ORDER OF THE BOARD
(by G.T. Girard):
Pursuant to the Board’s order of April
9,
1992,
hearing was
scheduled for July
8,
1992.
On June 10,
1992,
Atwood
moved to
reschedule hearing in this appeal of a RCRA closure plan.
Atwood
reports
that
its
consultant,
Baxter
and
Woodman,
completed its draft
of
a revised closure
plan and forwarded the
revised
plan to the Agency
on
March
18,
1992,
for
review
and
approval.
According to counsel for the Agency, the Respondent has
completed its review of the revised plan and expects to respond to
Atwood within the next two weeks.
Atwood
is hopeful that this
matter will be
resolved in the near future without the need for
briefing by the parties or a hearing.
The Board notes that the decision deadline in this matter has
been waived
only until
November
19,
1992.
Cancellation
of the
hearing could jeopardize the Board’s ability to meet its decision
deadline
in the event
a
dispute arises.
The Board
accordingly
denies Atwood’s motion.
However,
the Hearing Office is authorized
to
reschedule
hearing
in
the
event
an
appropriate
waiver
is
received.
If the July hearing is cancelled, the Board would expect
the filing of an updated status report on or before September 15,
1992.
IT IS SO ORDERED.
I,
Dorothy M. Gunn,
Clerk of the Illinois Pollution Control
Board, hereby certify that the above order was adopted on the
2~’~
day of
__________________
;
1992 by a vote of
7
c’
/
~
/1)
Dorothy
M.,áunn,
Clerk
Illinois Pollution Control Board
I
34—309