ILLINOIS POLLUTION CONTROL
BOARD
February 21, 1980
ALGONQUIN
AREA
PUBLIC
LIBRARY
DISTRICT,
)
)
Petitioner,
)
v.
)
PCB 79—159
)
ENVIRONMENTAL
PROTECTION
AGENCY,
Respondent.
OPINION
AND
ORDER
OF
THE
BOARD
(by
Mr.
Goodman):
This
is a petition for variance from Rules 102 and 202
of the Board’s noise regulations as they apply to Petitioner’s
(flgonquin) air conditioning facility located behind its library
building on 115 Eastgate, Algonquin.
Petition was made as. a
result of a complaint to the Illinois Environmental Protection
Agency (Agency) in 1977 by Lori and Joseph Jasinski, whose home
is situated approximately 50 feet behind Algonquin’s library.
Algonquin’s engineers studied the problem and made recommenda-
tions;
Algonquin
followed
certain
of
these
before
seeking
a
5—dB
variance
for
between the hours of 7:00 a.m. and 10:00 p.m.
if
and
when
conditions
require
operation
at
maximum
load
•
The
technical
reason
given
to
support
grant
of
variance
is
that
further
noise
reduction
can
be
achieved
only
by
restricting
air
movement
around
the
fans
and
coils.
The
hardship
alleged
is
the
already-spent
$10,000,
a present expenditure of uncertain
size, and the ‘only trivial’ further reductions possible by its
efforts.
The
Agency’s Recommendation was filed on October 30, 1979.
It recommended denial for the reasons that
(1) further noise
reduction may not be trivial depending on the efforts expended
by Petitioner;
(2) Petitioner has not
yet
established a detailed
noise abatement program; and (3)
Petitioner
to
date
has
not
followed all the recommendations of its consultant.
The Board
further notes that the variance petition did not specify the
period
for
which
the variance was sought and did not set forth
a
detailed
compliance
program.
Attempts
at
correcting
these
were
made
at
hearing
(R.75—79).
Algonquin first contacted its consultant—witness Yerges,
a man of 41 years’ experience in sound control, on
May
31,
1978
(R.10—11).
The problem
was
described as emanating from the
air—cooled condensers during operation at maximum load, and in
37—401
particular from the vertical
discharge
of air over the
fans
located on the top of the unit (R,12)~ Yerges~recommendations
one month later were to remove the tubular silencers on
the
top
of the unit,
replacing them with a lined,
acoustic plenum and
low pressure drop duct mufflers, and to screen the intakes to
the unit
(R,15)~
Yerges further recommended constructing an
8—foot barrier between the unit and the residential property,
installing three-foot-long mufflers on the top of the unit
(R,15-16),
installing further screening,
and adding absorptive
material to the library wall behind the unit (R,29)~
The system designer, Migdal, testified that the air
con-
ditioner could not be relocated much further away without
sacrificing loss of refrigeration capacity (R~62—63);that two
of
the
six
fans
could
not
be
shut
off
without
harming
the
system,
especially for two hours during the estimated 30 days of peak
demand annually (R~64—65),although this was possible after
7:00
pam.
(R~73—74); that
the
system,
installed
at
the
end
of
1975 and having
a 12—year life
(R.74), was not designed with
consideration of the noise levels
in Rule 204
(R,66—67);
and
that the manufacturer,
Trane Co., advised him that extending
the present 8—foot barrier by six feet or canting it would cause
shortcycling when wind velocity was “low”
(R.69—70).
The library building architect, Pigozzi, testified that
to move the 4,000-pound air conditioner would require roof
modifications at a cost of $10,000 plus labor (R.88—90).
The
Librarian,
Stahl,
testified
that
the
library
never
opens
before
10:00 a.m.
and is closed on Sundays
(R.92)
(Neighbor Jasinski
testified
that the noise is heard on
Sundays,
R,110); that
users
have
complained
“vehemently”
in
the
summer
that
the
library
is too
warm
(R.96);
and that there has been an
increased number of maintenance problems since the installa-
tion of screening over
a, year ago (R,94).
The
neighbor,
Ms.
Jaskinski,
testified
that
the
noise
interferes
with
her
family~s
and
friends~
being
outside
in
the yard
(R,105,
109),
with
both
of
her
children~s
falling
asleep
at
night
(R.106—107),
and
with
dinnertime
conversations
(R.105).
It
sounds to her, especially in the evening hours,
like a continual noise; when the system stops the quiet is
noticeable
(R,107—108),
She did not complain directly to
Algonquin because her builder informed her that the Agency was
handling the problem
(R,105—106),
The Agency testified that it observed that Petitioner
had
taken the noise abatement steps of adding an exhaust
plenum
with silencers and constructing
a barrier, but that the barrier
was insufficient because it was too low (R,124—126),
The Agency
testified that even after the control methods were put into
practice the noise
level was too loud and interfered with
living
(R.147).
The 60~dBsound
level in the Jasinskis~back
yard indicates that people must not stand more than 8-10 feet
37—402
from each other in order to converse normally (Recommendation,
Ex~5).
The Agency could not pursuant to Rule 405(a)(4) state
what costs
of compliance would he because Algonquin had not
established a compliance plan (Recommendation, p~2),
Exhibit
5 of the Recommendation,
an interoffice Agency
memorandum,
indicates that removing or relocating the unit will
substantially reduce noise levels,
as could barrier expansions
The current problem is the exhaust at the top of the silencers;
the Agency found this to be
a major factor in the barrier~s
ineffectiveness
(Recommendation, Ex~5)~However,
the barrier
was one of the first steps which Yerges had advised Algonquin
to take;
if compliance wasn~tthereafter achievable Yerges
advised various modifications to the barrier be made (Recom~
rnendation, App~IV)~ The Agency found that these second step
recommendations are what Algonquin must take, as
a minimum,
to
reach compliance
(Recommendation, Ex~5)~.
Yerges and Migdal both testified that within five years,
the period
for which Algonquin seeks a variance possible improve~-
ments
or modifications can cause compliance
—
but neither says
much more except that compliance will be due to new methods of
improvement (R~58)or to unspecified modifications (R~65~66).
Algonquin~sattorney admits that the state of the art has since
changed and offer~to modify or replace the unit accordingly,
meanwhile running it on four of the six fans after 7:00 p~m.to
ensure no operation at maximum load (R~77~78),
Although no evidence was introduced regarding how the state
of the art has changed,
let alone the extent of costs involved,
the Board will grant a limited variance for the purpose of allowing
Algonquin to further investigate methods of complying with the
Board~sRules~
The Board will grant Algonquin variance
from Rules
102 and 202 until
March
1,
1981 under certain conditions~
These
conditions will
be those generally suggested by Algonquin at the
hearing and to which the Agency refers
in their closing arguments
Although the Agency refers to a document dated December 27,
1979
supposedly submitted by Algonquin entitled uStatement of Interim
Remedial Measures During Variance~,the Board can find neither
the document nor any record of its having been filed before the
Board
This Opinion constitutes the findings of fact and conclu~~
sions of law of the Board
in this matters
ORDER
It
is the Order of the Board that variance from Rules 102
and 202 of the Board’s Noise Regulations be granted to Algonquin
37-403
—4—
Area Public Library District until March
1, 1981 under certain
conditions:
1.
Algonquin Area Public Library District shall
investigate and evaluate available methods
which will allow its air conditioning equipment
to meet limits imposed by the Board~sRules,
including but not limited to extension of the
noise barrier, modification of the exhaust and
intake mufflers and/or compressor exhaust fans
and the use of auxiliary air conditioners in
remote locations.
2.
During the period of this variance Algonquin
Area Public Library District shall modify its
equipment operation in the following manner:
(A)
Algonguin shall maintain the temperature
in the Library at the Federall~mandated
level of 78°Fduring the cooling system.
(B)
Algonquin shall schedule the air conditioning
equipment
so that no more than two compressors
and no more than four condenser fans are in
operation after 7:00 p.m. Monday through
Saturday and all day on Sunday.
(3)
Within 45 days of the adoption of this Order,
the
Algonquin Area Public Library District shall
execute and forward to the Illinois Environmental
Protection Agency,
2200 Churchill Road, Springfield,
Illinois 62706 a Certification of Acceptance and
Agreement to be hound to all terms ~nd conditions
of this Order,
The 45 day period shall be held in
abeyance during any period this matter is being
appealed,
The form of said certification shall be
as follows:
CERTIFICATION
I
(We),
having read and
fully understanding the Order of the Illinois Pollution Control
Board in PCB 79~159,hereby accept said Order and agree to be
bound
by
all of the terms and conditions thereof.
S IGNED______
TITLE_______
DATE
______
37—404
I, Christan L. Moffett, Clerk of the Illinois Pollution
Control Board,
hereby certify the a~vçOpinion and Order
were adopted on the
A1~’
day
of ~
1980
by
a vote of
4~
.
C)
Christan L.
Mof
,
Clerk
Illinois Pollution Control Board
37—405