ILLINOIS POLLUTION CONTROL BOARD
    March
    24,
    1988
    IN THE MATTER OF:
    SITE—SPECIFIC RULE CHANGE AT
    35 ILL.
    ADM.
    CODE PART
    304,
    )
    R87—22
    SUBPART
    B (CIPS NEWTON STATION)
    PROPOSED RULE.
    FIRST NOTICE.
    PROPOSED OPINION AND ORDER OF THE BOARD
    (by
    3.
    Marlin):
    This matter comes before the Board on
    a petition
    for site—
    specific relief filed
    by Central Illinois Public
    Service Company
    (CIPS)
    on July
    17,
    1987.
    Specifically, CIPS
    is seeking relief
    from the requirement
    of Section 304.124(a)
    as it pertains
    to
    effluent limits for total
    suspended solids (TSS).
    The relief
    would apply to the discharge
    from CIPS’
    ash pond system
    at its
    Newton generating station
    (Newton).
    Instead of the
    15 milligrams
    per
    liter
    (mg/i) standard imposed in Section 304.124(a), CIPS
    wishes
    to be subject
    to the following effluent limits:
    30 mg/i as
    a 30-day average
    and 100 mg/i
    as
    a daily maximum.
    A hearing was held
    in this matter
    on Noveniber
    4,
    1987
    in
    Newton.
    On January
    27,
    1988,
    the Department
    of Energy and
    Natural Resources
    (DENR)
    filed
    its determination that an economic
    impact study was not necessary
    in this matter.
    The
    Board was
    informed
    of the Economic and Technical Advisory Committee’s
    concurrence with this determination on January 29,
    1988.
    At Newton, CIpS generates electricity through
    the production
    of steam
    in boilers fueled by coal.
    Bottom ash from the boilers
    at Newton
    is sluiced out of the plant and
    is processed by an ash
    pond system.
    Water
    taken
    from Newton Lake
    is used for this
    purpose.
    The sluiced ash
    is
    first discharged
    to the primary
    settling pond.
    This primary settling pond has a surface area of
    401 acres.
    Currently,
    this
    pond
    is operated at
    a depth of
    7
    feet.
    The maximum design depth is
    23 feet.
    Originally,
    the pond
    system was intended
    to process both fly ash and bottom ash.
    However, only bottom ash
    is processed
    in the ash pond system;
    since
    1979,
    the fly ash has been utilized
    to stablize
    scrubber
    by—products before landfilling.
    This change resulted
    in
    an 85
    percent reduction
    in solids entering
    the pond with the result
    that,
    the primary settling pond now has an estimated
    life of
    277
    years.
    (R.
    13).
    The ponds
    have
    a 106 day retention
    time
    (R.
    44).
    The primary settling pond discharges
    to
    a 9.3 acre secondary
    settling pond.
    This pond
    is operated at
    a depth of
    12 feet,
    although
    it has a maximum design depth of
    26 feet.
    (Exh.
    #1,
    p.
    4).
    87—279

    2
    The secondary settling pond discharges
    to Newton Lake.
    The
    amount discharged
    is estimated
    to
    be between
    7.78
    and 8.98
    million gallons per day.
    (Exh.
    #1,
    p.
    3).
    It
    is this discharge
    that
    is the subject of CIPS’
    request.
    Aside from two isolated
    instances,
    CIPS first consistently
    failed
    to achieve the
    15 mg/I standard
    in January,
    1986.
    These
    problems persisted until September,
    1986.
    In
    that month,
    CIPS
    experienced
    its first and only violation of the daily maximum
    standard, which
    is 30 mg/i
    as figured pursuant
    to Section
    304.104.
    At the time of the hearing, CIPS’
    discharge had been
    in
    compliance since September,
    1986.
    (Exh.
    #1,
    p.
    5—6;
    R.
    47).
    After analyzing
    its discharge, CIPS has considered
    that
    algal
    blooms are a major contributing
    factor
    to CIPS’
    past
    exceedances of the total suspended solids standard.
    (R.
    45).
    The
    green algae,
    found
    in CIPS’
    discharge, would constitute part of
    the volatile suspended solids fraction of the TSS discharge.
    The
    ash,
    for which
    the ponds are designed
    to
    remove, would
    be
    included
    in
    the fixed solids
    fraction of the TSS discharge.
    Between February 1986
    and October
    1986,
    the
    total volatile
    suspended solids (TVSS)
    fraction ranged
    from 17.7
    to 68.2 percent
    of the TSS recorded.
    (Exh.
    #1,
    p.
    7;
    R.
    15).
    In
    1987,
    the
    percent of TVSS
    in the TSS was as high as 80 percent.
    (R.
    73).
    It
    is CIPS’
    position that the ash ponds are doing
    their
    job.
    That
    is,
    the ash
    is settling out in the ponds.
    CIPS does
    not believe that the ponds are “short—circuiting”
    (R.
    44).
    CIPS
    comes
    to this conclusion by comparing the concentration of ash
    in
    the pond water with the concentration of ash
    in the dischare.
    (R.
    26).
    Also,
    CIPS asserts that the water discharged
    to Newton Lake
    has
    less total
    fixed solids than the water CIPS takes from the
    lake
    to use
    in
    its sluicing operation.
    Data from April
    1, 1987
    are the only exception, according
    to CIPS.
    (R.
    61).
    For the period of time during which CIPS had compliance
    problems, February 1986
    through October
    1986,
    the fixed solids
    portion of
    the TSS would have only exceeded the 15 mg/i standard
    twice.
    The TVSS fractjon, when figured alone, would
    never have
    exceeded
    the standard.
    (Exh.
    #1, Attachment
    B).
    It
    is clear
    then that the exceedances are usually
    a result of the combination
    of the TVSS with the fixed
    solids.
    The largest
    exceedance by
    CIPS for TSS was recorded
    in September,
    1986 which yielded
    a
    25
    mg/i average.
    As previously stated,
    the highest daily value,
    39
    mg/i, was also recorded
    in that month.
    (Id.).
    CIPS evidently did not analyze
    fixed solids separately from
    TVSS
    for every month during
    that time period.
    87—280

    3
    CIPS claims that treatment alternatives
    to the ash pond
    system are cost prohibitive.
    According
    to CIPS,
    construction
    of
    a wastewater treatment plant would cost between
    9 and 17 million
    dollars,
    depending
    on the design
    selected.
    Also,
    CIPS claims
    that the cost
    of
    a recirculation system, which would require
    the
    landfilling
    of
    the ash,
    is estimated
    at $17 million.
    (Exh.
    1,
    Att.
    F
    &
    G,.. R.
    20—22).
    Both the primary and secondary ponds have
    a large population
    of bullheads.
    According
    to CIPS,
    the bullheads could contribute
    to the fixed solids portion of the TSS.
    Bullheads,
    as bottom
    feeders, churn up sediment thereby adding
    to the TSS.
    (Exh.
    #1,
    p.
    9).
    CIPS
    is uncertain as
    to the degree
    that the bullheads
    contribute
    to the fixed solids count.
    The only way to determine
    this level
    of contribution would
    be
    to kill
    all
    the fish
    in the
    ponds, by the use of toxicants,
    and examine
    if,
    or
    how,
    the fixed
    solids level
    improves.
    However, CIPS believes that this option
    would be difficult
    and would pose substantial risks
    for
    the fish
    population
    in Newton Lake.
    (Exh.
    #1,
    p.
    15).
    Also, CIPS states
    that the Illinois Department
    of Conservation
    (IDOC), which
    manages Newton Lake’s fishery,
    is against
    the use
    of toxicants
    in
    the ash ponds.
    (Id.
    at
    17).
    Similarly,
    the green algae can be eliminated
    through the use
    of algicides.
    As with the killing
    of
    fish,
    such
    a control would
    have
    to be used repeatedly.
    CIPS states that the algicides would
    also pose
    a great environmental risk
    to the biota of Newton
    Lake.
    IDOC does not favor this method either.
    (Exh.
    4~l,p. 20—
    21;
    R.
    74).
    CIPS has taken steps to
    reduce TSS by managing pond
    levels.
    Shoreline erosion due
    to wave
    action has been decreased
    by operating the primary pond
    at
    a depth of
    7 feet rather
    thai~23
    feet.
    This has encouraged
    the growth of macrophytes (rooted
    plants) which calm the water and help settle solids.
    The
    macrophytes
    compete
    with
    algae
    for
    sunlight
    and
    nutrients.
    (R.
    54—57).
    Environmental
    Impact
    CIPS asserts
    that its TSS discharge
    to Newton Lake has no
    detrimental
    impact upon Newton Lake.
    In
    fact, CIPS claims that
    the green algae may have
    a beneficial
    impact upon the Lake
    since
    algae
    is food
    for
    fish.
    According
    to CIPS,
    there
    is
    a favorable
    mix
    of algal
    species
    in
    the effluent.
    Blue—green algae,
    a
    potentially harmful
    type, are not present
    (Exh.
    #1,
    p.
    22—23;
    R.
    68—69).
    CIPS cites an IDOC study
    for the proposition that the
    discharge
    has no negative impact on the lake’s fishery.
    Evidently, more
    fish are caught per unit of effort
    in the cove
    where CIPS discharges as compared
    to
    a cove
    across the lake
    (Exh.
    41,
    p.
    24).
    The reasons why fish apparently congregate near the
    discharge are not certain
    (R.
    108).
    87—281

    4
    CIPS claims that
    a standard
    of 30/100 would not have
    a
    negative
    impact on the environment
    since that
    is the standard
    which was promulgated
    (and codified at
    40 CFR 423)
    by the U.S.
    Environmental Protection Agency
    ((JSEPA)
    for the discharge of ash
    pond systems.
    (Exh.
    #1, p.
    13;
    R.
    103).
    The Illinois Environmental Protection Agency
    (Agency)
    recommends
    that
    Cli’s be granted relief only to the extent
    of
    a
    25
    mg/i limit for
    the 30—day average and 40 mg/i limit
    for the daily
    maximum.
    The Agency asserts that the past performance levels of
    CIPS justifies only this level
    of relief.
    (Agency Brief,
    p.
    10).
    Anti—Backsliding
    Provision
    Both CIPS and the Agency were requested
    to address,
    in their
    briefs,
    how the requested relief related
    to Section 402(o)
    of the
    Clean Water Act, as amended
    by Pub.
    L.
    No.
    100—4.
    This Section
    is entitled “Anti—Backsliding.”
    In general, the Section
    prohibits
    the renewal
    of
    a permit
    if the effluent limits
    contained
    in that renewed permit are less stringent than the
    original
    permit.
    CuPS
    initially
    claims
    that
    the
    anti—backsliding
    provision
    is
    inapplicable
    to
    the situation
    at hand.
    CI’S asserts that the
    provision only applies to effluent standards based on “best
    professional
    judgment” and water quality based limitations.
    According
    to CuPS,
    the Section does not preclude backsliding for
    technology—based limits which
    is
    the issue
    in this proceeding.
    In addition,
    it
    is CIPS’
    position that
    the anti—backsliding
    amendment only applies
    to water quality standards or
    schedule of
    compliance.
    Finally, CuPS states that even
    if the anti—backsliding
    provision
    is applicable,
    Cli’s’
    ash pond system falls
    under two
    expressed exceptions
    to the provision.
    One exception allows less
    stringent limitations
    if such limitations are necessary due
    to
    circumstances beyond
    the permittees control and for when
    there
    is
    no
    reasonably available remedy.
    The other exception encompasses
    the situation where a permittee has installed and properly
    operated treatment
    facilities required
    to meet the original
    permit’s limits and yet the permittee
    is unable to deliver
    compliance.
    CIPS concludes that
    its situation fits both these
    exceptions.
    (CuPS’ Brief,
    p.
    3—7).
    The Agency states that the latter exception, discussed
    above,
    would likely apply.
    This exception also provides that
    a
    new permit contain limits which reflect
    the level
    of pollutant
    control “actually achieved.”
    (Agency Brief,
    p.
    9).
    In its Reply Brief, CIPS takes
    the position that the Board
    should not concern itself with
    the anti—backsliding
    issue.
    87—282

    5
    IEPA
    as
    the
    permitting
    authority
    and
    USEPA
    under
    its enforcement
    authority
    of
    the NPDES
    National
    Pollutant
    Discharge
    Elimination
    System
    program,
    not
    the
    Board,
    are
    the
    proper
    authorities
    for
    determining
    if
    a
    revised permit can be
    issued.
    *
    *
    *
    The
    question
    of
    whether
    the
    anti—
    backsliding provision
    is applicable should be
    resolved
    as
    a
    permitting,
    not
    a
    rulemaking,
    function.
    (CIPS Reply,
    p.
    11).
    The Board
    will not adopt
    rules which it believes
    are
    contrary
    to Federal law or
    regulations that the State
    administers.
    In this matter,
    the Board agrees with
    the
    participants that granting relief will not constitute
    backsliding.
    Findings
    The
    Board
    notes
    that
    considerable
    time
    was
    spent
    at
    hearing
    trying
    to clearly define the location or
    configuration
    of
    various
    structures and
    items under discussion.
    The exhibits such as
    Exhibit #1, Attachment A which showed the entire lake and plant
    area, would have been much more useful
    if items such as the
    ponds,
    intakes,
    and discharge points had been indicated.
    Although there are technically feasible methods
    for
    compliance by utilizing treatment alternatives other than the ash
    pond system,
    such treatment appears
    to be economically
    unreasonable
    in light of the nature and impact of the
    discharge.
    It also appears that no modification
    of the current
    ash pond system would significantly reduce the fixed
    solids
    portion of CIPS’
    TSS discharge.
    Given
    the current levels of TSS
    in CIPS’
    discharge,
    the use of toxicants
    to kill fish or
    algicides
    to kill
    algae
    in the ponds would pose environmental
    risks
    to Newton Lake which are greater
    than any negative impact
    associated with CIPS’
    current TSS discharge.
    At hearing, the attending Board Member asked whether CIPS
    would
    be amenable
    to regulating
    the fixed solids portion of the
    TSS apart
    from the TVSS portion.
    In its brief, CIPS states that
    “application of the current
    Board limits,
    15 mg/i and 30 mg/i,
    just
    to
    the fixed portion of the TSS
    in
    the effluent also has
    support
    in the record and certainly is
    an acceptable alternative
    to CIPS.”
    (CuPS Brief,
    p.
    12).
    In response, the Agency states:
    87—283

    6
    The
    suggested
    bifurcation
    of
    TSS
    into
    volatile
    and
    fixed
    portions
    is
    unprecedented
    in
    the
    Board’s
    regulations.
    There
    is
    no
    compelling
    reason
    in
    the present
    case
    to do
    so
    even
    though the volatile
    portion
    is
    known
    to
    be
    primarily
    algal
    and
    does
    not
    appear
    to
    hve
    an
    adverse
    impact
    upon
    Newton
    Lake.
    Further, because
    still higher levels of algae
    could
    prove
    detrimental
    to
    the
    lake,
    the
    volatile
    portion
    of
    TSS would
    still
    need
    to
    be
    regulated
    in
    some
    fashion.
    The record
    in
    this matter
    is not sufficient
    to address this
    issue.
    (Agency Brief,
    p.
    5)
    The Board is reluctant
    to grant TSS levels of 25/40
    as
    suggested
    by the Agency.
    This could
    lead
    to
    a situation where
    fixed solids exceed 15 mg/i.
    Presently,
    CIPS’
    discharge of
    fixed
    solids generally meets the current
    limit of
    15 mg/l.
    Relief
    which
    ignores
    the composition of
    the TSS discharge could allow
    CIPS to produce
    an effluent which has greater
    ash content when
    compared
    to its present discharge.
    The ash pond system
    is
    designed
    to remove ash; the record does not support amending
    regulations
    in any way which would accept decreased efficiency of
    ash removal.
    There has already been
    a major change
    in
    the ash
    loading
    to the ponds.
    It is impossible
    to predict
    the nature of
    future discharges.
    The CIPS witness did, however,
    state
    that
    if
    relief
    is granted, CIPS would continue
    to manage
    the ponds to
    minimize TSS.
    (R.
    29).
    It
    is evident
    in the record
    that the type and amount of
    algae presently discharged by CIPS has
    no apparent deleterious
    effect on Newton Lake.
    Also,
    the Board
    notes that the ash pond——
    Newton Lake system is essentially
    a closed
    loop.
    The lake
    discharges only intermittently
    to Weather Creek.
    (R.
    110).
    Although the algal discharge
    is not presently harmful due
    to its
    type and quantity,
    the Board
    agrees with the Agency that the
    algal portion should not go unregulated.
    The Board believes that
    the record supports granting some relief from TSS caused
    by
    algae.
    A level of
    30/50
    is supported by the data
    in the record
    as
    consistent
    with
    current
    performance
    of
    the
    ponds
    with
    a
    reasonable
    amount
    of
    leeway
    given
    the
    unpredictable
    nature
    of
    algal
    blooms.
    Given
    the
    unique
    circumstances
    of
    this
    situation,
    the
    Board
    will propose relief such that CIP’s TSS discharge shall
    not
    exceed
    30 mg/i monthly average or
    50 mg/l daily composite.
    The
    definitions
    of Section 304.104(b)
    shall apply
    to these
    limits.
    Also,
    the Board will impose
    the requirement that the non—volatile
    portion
    of
    the
    TSS
    not
    exceed
    15
    mg/i
    monthly
    average
    and
    30
    mg/l
    daily composite.
    In granting
    this relief,
    the Board notes that
    the volatile fraction of TSS
    in many discharges can be
    87—284

    7
    environmentally
    harmful.
    The
    30/50
    TSS
    levels
    specified
    in
    this
    rule
    are
    intended
    to
    include
    both
    the
    fixed
    and
    volatile
    fractions.
    The
    Board
    granted
    Illinois
    Power Company’s Wood
    River
    Station TSS limits of 30/50
    in
    1985.
    In
    the Matter of: Proposal
    of
    the Illinois Power Company for
    a Site—Specific Effluent Rule
    Change
    (Proposed Amendment
    to
    Ill. Adm.
    Code, Title 35,
    Part
    304,
    Subpart
    B), R.
    83—lI,
    63 PCB
    118,
    (February 20,
    1985).
    That
    matter
    involved
    a relatively new ash pond with
    a retention time
    of
    67
    days.
    The Board denied TSS relief to
    the Central Illinois Light
    Company’s
    (CILCO)
    E.D.
    Edward’s
    Station South of Peoria
    in 1986.
    In the Matter
    of:
    Site Specific Rulemaking
    for Central Illinois
    Light Company, R85—7,
    72 PCB 369 (September
    11,
    1986), aff’d
    Central
    Illinois Light Company
    v.
    Ill.
    Pollution Control Board,
    Ill.
    App.
    3d.
    _____,
    _______
    N.E.2d
    ______
    (3rd
    Dist.
    1987)
    citation
    will be supplied later
    In that proceeding,
    an older pond with
    a retention
    time of
    90 hours exceeded the TSS standard.
    The Board denied
    the
    petition for
    a number of reasons including
    failure
    to demonstrate
    that
    the
    excess
    TSS
    were
    not
    environmentally
    harmful.
    CILCO
    also
    failed
    to adequetely address why the pond had previously met the
    standard,
    to support
    its contention
    that influent solids were
    a
    major contribution
    to the violstion,
    to refute the Agency’s
    contention
    that the pond had filled
    with sediment
    to the point
    that
    it did not provide
    the necessary settling opportunity, and
    to demonstrate that compliance was technically infeasible
    or
    economically unreasonable.
    The Board believes its decision today is in concert with
    prior decisions
    in this area.
    CI’S has
    a relatively new pond
    with
    a more than adequate retention
    time.
    Based
    on experience,
    CIPS manages
    the pond
    to minimize
    algae and inorganic
    particles.
    The Company had adequately characterized
    the influent
    and effluent water
    and determined where
    the problems exist.
    The
    Board
    is convinced
    that given
    the current situations,
    it
    is
    technically
    feasible but economically unreasonable
    to implement
    further capital—intensive controls.
    The proposed rule will not
    allow
    an increase
    in fixed TSS,
    but will give CIPS reasonable
    relief from
    its algae problem.
    87—285

    8
    ORDER
    The Board hereby proposes for First Notice the following
    amendment
    to
    be
    published
    in
    the
    Illinois
    Register.
    TITLE
    35:
    ENVIRONMENTAL PROTECTION
    SUBTITLE
    C:
    WATER
    POLLUTION
    CHAPTER
    I:
    POLLUTION CONTROL BOARD
    PART 304
    EFFLUENT STANDARDS
    SUBPART
    B:
    SITE SPECIFIC RULES
    AND EXCEPTIONS NOT OF GENERAL APPLICABILITY
    Section
    304.216
    Newton
    Station
    Suspended
    Solids
    Discharges
    The limitation on the discharge of
    total suspended solids (TSS)
    contained
    in
    Section
    304.124(a)
    does
    not
    apply
    to
    the
    discharge
    from
    the
    ash
    pond
    system
    of
    Central
    Illinois
    Public
    Service
    Company’s
    Newton
    Station
    (CIPS),
    located
    in
    Jasper
    County.
    Instead,
    CIPS’
    ash
    pond
    system
    discharge
    shall
    not
    exceed
    30
    mg/i
    monthly
    average
    and
    50
    mg/l
    daily
    composite
    for
    TSS,
    and
    15
    mg/i
    monthly
    average
    and
    30
    mg/i
    daily
    composite
    for
    non—volatile
    TSS.
    The definitions of
    Section 304.104(b)
    apply to these
    effluent
    limits.
    (Source:
    12
    Iii.
    Reg.
    ,
    effective
    IT
    IS
    SO
    ORDERED.
    I,
    Dorothy
    M.
    Gunn,
    Clerk
    of
    the
    Illinois
    Pollution
    Control
    Board,
    hereby
    certify
    that
    the
    above
    Proposed
    Opinion
    and
    Order
    was
    adopted
    on
    the
    ~
    day
    of
    ~77?a.-t_~?_’
    ,
    1988,
    by a
    vote
    of
    ~I..—O
    Dorothy
    M.
    Gunri,
    Clerk
    Illinois Pollution Control Board
    87—286

    Back to top