to-
    wards such construction can be clearly used to judge hardship.
    This
    position, however, was founded without the rather unique situations
    of this case.
    This Opinion constitutes the findings of fact and conclusions of
    law of the Board.
    ORDER
    IT IS TUE ORDER of the Pollution Control Board that variance is
    hereby granted to Cameo Development,
    Inc.,
    from the Agency sewer ban
    in the city of Effingham to connect a 122 unit Days
    Inn, a 100-seat
    Tasty World restaurant, and a three-pump gas station.
    I, Christan L. Moffett, Clerk of the Illinois Pollution Control
    Board,
    certify that the above Opinion and Order was adopted by the
    Board on the c~&~’~
    day of
    __________,
    1974, by a vote of
    ____
    to
    b
    12—582

    Back to top