ILLINOIS POLLUTION CONTROL BOARD
    June
    30,
    1988
    KING-SEELEY THERMOS CO.,
    )
    Petitioner,
    v.
    )
    PCB 87—154
    ILLINOIS ENVIRONMENTAL
    )
    PROTECTION AGENCY,
    )
    Respondent.
    ORDER OF THE BOARD
    (by J.D. Dumelle):
    This matter comes before the Board upon receipt of
    Petitioner’s June
    22,
    1988, Agreed Motion To Modify Previous
    Board Order, filed by King—Seeley Thermos Co.
    The Motion notes that in its prior
    Order
    of February 4,
    1988,
    this Board granted King—Seeley Thermos Co.
    a variance from
    the air emission limitations set forth at 35
    Ill.
    Adm. Code
    215.204(j)(4) until June
    30,
    1988.
    The Motion states that during
    the period of the variance Petitioner has acted
    in accordance
    with its compliance plan and proceeded diligently to construct
    new painting facilities which will allow the Freeport plant to
    reduce
    its VOC emissions below the required limit.
    However,
    delay of equipment deliveries and labor
    difficulties beyond King—Seeley’s control have necessitated a
    need for extension of the original variance for an additional
    45
    days.
    King—Seeley Thermos Company is granted an extension for 45
    days
    of this Board’s final deadline for compliance with the VOC
    emission limitations set forth at
    35
    Ill.
    Adm. Code
    215.204(j)(4).
    IT IS SO ORDERED.
    I, Dorothy M.
    Gunn, Clerk of the Illinois
    Pollution Control
    Board, hereby certify that the above Order was adopted on
    the
    _____________
    day of
    ___________,
    1988 by a vote
    of
    7-~
    I~A1
    ~
    Dorothy M./Gunn, Clerk
    Illinois Pollution Control Board
    90—483

    Back to top