ILLINOIS POLLUTION CONTROL BOARD
October
14,
1971
SPARTAN PRINTING
CO.
v,
)
#
71—19
ENVIRONMENTAL PROTECTION AGENCY
Supplemental Opinion and Order of the Board
(by Mr.
Currie)
Spartan was given until July
1,
1971 to complete Phase
I
of
its wastewater treatment
facilities
(Spartan Printing Co.
v.
EPA,
#
71-19, June
23,
1971).
On June
29, however,
the
company requested
a brief extension because of delays caused by
unanticipated
foundation conditions, unusually wet weather,
and
failure of equipment
to meet specifications.
We asked for the
Agency~srecommendation,
which was
that
the $200,000 bond we
required posted be forfeited and that
a hearing be held.
Spartan has
also
filed
a proceeding for judicial review of
our decision,
and,
under Supreme Court Rule
335, has asked us
to modify and to stay our order in certain respects.
The Agency
has not responded
to this latest motion.
We agree with
the company that
a $200,000 forfeiture would
be
an excessive imposition
for the brief and unintentional set-
back suffered
in attempting
to meet the Board~s order.
The first
stage was completed August
4,
scarcely a month behind schedule;
the second stage has
not been delayed at all;
it
is not the
cornpany~sfault the delay occurred.
We
see
no need for
a hearing;
the
delay
was
trivial
and
the
facts
have
not been disputed.
We
grant
the
extension
to
August
4,
1971,
and
since
that
date
is
past
we
remove
the
provision
requiring
that
the bond cover the
installation or operation
of Phase
I.
We will not, however,
lift the requirement of
a bond to secure Phase
II,
as that’the
statute flatly requires.
We are also asked to stay enforcement
of our
order, pending
review, with respect both to the bond
and to the penalty we imposed
as
a condition of the variance.
We agree a~to the penalty,
for
we
see
no
point
in requiring
the money
to be paid now if it may
have to be repaid after judicial review.
The purposes
of the
order
will
be
as
well
served
by
later
payment
if
the
appeal
fails.
But
this
is
not
the
case
with
the
bond,
for
a
bond
will
do
no
good if
it
is
filed after the
date
of
compliance;
it
must
be
filed now
if it is
to serve
its
purpose.
2
—
589
Accordingly the June
23 order is hereby modified by extending
the Phase
I date to August
4,
1971,
and by eliminating the re-
quirement that the bond cover Phase
I;
and the penalty
provision.
in paragraph
3
of that order is hereby stayed pending judicial
review, on condition that
a bond to secure payment of
the penalty
in the event of an adverse judicial decision is filed with the
Environmental Protection Agency within 15 days after receipt
of this
order.
In other respects
the motion for modification
and stay
is
denied.
I, Regina
E.
Ryan, Clerk of the Pollution Control Board,
certify
that the Board adopted the above Supplemental Opinion of the
Board
this
14
day of
October
,
1971.